Planning and Development Committee

 

Agenda

 

7 July 2020

 

 

Notice is hereby given, in accordance with the provisions of the Local Government Act 1993 that a Planning and Development Committee meeting of ORANGE CITY COUNCIL will be held in the Via online video conferencing platform zoom, Orange on Tuesday, 7 July 2020.

 

 

David Waddell

Chief Executive Officer

 

For apologies please contact Administration on 6393 8218.

  

 


Planning and Development Committee                                                         7 July 2020

Agenda

  

1                Introduction.. 3

1.1            Declaration of pecuniary interests, significant non-pecuniary interests and less than significant non-pecuniary interests. 3

2                General Reports. 5

2.1            Items Approved Under the Delegated Authority of Council 5

2.2            Development Application DA 234/2018(1) - 129-133 Sale Street (Caldwell House) 11

2.3            Development Application DA 120/2020(1) - 52-54 Bathurst Road, and 25 and 27 Eyles Street (Taco Bell) 117

 


Planning and Development Committee                                                         7 July 2020

1       Introduction

1.1     Declaration of pecuniary interests, significant non-pecuniary interests and less than significant non-pecuniary interests

The provisions of Chapter 14 of the Local Government Act, 1993 (the Act) regulate the way in which Councillors and designated staff of Council conduct themselves to ensure that there is no conflict between their private interests and their public role.

The Act prescribes that where a member of Council (or a Committee of Council) has a direct or indirect financial (pecuniary) interest in a matter to be considered at a meeting of the Council (or Committee), that interest must be disclosed as soon as practicable after the start of the meeting and the reasons given for declaring such interest.

As members are aware, the provisions of the Local Government Act restrict any member who has declared a pecuniary interest in any matter from participating in the discussion or voting on that matter, and requires that member to vacate the Chamber.

Council’s Code of Conduct provides that if members have a non-pecuniary conflict of interest, the nature of the conflict must be disclosed. The Code of Conduct also provides for a number of ways in which a member may manage non pecuniary conflicts of interest.

Recommendation

It is recommended that Committee Members now disclose any conflicts of interest in matters under consideration by the Planning and Development Committee at this meeting.

 


Planning and Development Committee                                                        7 July 2020

 

 

2       General Reports

2.1     Items Approved Under the Delegated Authority of Council

RECORD NUMBER:       2020/866

AUTHOR:                       Paul Johnston, Manager Development Assessments    

 

 

EXECUTIVE Summary

Following is a list of more significant development applications approved by the Chief Executive Officer under the delegated authority of Council.  Not included in this list are residential scale development applications that have also been determined by staff under the delegated authority of Council.

Since the June PDC Meeting report periods (21 May to 25 June), a combined total of 50 Development Applications have been determined under delegation (CEO and staff) with a combined value of $9,651,365.

Link To Delivery/OPerational Plan

The recommendation in this report relates to the Delivery/Operational Plan strategy “7.1 Preserve - Engage with the community to develop plans for growth and development that value the local environment”.

Financial Implications

Nil

Policy and Governance Implications

Nil

 

Recommendation

That Council resolves to acknowledge the information provided in the report by the Manager Development Assessments on Items Approved Under the Delegated Authority of Council.

 

further considerations

Consideration has been given to the recommendation’s impact on Council’s service delivery; image and reputation; political; environmental; health and safety; employees; stakeholders and project management; and no further implications or risks have been identified.

 

Reference:

DA 130/2007(2)

Determination Date

9 June 2020

PR Number

PR13267

Applicant/s:

Mandagery Constructions

Owner/s:

Mr GC Barrett

Location:

Lot 40 DP 810916 - 99 Bathurst Road, Orange

Lot 41 DP 810916 – 101 Bathurst Road, Orange

Proposal:

Modification of development consent - demolition (existing shed), residential units and subdivision. The modified development involves minor changes to approved Units 6 and 7 (within the converted dwelling house); and provision of two additional onsite car parking spaces at the site frontage within common property.

Value:

Not applicable

 

Reference:

DA  367/2008(2)

Determination Date

19 June 2020

PR Number

PR28460

Applicant/s:

Mr MA and Mrs BM Crombie

Owner/s:

Mr MA and Mrs BM Crombie

Location:

Lot 100 DP 1257871- 5A Ploughmans Lane, Orange

Proposal:

Modification of development consent - demolition (existing building) and outbuilding (new construction). The modification application seeks approval to regularise the unauthorised works.

Value:

Not applicable

 

Reference:

DA 101/2016(3)

Determination Date

19 June 2020

PR Number

PR2313

Applicant/s:

Mrs BJ  Maurice and Mr CA and Mrs CE Bailey

Owner/s:

Mr CA and Mrs CE Bailey

Location:

Lots 1 and 2 DP 715252 – 1 and 3 Carwoola Drive, Orange

Proposal:

Modification of development consent - subdivision (21 lot residential). The modified proposal will modify Condition 29 of the development consent. This will remove the requirement to construct the concrete footpath along Cargo Road. A concrete footpath has already been constructed along the southern side of Cargo Road.

Value:

Not applicable

 

Reference:

DA 364/2017(3)

Determination Date

25 May 2020

PR Number

PR8325

Applicant/s:

Mr JA Vandenberg

Owner/s:

Amberlend Pty Limited

Location:

Lot 4 DP 233405 - 45-47 McNamara Street, Orange

Proposal:

Modification of development consent - small bar. The modification involves an extension to approved weekend trading hours. A 1am closure is now proposed on Friday and Saturday nights, being an extension to trade of 1 hour per night.

Value:

Not applicable

 

Reference:

DA 417/2017(2)

Determination Date

3 June 2020

PR Number

PR8327

Applicant/s:

Ryan Stewart

Owner/s:

Mr RJ Stewart

Location:

Lot 1 DP 91037, 72 McNamara Street, Orange

Proposal:

Modification of development consent - office premises (alterations and additions to existing building). The modified proposal seeks minor changes to the internal layout of the building as well as changes to the external façade in relation to window and door openings.

Value:

Not applicable

 


 

 

Reference:

DA 411/2018(1)

Determination Date

18 June 2020

PR Number

PR4533

Applicant/s:

Zhang Building and Development Pty Ltd

Owner/s:

Zhang Building and Development Pty Ltd

Location:

Lot 22 DP 522405 - 101 Gardiner Road, Orange

Proposal:

Demolition (existing dwelling, ancillary structures, vegetation), multi dwelling housing (six dwellings), subdivision (four lot residential Torrens Title) subdivision (four lot residential Community Title)

Value:

$800,000

 

Reference:

DA 326/2019(1)

Determination Date

16 June 2020

PR Number

PR13267

Applicant/s:

Mandagery Constructions

Owner/s:

Mr GC Barrett

Location:

Lot 40 DP 810916 – 99 Bathurst Road and

Lot 41 DP 810916 – 101 Bathurst Road

Lot 30 DP 1190518 – 59-67 Bathurst Road

Proposal:

Consolidation (Lots 40 and 41 DP 810916) , multi dwelling housing (three units) and subdivision (four lot Strata)

Value:

$500,000

 

Reference:

DA 406/2019(2)

Determination Date

28 May 2020

PR Number

PR19434

Applicant/s:

Adam Grant Constructions Pty Ltd

Owner/s:

Mrs F Grant

Location:

Lot 105 DP 1067744 - 259 Clergate Road, Orange

Proposal:

Modification of development consent - general industry (16 industrial units) and subdivision (17 lot Strata title). The modified proposal seeks to form a 17 lot Strata Title subdivision, where the approved development was for a 17 lot Community Title subdivision.

Value:

Not applicable

 

Reference:

DA 16/2020(2)

Determination Date

12 June 2020

PR Number

PR25385

Applicant/s:

Canobolas Hotel Pty Ltd

Owner/s:

Hotel Canobolas Pty Limited

Location:

Lot 18 SP 82891 - 18/266 Summer Street, Orange

Proposal:

Modification of development consent - pub (internal alterations). The modified proposal involves reconfiguration of spaces at ground level, and part louvered infill to existing windows on the Lords Place western façade.

Value:

Not applicable

 


 

 

Reference:

DA 29/2020(1)

Determination Date

25 June 2020

PR Number

PR9676

Applicant/s:

Mad Hatter Beverage Co Pty Ltd

Owner/s:

Mr MR Hardman

Location:

Lot 1 DP 779074 - 137-139 Peisley Street, Orange

Proposal:

Artisan food and drink industry

Value:

$35,000

 

Reference:

DA 52/2020(1)

Determination Date

1 June 2020

PR Number

PR2631

Applicant/s:

Mr D Farr

Owner/s:

Mr RJ and Mrs DM Barnes

Location:

Lot 6 DP 362829 - 148 Clergate Road, Orange

Proposal:

Dwelling house and depot (ancillary office (former dwelling) and industrial shed)

Value:

$650,000

 

Reference:

DA 93/2020(2)

Determination Date

28 May 2020

PR Number

PR28396

Applicant/s:

Hibbards Pty Ltd

Owner/s:

Hibbards Pty Ltd

Location:

Lot 5 DP 1255866 - 8 Catherine Place, Orange

Proposal:

Modification of development consent - dual occupancy and subdivision (two lot residential). It is proposed to modify the consent, specifically Stage 2 of the approved development, to effect a strata subdivision of the attached dual occupancy. The approved development was for a Torrens lot subdivision of the dual occupancy. The lot sizes will be altered very slightly, Lot 1 is proposed at 410.4m2 (approved 410.3m2), and Lot 2 is proposed at 568.5m2 (approved 568.6m2).

Value:

Not applicable

 

Reference:

DA 96/2020(1)

Determination Date

19 May 2020

PR Number

PR24012

Applicant/s:

Mr J Benson

Owner/s:

J & M Benson Properties Pty Ltd

Location:

Lot 17 DP 1147595 - 13 Scott Place, Orange

Proposal:

Depot

Value:

$60,000

 

Reference:

DA 130/2020(1)

Determination Date

 

PR Number

PR27838

Applicant/s:

Peter Basha Planning and Development

Owner/s:

Hibbards Pty Ltd

Location:

Lot 527 DP1233683, 25 Young Street, Orange

Proposal:

Dual occupancy (attached) and subdivision (two lot strata)

Value:

$420,000


 

 

Reference:

DA 132/2020(1)

Determination Date

27 May 2020

PR Number

PR8422

Applicant/s:

Designs@M

Owner/s:

Ms NL Fogarty

Location:

Lot 7 DP 259055 - 14 Mitchell Parade, Orange

Proposal:

Dwelling additions and secondary dwelling

Value:

$120,000

 

 

Reference:

DA 134/2020(1)

Determination Date

5 June 2020

PR Number

PR26308

Applicant/s:

Kinross Wolaroi School

Owner/s:

The Uniting Church in Australia Property Trust (NSW)

Location:

Lot 30 DP 1190518 - 59-67 Bathurst Road, Orange

Proposal:

School (new metalwork building) and demolition (shed and tree removal)

Value:

$2,500,000

 

 

Reference:

DA 159/2020(1)

Determination Date

16 June 2020

PR Number

PR1725

Applicant/s:

David Carey Town Planning and Development

Owner/s:

Mr JD Burns

Location:

Lot 1 DP 215365 - 6 Breen Street, Orange

Proposal:

Secondary dwelling (conversion from outbuilding) and carport

Value:

$14,000

 

 

Reference:

DA 165/2020(1)

Determination Date

19 June 2020

PR Number

PR28460

Applicant/s:

Mr MA and Mrs BM Crombie

Owner/s:

Mr MA and Mrs BM Crombie

Location:

Lot 100 DP 1257871 - 5A Ploughmans Lane, Orange

Proposal:

Change of Use of part of the existing outbuilding to secondary dwelling

Value:

$10,000

 

 

Reference:

DA 182/2020(1)

Determination Date

9 June 2020

PR Number

PR11517

Applicant/s:

McPickelway Properties Orange Pty Ltd

Owner/s:

Ms V Kourtis and Mrs M Pertsoulis

Location:

Lot 10 DP 203590, Lot 351 DP 625439 –

249 and 251-257 Summer Street, Orange

Proposal:

Pub (alterations and additions and change of use)

Value:

$25,000

 


 

 

Reference:

DA 199/2020(1)

Determination Date

22 June 2020

PR Number

PR7529

Applicant/s:

Orange City Council

Owner/s:

Orange City Council

Location:

Lots 1 and 2 DP 526194 - March Street, Orange

Proposal:

Recreation area (demolition and earthworks)

Value:

$20,000

 

 

Reference:

DA 205/2020(1)

Determination Date

11 June 2020

PR Number

PR27675

Applicant/s:

Sandy June Pty Ltd

Owner/s:

Sandy June Pty Ltd

Location:

Lot 110 DP 1229500 - 48 Molong Road , Orange

Proposal:

Fencing (replacement of front boundary fence)

Value:

$3,500

 

 

TOTAL NET* VALUE OF DEVELOPMENTS APPROVED BY THE CEO UNDER DELEGATED AUTHORITY IN THIS PERIOD: $5,157,500.00

* Net value relates to the value of modifications. If modifications are the same value as the original DA, then nil is added. If there is a plus/minus difference, this difference is added or taken out.

Since the June PDC Meeting report periods (21 May to 25 June), a combined total of 50 Development Applications have been determined under delegation (CEO and staff) with a combined value of $9,651,365.

 

 

 

  


Planning and Development Committee                                                        7 July 2020

2.2     Development Application DA 234/2018(1) - 129-133 Sale Street (Caldwell House)

RECORD NUMBER:       2020/294

AUTHOR:                       Andrew Crump, Senior Planner    

 

 

EXECUTIVE Summary

Application lodged

4 July 2018

Applicant/s

Health Infrastructure on behalf of Health Administration Corporation

Owner/s

Health Administration Corporation

Land description

Lot 2 DP 1230592 - 129-133 Sale Street, Orange

Proposed land use

Demolition of a Heritage Item (all buildings, structures and vegetation to be removed) and Category 1 Remediation (asbestos removal)

Value of proposed development

$1,800,000.00 (as originally submitted)

$3,945,295.00 (revised application)

Council's consent is sought to demolish all buildings, structures and vegetation on the subject land, known as 129-133 Sale Street, Orange (refer Figure 1).

Figure 1 – locality plan

The subject land contains Caldwell House (former nurses quarters) and the more recent nurses quarters on the corner of Sale and Dalton Streets.

The buildings have been vacant for a number of years and have been neglected in more recent times. Over the course of the last decade or so the buildings have been subject to numerous break and enters, with perpetrators searching for copper wire and other materials of value left in the buildings upon them being vacated. In the process of illegally obtaining the copper wire and other material, friable asbestos has been disturbed and has been distributed throughout the buildings.


 

The applicant has presented a case purporting that the buildings would be unable to be occupied for future adaptive re-use as a result of asbestos contamination; or, in the event that the buildings could be successfully cleaned and encapsulated, the buildings would be subject to ongoing asbestos management plans, making the buildings undesirable to future occupants.

In addition to this, the applicant has suggested that the cost of remediating Caldwell House would be substantially more expensive than a full demolition option, resulting in any future adaptive re-use of the buildings being financially unviable.

The applicant is not contesting the heritage significance of Caldwell House – indicating that, if it were possible, they would prefer to see the building remain and be adaptively reused.

It is important to note that it is understood from the application that Health Infrastructure (NSW Health) have no intention of carryout the work, but are rather seeking consent for demolition so that the property can be divested and another party can carry out the work if so desired.

Council staff have scrutinised the claims presented within the application with the assistance of a contamination expert and a consultant engineer. Council’s experts were directed to focus their advice on the heritage significant Caldwell House as it is accepted by Council staff that the more recent nurse’s quarters (located in the north-eastern corner of the site) has only low levels of heritage significance.

The expert advice obtained by Council staff concluded that:

1.       Caldwell House could be successfully remediated and occupied under an ongoing asbestos management plan[1]. Council’s expert notes that the building is required to be cleaned under all the scenarios presented by the applicant.

2.       The building is structurally adequate to the extent that the necessary remediation steps suggested as being necessary by the applicant (such as lifting the floor, removing internal wall linings etc) could be safely undertaken.

It should be noted that one of the submissions from Adaptive Architects offers a methodology for cleaning and encapsulating that meets heritage conservation principles. Such a methodology would need to be fully resolved when Caldwell House is remediated.

3.       Retention of Caldwell House would be approximately 33% more expensive than the complete demolition option. Noting that the additional cost purported by the application does not factor in the cost of a complete re-development of the site incorporating an adaptive re-use of Caldwell House.

It is important to reiterate, that under all possible scenarios, the asbestos must be removed from the building prior to it being demolished or adaptively re-used as required by Clause 452 of the Work Health and Safety Regulation 2017 and the Safe Work Australia‘s Demolition Code of Practice. In other words, the building needs to be cleaned of asbestos or asbestos-containing material in any case.


 

It is also important to note that at the moment, the land with the significant heritage building still retained on the land, benefits from Council’s generous incentives clause within the LEP. This clause effectively allows an impermissible use on the land such as offices or retail; or even a pub for instance provided that Council can be satisfied amongst other things that conservation of the heritage item was facilitated by the granting of a consent and that any proposal was in accordance with a heritage management document approved by the consent authority. Should it be agreed that the building can be demolished, the ability to rely on this clause evaporates.

The economic arguments presented within the application and discussed in detail below within the report, fail to account for this. That is, the demolition of Caldwell House would have a far greater negative impact on the value of the land than if the building was retained and the highest and best use sought for the land.

DECISION FRAMEWORK

Development in the Orange LGA is governed by The Environmental Planning and Assessment Act 1979 and the accompanying Environmental Planning and Assessment Regulations 2008. Sitting below the Act and Regulations is the Orange LEP 2011 and other State wide Environmental Planning Instruments (SEPP). Subordinate to the LEP and SEPPs is the Orange Development Control Plan 2004 which is a guiding document used to inform decision making. In addition the Infill Guidelines are used to guide development, particularly in the heritage conservation areas and around heritage items.

Orange Local Environment Plan 2011 – The provisions of the LEP must be considered by the Council in determining the application. LEPs govern the types of development that are permissible or prohibited in different parts of the City and also provide some assessment criteria in specific circumstances. Uses are either permissible or not. The objectives of each zoning and indeed the aims of the LEP itself are also to be considered and can be used to guide decision making around appropriateness of development.

Orange Development Control Plan 2004 – the DCP provides guidelines for development. In general it is a performance based document rather than prescriptive in nature. For each planning element there are often guidelines used. These guidelines indicate ways of achieving the planning outcomes. It is thus recognised that there may also be other solutions of merit. All design solutions are considered on merit by planning and building staff. Applications should clearly demonstrate how the planning outcomes are being met where alternative design solutions are proposed. The DCP enables developers and architects to use design to achieve the planning outcomes in alternative ways.

DIRECTOR’S COMMENT

This application relates to the heritage item “Caldwell House” and the associated nurse’s quarters. 

The applicant has presented a number of reasons to support their intent to demolish the buildings on the land which have been scrutinised in detail by Council’s consultants and planning staff. The justification presented by the applicant is considered to be based on flawed logic; and accordingly is not supported by staff.

Due to the technicalities of this proposal in terms of heritage, demolition and remediation, staff engaged independent experts to provide practical advice regarding the application.  Council’s experts suggest that the buildings can be saved and adequately remediated.  This advice is at odds with the claims of the applicant’s experts.  Whilst the applicant offered to have the consultants meet to debate the conclusions of both sides, this offer was not taken up as the Council experts suggested such meetings generally are not fruitful.

It is extremely disappointing that the buildings on this site, as significant to the community as they are, have been left by the owners to become accessible to vandals and as a result, dilapidated.

This DA is a Crown Development, therefore Council cannot determine the application without the concurrence of the Applicant or Minister. This process would follow Council’s advice on how it would like to progress this application. Council cannot refuse the application (it would have to be referred to the Western Regional Planning Panel).

Ten submissions were received from residents and community groups relating to this proposal.  A small number (2) supported the proposal, whilst the majority oppose the application due mostly to the loss of a significant heritage item. 

Staff recommend that demolition only be permitted of the later nurse’s quarters and other less-significant buildings on the land, not of Caldwell House itself. 

I support the recommendations within the report.

Link To Delivery/OPerational Plan

The recommendation in this report relates to the Delivery/Operational Plan strategy “10.1 Preserve - Engage with the community to ensure plans for growth and development are respectful of our heritage”.

Financial Implications

Nil

Policy and Governance Implications

Nil

 

Recommendation

With respect to development application DA 234/2018(1) for Demolition of a Heritage Item (all buildings, structures and vegetation to be removed) and Category 1 Remediation (asbestos removal) at Lot 2 DP 1230592 - 129-133 Sale Street, Orange it is recommended that Council:

1        Note the contents of the planning report and the recommendations therein.

2        Accept the terms of the draft notice of determination.

3        Direct Council staff to obtain the concurrence of either the applicant or the Minister as required by Section 4.33 of the Environmental Planning and Assessment Act.

4        That Council delegate the authority to determine Development Application DA 234/208(1) to the Chief Executive Officer subject to the receipt of concurrence from the Crown.

 

further considerations

Consideration has been given to the recommendation’s impact on Council’s service delivery; image and reputation; political; environmental; health and safety; employees; stakeholders and project management; and no further implications or risks have been identified.

 

SUPPORTING INFORMATION

THE LAND

The land is a large residentially zoned parcel of land to west of the former base hospital site. The land is described as Lot 2 DP 1230592, known as 129-133 Sale Street, Orange. The land is identified as a Local heritage item as it contains Caldwell House (former nurses quarters). The site also contains the more recent former nurses quarters on the north-eastern corner of the site.

The land is located on the (south-western) corner of the Dalton and Sale Streets intersection. The land adjoining to the west is residentially zoned and contains a single storey dwelling house. To the south of the land, part of the southern boundary shares a boundary with a former dwelling that been converted into health consulting rooms, and then a number of residential properties adjoin for the balance of the southern boundary.

The land across from Caldwell House is the former Orange Base Hospital site which is now three separate lots; the lot closest to the subject land is vacant, while the adjoining lot to the east comprises the partially constructed office building that will house the Department of Industries, and the third lot comprises the former ambulance station.

THE APPLICATION/PROPOSAL

Council's consent is sought to demolish all buildings, structures and vegetation on land described as Lot 2 DP 1230592, known as 129-133 Sale Street, Orange. As part of the demolition, the site would be remediated and made good for future development.


 

BACKGROUND

The subject land contains two primary buildings (Caldwell House and the later former nurse’s quarters). It is accepted by Council staff that the later constructed former nurses quarters holds limited heritage significance, and therefore the proposal to demolish that particular building is accepted by Council staff and relevant conditions of consent are attached addressing the asbestos clean-up and other measures such as the control of dust and noise.

The other building on the land, Caldwell House, has been vacant since c2011. This is around the time the hospital moved to the Bloomfield Campus; at this time Community Health (the most recent occupants of the building) moved to the new hospital also.

The applicant advises that in:

June 2016 an EOI sales campaign for the site culminated in a commercial offer from a developer of aged care. The offer was accepted subject to Health Administration Corporation’s (HAC) registration of a subdivision and the approval of the developer’s DA for that aged care facility.

In late 2016 and again in mid-2017, whilst in final negotiations, there was forced entry, theft and a vandalism attack on the buildings, resulting in significant damage. The vandalism involved the forced removal of copper pipes and wiring. This has caused damage to ceilings and lagging which has resulted in asbestos being dispersed throughout the buildings.

 

CHRONOLOGY OF APPLICATION

The application was originally lodged on 4 July 2018. Shortly after receipt of the application, Council exhibited the material and engaged relevant experts.

Additional information was requested on 25 September 2018 which requested a revised Heritage Impact Statement (HIS) that provided a more detailed analysis of options and also provided heritage significance mapping. Council expert advice was provided along with the submission received.

Additional information was received 19 August 2019. The additional information purported that the extent of asbestos contamination was underestimated in the original application and that the cost of all options presented originally would be significantly more expensive than first suggested - in the order of approximately double the cost. Further asbestos audits were undertaken, a revised HIS was provided and additional expert advice was presented from Dr Ian Gardiner.

The revised material, along with the original material, was publicly exhibited on 30 September 2019 for a period of in excess of 30 days.

OPTIONS ANALYSIS

The applicant provides the following options analysis of a range of possible scenarios for the use of the site. The options include:

1        Asbestos remediation and clean-up; and complete demolition of all buildings, structures and vegetation (this is the applicant’s preferred option).

2        Asbestos remediation and clean-up; with retention of front facade (and section of return side walls) of Caldwell House only.

3        Asbestos remediation and clean-up; demolition of later nurses quarters and ancillary structures, retention of main Caldwell House as shown red below labelled “B”.

A picture containing table, green, cake, cutting

Description automatically generated

Figure 2 - extract from HIS – heritage significance mapping (B represents High Heritage Significance, C represents Moderate Heritage Significance and D represents Low Heritage Significance)

 

DEMOLITION METHODOLOGY

The applicant submits that the demolition will occur as follows:

Stage 1 – Site Establishment

·    Site facilities to be located in the western side of the site.

·    Provide security fencing around the site perimeter and manage the site against unauthorised entry.

·    Provide an access and egress route, connecting all undemolished floors to the nearest street and identify it as an emergency exit.

Stage 2 – Removal of Hazardous Substances

·    Prior to any stripping out or demolition, remove hazardous substances as outlined in the Hazard Material Survey by Envirowest Consulting (refer Annexure D).

·    Prior to any stripping out or demolition, remove asbestos or materials containing asbestos in accordance with Asbestos Removal Control Plan by Envirowest Consulting (refer Annexure C).

Stage 3 – Removal of Single Storey Structures

·    Use 1.8m high temporary fencing panels with appropriate signage to establish an exclusion zone around the immediate work area in accordance with AS 2601.

·    Disconnect services at each building.

·    Manually remove salvageable material.

·    Remove miscellaneous ground structures (light poles, signs etc).

·    Use 25-tonne excavator with grab attachment to pull down structures.

·    Wet down work face continually to minimise potential impact of raised dust within the site and upon adjoining properties.

·    Sort and stockpile materials for recycling.

·    Concrete/masonry waste may be crushed onsite or removed off-site for recycling  

·    Scrap metal stored and for removal from site.

·    Clean up Stage 3 work area before commencing the removal of the multi storey buildings.

Stage 4 – Removal of Multi Storey Buildings

·    Demolish Caldwell House first to allow greater access to the three-storey Nurses Accommodation building.

·    Establish an exclusion zone around the immediate work area in accordance with AS 2601.

·    Disconnect services at each building.

·    Manually remove salvageable material.

·    Remove miscellaneous ground structures (light poles, signs etc).

·    Use 38-47 tonne excavator with grab attachment to pull down Caldwell House. A hammer attachment will likely be required for the demolition of the suspended first floor slab. The work face should be sprayed continuously during the demolition to minimise and dust being generated that may affect the subject site and adjoining properties. It is anticipated that demolition work will commence at the western end of Caldwell House and progress towards the eastern, Sale Street end.

·    During the demolition works for Caldwell House, rubble should be progressively dropped to the ground by the excavator, and not stockpiled on the suspended concrete slab. Once rubble has been deposited on the ground, the area is to be made safe and the rubble moved to a designated stockpile area.

·    Clean up the Caldwell House work area before commencing the removal of the 3-storey Nurses Accommodation building.

·    Use 38-47 tonne excavator with grab attachment to pull down For the Nurses Accommodation building. Temporary work platforms constructed with compacted fill material may be required to be constructed along the southern side of the Nurses Accommodation Quarters to ensure that the entire structure can be safely demolished from the southern side of the building. A hammer attachment will likely be required for the demolition of the suspended first and second floor slabs. The work face should be sprayed continuously during the demolition to minimise and dust being generated that may affect the subject site and adjoining properties;

·    During the demolition works rubble should be progressively dropped to the ground by the excavator, and not stockpiled on the suspended concrete slabs. Once rubble has been deposited on the ground the area is to be made safe and the rubble moved to a designated stockpile area;

·    Once the above ground structure of the Nurse’s Quarters has been demolished work can then commence on the demolition of slabs on ground, foundations and concrete hardstands. The excavator, with hammer attachment should pulverize the concrete foundations and any adjacent hardstand;

·    Following the completion of demolition works on the multi storey buildings any remaining hardstand should be demolished by the excavator using conventional means;

·    Any recyclable materials should be separated from the demolition waste and stockpiled. Concrete and masonry may be crushed onsite or carted off-site for recycling;

·    Any scrap metal should be demolished and stored in a designated lay-down area for removal from site;

·    Once all buildings and structures have been demolished a general clean-up of the site should be completed, with the site generally levelled to approximate natural ground levels.

Stage 5 – Demobilisation of Site

·    Following the completion of all demolition, remediation works and site clearance the contractor shall be responsible for the removal of all plant equipment and rubbish generated throughout the demolition works. The site shall then be returned to the client upon completion of this stage.

·    Any certifications required by Council should be provided to the client during the final handover of the site. This is likely to include certification from the environmental consultant that all asbestos has been cleared from the site, and certification from a geotechnical consultant that any earthworks, particularly and backfill on basement areas, has been carried out in accordance with Australian Standard AS 3798 – Guidelines on earthworks for commercial and residential developments.

Stage 6 – Stabilisation of Site

The surface of the site is to be reasonably levelled and sown with appropriate grass seeds. Erosion and sediment controls should be placed as required.

Stage 7 – Final Handover

Following the completion of the Stage 6 works the site shall then be returned to the client. Any certifications required by Council should be provided to the client during the final handover of the site.

This is likely to include certification from the environmental consultant that all asbestos has been cleared from the site, and certification from a geotechnical consultant that any earthworks, particularly and backfill on basement areas, has been carried out in accordance with Australian Standard AS 3798 –Guidelines on earthworks for commercial and residential developments.

 

 

 

REMEDIATION COMPARISION

The submitted material by the applicant provides the following list of works that are suggested to be required to clean the site under either the demolition scenario and retain Caldwell House scenario:

 Roof space 

 

 Works required if Building Retained 

 

 Works required if Building Demolished 

·      Collect lagging and vacuum dust 

·      Remove all pipes, cables, other contents 

·      Remove roof tiles and clean and replace 

·      Vacuum all timber trusses and paint to encapsulate remaining fibres 

·      Remove original ceiling and suspended ceiling as contaminated waste 

·      Works undertaken to avoid damage to frame 

·      Remove residue in wall cavity as practical then drench with dilute paint to encapsulate fibres 

·      Manual labour including bagging of waste  for removal 

·      Collection of lagging 

·      Wet and seal all contents for later demolition 

·      Removal comprises combination of manual removal and machines 

 

 Ground and First Floor 

 

Works required if Building Retained

Works required if Building Demolished

·      Remove external pipes 

·       Collect lagging and vacuum asbestos residue dust 

·       Remove all asbestos material in walls, ceiling, doors 

·       Remove vinyl floor. Will require grinding of floor for complete removal 

·       Manual labour including bagging of waste  for removal 

·     Cleaning of all surfaces required after removal of asbestos contaminated waste 

·      Collection of lagging 

·       Remove all asbestos material in walls, ceiling, suspended ceiling 

·       Wet and seal all contents for later demolition 

·       Removal comprises combination of manual removal and machines 


 

 Sub floor Space

 

 Works required if Building Retained 

 

 Works required if Building Demolished 

·      Remove pipes and lagging residue 

·       Remove all cables and remaining pipes 

·       Alternative is to clean pipes and cables but this incurs higher labour charge 

·       Remove all other contents including vinyl floor 

·       All access to subfloor to be via existing access doors 

·       Limited working height to be considered 

·       All sub floor space requires covering with 50mm concrete slab to encapsulate residual asbestos on soil 

·       Manual labour including bagging of waste  for removal 

·      Collect pipes and lagging residue 

·       Wet and seal all contents for later demolition 

·       Removal comprises combination of manual removal and machines 

·       Excavation of 100mm of soil as asbestos waste 

 Clean Up 

 

 

Works required if Building Retained 

 

 

Works required if Building Demolished 

·      After removal of asbestos containing material cleaning would to be undertaken. The preferred method is washing to a collection area where the water is filtered before discharge.  

·       The final structure retains the concrete and brick with timber roof frame. 

·       Roof tiles will be replaced after cleaning. 

·       All remaining timber in the roof frame and sub floor space potentially contains asbestos and spraying with a dilute plastic paint is required for encapsulation. 

·     Treatment of the external wall cavity is required to seal asbestos lagging residue.   

·      After building demolition surface soil will be removed and transported to landfill as asbestos waste. 


 

 Waste and Traffic 

 

 Works required if Building Retained 

 

 Works required if Building Demolished 

·      Asbestos waste will require disposal at a landfill licenced to accept friable asbestos waste.  

·       Some asbestos cement material and vinyl may be removed as non-friable waste if not contaminated with lagging.  

·       The waste will be wrapped prior to transport.  

·       The quantity of waste has not been accurately determined however only asbestos contaminated waste will be removed and transported off-site. 

·      Asbestos waste will be removed from the building prior to demolition.  

·       Separate removal of asbestos will enable reuse or recycling of material not containing asbestos.  

·       Material with hard surfaces will be cleaned then classified as non-asbestos waste. 

·       Non-asbestos waste such as bricks and concrete will be crushed onsite and sold for reuse as fill. 

·       The demolition option will generate additional asbestos waste from all timber surfaces and soil excavations. 

·       The demolition option will produce asbestos and non-asbestos wastes. A demolition management plan will be prepared describing the process 

 

 Future Restrictions and Management 

 

 Works required if Building Retained 

 

 Works required if Building Demolished 

·      Asbestos cannot be completely removed from the building due to impact on porous surfaces and inaccessible location in voids. All timber in the roof and timber in sub floor space will remain and is impacted with asbestos fibres. Asbestos in the exterior wall cavity is also impacted with asbestos fibres. The asbestos on all timber surface and the wall cavities will be made safe by sealing with paint. 

·     Asbestos will also remain in the soil under the building after the removal works. Due to the nature of the asbestos in the soil it is unlikely it can be removed. The preferred make safe method of remediation is sealing with 50mm of concrete to encapsulate the asbestos residue. 

·      The site will need to be registered as contaminated land on the section 149 certificate for the land title deed. The land-use will be subject to implementation of a site management plan which restrict disturbance of the capping layer. The plan will need to be managed by the land owner and enforced by local council as a contaminated site. Restrictions will apply to retaining the building which has cost implications for redevelopment and ongoing maintenance. 

·      No restriction on the land–use following demolition and clearance by hygienist/environmental scientist. 


 

·       A site management plan will be required to be prepared for any works potentially breaching the encapsulation layers in the ceiling or sub floor space. The plan will recommend breaches to the encapsulated material are classified as friable asbestos works. Works on friable asbestos is required to be undertaken by a licensed asbestos removalist with SafeWork NSW class A licence. 

 Uncertainties 

 

It is possible unidentified asbestos is present in the building due to location in inaccessible areas or covered by renovations over time. Asbestos lagged pipes in the walls have not been identified however they may be present which will not be known until the area is disturbed. The location of unidentified asbestos will require management at the time of identification

 

It is important to note that a large amount of the identified disturbed material is assumed to be asbestos based on the submitted asbestos audits (testing has not been carried out to positively identify all material as asbestos – the audit relies mostly on visual inspection); and a large proportion of the identified asbestos is intact and not damaged. It is therefore possible that not all of the disturbed material is asbestos and the extent of contamination may be overstated by the applicant.

Further to the above; the Asbestos Removal Options report provides the below table which compares the removal factors for the scenarios of the building being retained and the building being demolished.

 Factor 

 

 Retain Building 

 Demolition 

Staff comment

Practical 

Yes (accessibility restrictions) 

Yes 

Noted – both options are practically possible.

Damage to building 

Floor requires grinding for vinyl floor removal 

All cable and pipes will require reinstallation 

Ceilings and walls will require replacement 

Possible accidental damage in removal process 

N/A 

The damage to the building could easily be managed through recognised conservation principles.

These have not been explored as part of the submitted Heritage Impact Statement.

Cost 

High 

Moderate 

33% additional cost for retention of Caldwell House is not considered exorbitant.

Particularly in consideration of how the building has been irresponsibly managed over the last decade.

Clean-up Time 

High 

Low 

Noted. This could have been dramatically reduced had the building been managed more responsibly. 

Asbestos retained onsite 

Yes (encapsulated to make safe) 

No 

This is easily managed through a site specific management plan. This is not uncommon for a building of this era.

Waste generated 

Asbestos 

Asbestos and non-asbestos 

NOTED. Retention of Caldwell House is far better for the environment and presents a much more sustainable option.

Transport 

Asbestos waste only 

Asbestos waste & non-asbestos waste for re-use material  

Noted. As with above, retention presents a much better outcome for the environment.

Reuse of materials 

No 

Crushed brick/concrete 

There is reuse of materials under the retention option as the build materials will remain as part of the building.

The above table does not clearly articulate the significant embodied energy[2] costs of the demolition scenario. The demolition scenario would have a far greater impact on the environment then the retention option through the additional embodied energy generated as a result of demolition of all buildings and redeveloping the site with all new buildings.

The embodied energy costs would be reduced significantly if only the later 1950s nurse’s quarters were to be demolished.

Thus, the full demolition option is fundamentally inconsistent with the objects of the Act, which seeks to:

 

facilitate ecologically sustainable development by integrating relevant economic, environmental and social considerations in decision-making about environmental planning and assessment.

Relying solely on an economic argument is contrary to the intent of the above object of the Environmental Planning & Assessment Act.

JUSTIFCATION

The applicant submits that the building is contaminated beyond being able to be made habitable; and even if it were able to be occupied it would be cost prohibitive and the stigma attached to the building as a consequence of the contamination makes the building undesirable.

In response to the presented justification by the Applicant, Council staff make the following comments:

·    The building is a listed Heritage Item.

·    The extent of asbestos disturbed within the building is a direct consequence of the poor management of the building by the owners.

·    The exact extent of asbestos or asbestos-containing material distributed within the building is based on supposition rather than laboratory testing of all disturbed material.

·    All asbestos must be removed from the building prior to it being demolished as required by Clause 452 of the Work Health and Safety Regulation 2017 and the Safe Work Australia‘s Demolition Code of Practice. In other words, the building needs to be cleaned of asbestos or asbestos-containing material in any case.

·    The building can be made fit for purpose and can be adaptively reused retaining the heritage significance of the place.

·    The highest and best use of the property will only be achieved with retention of the heritage building and having the benefit of Council’s generous heritage incentives clause under the LEP. The ability to use the incentives clause will evaporate if the heritage item is removed from the site.

·    The cost analysis presented by the applicant is based on flawed logic – it only accounts for the redevelopment of the site to a point that stops at the demolition phase and not the complete redevelopment of the site; where at a point in time the (comparative) additional cost in retaining the building would be recouped by the mere fact that there is a building on the land that does not need to be rebuilt.

MATTERS FOR CONSIDERATION

Section 1.7 - Application of Part 7 of the Biodiversity Conservation Act 2016 and Part 7A of the Fisheries Management Act 1994

Section 1.7 of the EP&A Act identifies that Part 7 of the Biodiversity Conservation Act 2016 (BC Act) and Part 7A of the Fisheries Management Act 1994 have effect in connection with terrestrial and aquatic environments.

There are four triggers known to insert a development into the Biodiversity Offset Scheme (ie the need for a BDAR to be submitted with a DA):

 

·    Trigger 1: development occurs in land mapped on the Biodiversity Values Map (OEH) (clause 7.1 of BC Regulation 2017);

·    Trigger 2: development involves clearing/disturbance of native vegetation above a certain area threshold (clauses 7.1 and 7.2 of BC Regulation 2017); or

·    Trigger 3: development is otherwise likely to significantly affect threatened species (clauses 7.2 and 7.3 of BC Act 2016).

The fourth trigger (development proposed to occur in an Area of Outstanding Biodiversity Value (clause 7.2 of BC Act 2016) is generally not applicable to the Orange LGA; as no such areas are known to occur in the LGA. No further comments will be made against the fourth trigger.

In relation to the above triggers; the subject land is not within an area of mapped high biodiversity value and there is no clearing of native vegetation proposed.

In terms of a test of significance pursuant to section 7.3 of the Biodiversity Conservation Act, given the disturbed urban environment, the development is not likely to significantly affect any threaten species, habitats or endanger ecological communities.

CROWN DEVELOPMENT

Section 4.32 of the Environmental Planning and Assessment Act defines a Crown Development Application as: a development application made by or on behalf of the Crown. The Crown includes a public authority. The EP&A Act defines a public authority as including a statutory body representing the Crown. The application was lodged by Health Administration Corporation. Health Administration Corporation as established by S9(1) of the Health Administration Act. According to s9(2)(f): The Corporation … is, for the purpose of any Act, a statutory body representing the Crown.

The Crown Development provisions preclude Council from imposing a condition of consent to this development, except with the written approval of the Minister or the applicant.  These same provisions also preclude Council from refusing to grant a consent for a Crown Development Application except with the written approval of the Minister (having first put the application before the Western Regional Planning Panel as the consent authority).

As the application is a Crown Development Application, the following process is recommended to be followed by Council:

With respect to development application DA 234/2018(1) for Demolition of a Heritage Item (all buildings, structures and vegetation to be removed) and Category 1 Remediation (asbestos removal) at Lot 2 DP 1230592 - 129-133 Sale Street, Orange it is recommended that Council:

1        Note the contents of the planning report and the recommendations therein.

2        Accept the terms of the draft notice of determination.

3        Direct Council staff to obtain the concurrence of either the applicant or the Minister as required by Section 4.33 of the Environmental Planning and Assessment Act.

4        Council provide delegated Authority to the Chief Executive Officer that upon concurrence being obtained, that the Development Application be determined (approved) based on the draft consent considered by Council (with minor amendments permitted as part of the concurrence process).  Alternatively, a report would have to be prepared to Council for development consent to be granted.

Section 4.15

Section 4.15 of the Environmental Planning and Assessment Act 1979 requires Council to consider various matters, of which those pertaining to the application are listed below.

PROVISIONS OF ANY ENVIRONMENTAL PLANNING INSTRUMENT s4.15(1)(a)(i)

Orange Local Environmental Plan 2011

Part 1 - Preliminary

Clause 1.2 - Aims of Plan

The broad aims of the LEP are set out under Subclause 2. Those relevant to the application are as follows:

(f)      to recognise and manage valued environmental heritage, landscape and scenic features of Orange.

The development, specially the demolition of Caldwell House is fundamentally inconsistent with above aim of the plan.

Clause 1.6 - Consent Authority

This clause establishes that, subject to the Act, Council is the consent authority for applications made under the LEP.

Clause 1.7 - Mapping

The subject site is identified on the LEP maps in the following manner:

Land Zoning Map:

Land zoned R1 General Residential

Lot Size Map:

No Minimum Lot Size

Heritage Map:

Heritage item

Height of Buildings Map:

No building height limit

Floor Space Ratio Map:

No floor space limit

Terrestrial Biodiversity Map:

No biodiversity sensitivity on the site

Groundwater Vulnerability Map:

Groundwater vulnerable

Drinking Water Catchment Map:

Not within the drinking water catchment

Watercourse Map:

Not within or affecting a defined watercourse

Urban Release Area Map:

Not within an urban release area

Obstacle Limitation Surface Map:

No restriction on building siting or construction

Additional Permitted Uses Map:

No additional permitted use applies

Flood Planning Map:

Not within a flood planning area

Those matters that are of relevance are addressed in detail in the body of this report.


 

Clause 1.9A - Suspension of Covenants, Agreements and Instruments

This clause provides that covenants, agreements and other instruments which seek to restrict the carrying out of development do not apply with the following exceptions:

covenants imposed or required by Council

·    prescribed instruments under Section 183A of the Crown Lands Act 1989

·    any conservation agreement under the National Parks and Wildlife Act 1974

·    any trust agreement under the Nature Conservation Trust Act 2001

·    any property vegetation plan under the Native Vegetation Act 2003

·    any biobanking agreement under Part 7A of the Threatened Species Conservation Act 1995

·    any planning agreement under Division 6 of Part 4 of the Environmental Planning and Assessment Act 1979.

Council staff are not aware of the title of the subject property being affected by any of the above.

Part 2 - Permitted or Prohibited Development

Clause 2.1 - Land Use Zones and Clause 2.3 - Zone Objectives and Land Use Table

The subject site is located within the R1 General Residential zone. If the subject land was still being used for the purposes of Community Health Services (as community health [being a directorate within NSW Health] was the most recent occupant of the building), the current land-use would be characterised as a health services facility which is defined as:

health services facility means a building or place used to provide medical or other services relating to the maintenance or improvement of the health, or the restoration to health, of persons or the prevention of disease in or treatment of injury to persons, and includes any of the following—

(a)     a medical centre,

(b)     community health service facilities,

(c)     health consulting rooms,

(d)     patient transport facilities, including helipads and ambulance facilities,

(e)     hospital.

Health services facilities are permissible in the R1 General Residential zone.

Notwithstanding the above, the applicant is not seeking consent for a health services facility, but rather the demolition of the existing buildings. Accordingly, the demolition provisions are addressed below.


 

Clause 2.3 of LEP 2011 references the Objectives for each zone in LEP 2011. These objectives for land zoned R1 General Residential are as follows:

1 - Objectives of the R1 General Residential Zone

·    To provide for the housing needs of the community.

·    To provide for a variety of housing types and densities.

·    To enable other land uses that provide facilities or services to meet the day to day needs of residents.

·    To ensure development is ordered in such a way as to maximise public transport patronage and encourage walking and cycling in close proximity to settlement.

·    To ensure that development along the Southern Link Road has an alternative access.

Retention of Caldwell House would be consistent with the objectives of the zone in so far as an adaptive re-use of the building could accommodate a future use that provides facilities or services to meet the day-to-day needs of the occupants of surrounding residential properties. Or alternately, Caldwell House could be adaptively re-used for residential purposes, adding to the diversity of the existing housing market.

Clause 2.7 - Demolition Requires Development Consent

This clause triggers the need for development consent in relation to a building or work.

The applicant is seeking consent to demolish all buildings and structures upon the land. The development requires consent given the heritage listing of the site, and the applicant has sought consent.

Part 3 - Exempt and Complying Development

The application is not exempt or complying development.

Part 5 - Miscellaneous Provisions

5.10 - Heritage Conservation

The subject land is identified as a heritage item pursuant to Schedule 5 of Orange LEP 2011. The relevant heritage inventory for the property provides the following statement of significance:

The 1937 Nurses Home is an historically and socially important element of the Orange Hospital which has retained the distinctive original character, including the Sale Street wing with art deco influences, complements the streetscape and contributes to the City as a heritage item.

(1)     Objectives

          The objectives of this clause are as follows:

(a)     to conserve the environmental heritage of Orange,

(b)     to conserve the heritage significance of heritage items and heritage conservation areas, including associated fabric, settings and views,

(c)     to conserve archaeological sites,

(d)     to conserve Aboriginal objects and Aboriginal places of heritage significance.

The development, specifically the proposal to demolish Caldwell House, is fundamentally antipathetic to the above objects of this clause, specifically objects (a) and (b). The development will result in the loss of a highly significant heritage item.

The demolition of Caldwell House is also antipathetic with the objects of the Environmental Planning and Assessment Act, specifically object (f) which seeks :

To promote the sustainable management of built and cultural heritage (including Aboriginal cultural heritage),

 

Allowing the demolition of Caldwell House is not an example of sustainable management of a significant heritage item; and accordingly the demolition of Caldwell House is not supported.

(2)     Requirement for Consent

          Development consent is required for any of the following:

(a)     demolishing or moving any of the following or altering the exterior of any of the following (including, in the case of a building, making changes to its detail, fabric, finish or appearance):

(i)      a heritage item,

The development involves the demolition of a heritage item, and as such development consent is required, which the applicant has sought.

(4)     Effect of Proposed Development on Heritage Significance

          The consent authority must, before granting consent under this clause in respect of a heritage item or heritage conservation area, consider the effect of the proposed development on the heritage significance of the item or area concerned. This subclause applies regardless of whether a heritage management document is prepared under Subclause (5) or a heritage conservation management plan is submitted under Subclause (6).

As mentioned above, if demolition of Caldwell House was agreed to it would have a substantial detrimental effect on the heritage significance of the site, effectively removing the significance entirely.

Council’s Heritage Advisor has strongly opposed the development and has prepared detailed advice to Council. This was provided to the applicant, who in turn provided a detailed response. The heritage advice received by Council (bold and paraphrased in the applicant’s response) and applicant’s response (italics) is provided below:

In regard to the heritage value of Caldwell House, it is noted that:

1.       The potential exists for the building to be converted to many uses as facilitated by the heritage conservation incentives of Orange LEP 2011; and

2.       The preferred approach would be for the building to be remediated (in terms of asbestos) and adaptively re-used.

However, the ability to pursue the above is significantly constrained by the environmental risks to future occupants and the economic burden and risk outlined earlier.

In response to the matters raised in the Summary and Recommendations sections of the heritage advisor’s report dated July 2018, we advise as follows:

1.       The heritage advisor states that the HIS is not consistent with the NSW Heritage template or guide.

          The Heritage Impact Statement (HIS) by Weir Phillips Heritage has been revised and a copy is attached.

2.       The heritage advisor is concerned that appropriate expert heritage advice has not been used to pursue appropriate options for the site. In response to this:

a)      Despite the fact that the HIS could not recommend retention of the building; it is our submission that Weir Phillips has provided “appropriate expert heritage advice”. The HIS has assessed the proposal in the context of the following heritage publications:

·   NSW Heritage Office, Statements of Heritage Significance (2002 update)

·   NSW Heritage Office, Statements of Heritage Significance (2002)

          In particular, Sections 5.3.3 and 5.4 of the revised HIS consider sympathetic solutions and explain why they have been discounted in terms of heritage values.

b)      The conclusion reached in the HIS (essentially that there is no alternative but to demolish the building) is reflective of the well supported argument, that the environmental risks and the economic burden associated with asbestos remediation and demolition/retention of the building outweigh the heritage values.

3.       Orange Council’s heritage advisor is concerned that the SoEE and HIS draw erroneous conclusions of non-viability related to decontamination costs which are unrelated to heritage options.

The process of having specialist contractors (in conjunction with asbestos assessors) provide detailed quotations has demonstrated that:

a)      The level of asbestos contamination is greater and more complicated than what was expressed in the original DA documentation, particularly in terms of the difficulty in treating inaccessible areas and minimising the risk of airborne fibres for future occupants.

b)      The cost of remediation is far greater than the estimates that were provided in the original DA documentation.

4.       The heritage advisor is concerned that the justification for the demolition of the last remaining buildings associated with the Orange Base Hospital are not borne out by the evidence presented.

It is suggested that the additional information provided in this document would address any concerns in this regard.


 

5.       The heritage advisor is concerned that the proposal does not include an end use and built form which would replace the existing development of the site.

We agree; however, it is considered appropriate for Council to allow demolition without having this information provided due to the following:

a)      The circumstances around the asbestos situation suggest that demolition of the building is required (particularly for environmental reasons) regardless of future development plans for the site.

b)      It is difficult to practically nominate “an end use and built form” option as part of this development application. In this regard, there is a range of future development options for the site, but none are known at this stage; and there is no obligation to pursue any option that may be put forward at this stage.

c)       Once a development option is determined, the appropriateness and impact of such development will be guided, assessed and addressed as part of the DA process.

6.       The heritage advisor recommends that:

The Applicant is encouraged to engage with skilled and experienced heritage architects who can develop options for the adaptive re-use of the original East wing known as Caldwell House and the sympathetic development of the remainder of the site in accord with market indicators and use of the incentive clauses under the Orange LEP.

The options should then be costed in relation to the related decontamination and structural issues and reviewed with Council and following suitable discussions and market testing an application be prepared and lodged.

We appreciate the intent of the recommendation; however, our response is as follows:

a)      Before considering heritage appropriate options for re-use of the East wing, the first step is to address concerns regarding the asbestos contamination.

b)      In pursuit of point (a), both specialist contractors (with their respective assessors) were asked to consider the following scenarios:

·   Undertake the asbestos remediation of Caldwell House and retain front façade and verandah only. In this regard:

DEMEX/ERS provided a quotation which has been provided to Council as commercial-in-confidence. In short, the cost is unrealistic; impractical; and prohibitive. This also should be regarded as a theoretical price only as a clearance certificate cannot be issued for the retained elements.

IP/Airsafe refused to offer a quotation.

·   Undertake the asbestos remediation of Caldwell House and retain the sale Street building (i.e. the east wing as referred to by the heritage advisor). In this regard both DEMEX/ERS and IP/Airsafe refused to offer a quotation because neither were confident that the remaining building would achieve a satisfactory standard of asbestos clean-up and could not obtain a clearance certificate.

c)       Given that a satisfactory situation is unlikely to be achieved in terms of asbestos remediation, we don’t think that engaging a “skilled and experienced heritage architect” to consider adaptive re-use options for the East wing is necessary. It is recognised that the Orange LEP 2011 heritage conservation incentives facilitate a broad range of adaptive re-use options for Caldwell House. However, the highest and best land use will always be constrained by the asbestos situation and it is likely that the building and site will remain undeveloped and boarded up for the foreseeable future.

The justification presented within the application is not centred on a proposition that the building is not heritage significant. The applicant fully acknowledges this by stating: The preferred approach would be for the building to be remediated (in terms of asbestos) and adaptively re-used.

The applicant’s justification rather centres on the proposition that the building has deteriorated (although not expressly acknowledged by the applicant; the deterioration has occurred as a direct consequence of the neglect and inattention given to one of NSW Health’s assets) to the point where it is unsalvageable/unusable; and therefore this results in it being acceptable to lose one of the City’s valued heritage assets: a building that is effectively the only remnant health related building in an area of the City that has provided significant health care to the community within the region, an area much broader than just the Orange LGA.

Therefore, given that Council staff and the applicant are in agreement that the building is an important heritage item and should be retained, and given that the applicant has not categorically ruled out that the building cannot be cleaned-up, there is very little justification to support the demolition of Caldwell House.

With the proposition put forward by the applicant that the building is required to be demolished due to the deteriorated state (again caused directly by the neglect of the owners) refuted; it is then necessary to explore the applicant’s secondary argument around the financial imposition of retention of the significant heritage item.

The applicant suggests that retaining the building following remediation would be cost prohibitive. Of the three options referred to above, retention is the most expensive. However, the applicant indicated that their consultant/contractors were not prepared to price the option of retention as they were of the view it could not be successfully achieved.

As indicated above, Council’s experts disagree with the assertion that the building cannot be appropriately cleaned and occupied. Council engaged engineering consultants Bradford Barker to complete a peer review of the submitted material, carry out a basic inspection of Caldwell House in terms of its structural adequacy, and finally provide the missing costings that the applicant was unwilling to provide.

Bradford Barker concluded that:

·    they agree with findings of Council’s Contamination Expert;

·    that the building would be structurally adequate to enable the necessary remediation works to be carried out; and

·    that the option to retain Caldwell House is approximately 33% more expensive than the applicant’s preferred option of complete demolition.

There is an important observation to make at this point. The applicant’s cost argument is somewhat flawed. The focus of cost has been entirely focused only on the cost of demolition. But as indicated in the application, Health Infrastructure are not intending on carrying out the work. It is understood that their interests to date are simply in divesting the property with the consent in place.

Therefore, when a new party comes to acquire the land, it is very unlikely that they would stop at the completion of the demolition, but rather they would continue to develop the land to its highest and best use[3].

What has been provided by the applicant is only an analysis of the demolition cost, not a realistic cost to redevelop the site. It is highly likely that the 33% additional cost at the remediation stage (to retain the building) would be partly or fully recouped by the mere fact that there was an existing building on the land that could be simply adapted for the desired highest and best use; albeit with the necessary upgrades required under the NCC.

The point being, the additional cost at the remediation stage to retain the building would not be the actual additional cost when accounting for the total redevelopment of the site.

In the absence of such a detailed, realistic and rigorous cost analysis of the complete redevelopment of the site, the cost argument is not one that could be supported.

So in summary:

·    Caldwell House is a significant heritage item, a remnant of the historic and significant use of this locality as a regional medical precinct.

·    Caldwell House is capable of being successfully remediated, albeit with an ongoing management plan (again such a document is not uncommon).

·    The cost analysis provided by the applicant provides an incomplete picture of the total redevelopment cost of developing the subject land.

On this basis, allowing the demolition of Caldwell House would be fundamentally contrary to the objects of the Environmental Planning and Assessment Act, the aims of the LEP and the objects of this clause. Thus, demolition of Caldwell House should not be supported.

(5)     Heritage Assessment

          The consent authority may, before granting consent to any development:

(a)     on land on which a heritage item is located, or

(b)     on land that is within a heritage conservation area, or

(c)     on land that is within the vicinity of land referred to in paragraph (a) or (b),

          require a heritage management document to be prepared that assesses the extent to which the carrying out of the proposed development would affect the heritage significance of the heritage item or heritage conservation area concerned.


 

A heritage management document as defined in the LEP means:

(a)     a heritage conservation management plan, or

(b)     a heritage impact statement, or

(c)     any other document that provides guidelines for the ongoing management and conservation of a heritage item, Aboriginal object, Aboriginal place of heritage significance or heritage conservation area.

A heritage impact statement has been submitted in support of the application.

(6)     Heritage Conservation Management Plans

          The consent authority may require, after considering the heritage significance of a heritage item and the extent of change proposed to it, the submission of a heritage conservation management plan before granting consent under this clause.

At present there is no Conservation Management Plan prepared for the land. Given the recommendation for the retention of Caldwell House, it is appropriate to require that a Conservation Management Plan be prepared to guide future adaptive reuse along with the ongoing maintenance and management of Caldwell House.

(7)     Archaeological Sites

          The consent authority must, before granting consent under this clause to the carrying out of development on an archaeological site (other than land listed on the State Heritage Register or to which an interim heritage order under the Heritage Act 1977 applies):

(a)     notify the Heritage Council of its intention to grant consent, and

(b)     take into consideration any response received from the Heritage Council within 28 days after the notice is sent.

The site is not a known archaeological site. Notwithstanding this, as the development will involve extensive ground disturbance with the demolition of the red brick (more recent) nurses quarters, there is a high likelihood of encountering an aboriginal object or archaeological relic. As such, Council’s standard precautionary condition is attached that specifies a process to follow in the event an object or relic is discovered.

(8)     Aboriginal Places of Heritage Significance

          The consent authority must, before granting consent under this clause to the carrying out of development in an Aboriginal place of heritage significance:

(a)     consider the effect of the proposed development on the heritage significance of the place and any Aboriginal object known or reasonably likely to be located at the place by means of an adequate investigation and assessment (which may involve consideration of a heritage impact statement), and

(b)     notify the local Aboriginal communities, in writing or in such other manner as may be appropriate, about the application and take into consideration any response received within 28 days after the notice is sent.

The subject land is not an Aboriginal Place of Heritage Significance. An AHIMS search confirms that the site has no Aboriginal sites or places recorded against it.


 

(9)     Demolition of Nominated State Heritage Items

          The consent authority must, before granting consent under this clause for the demolition of a nominated State heritage item:

(a)     notify the Heritage Council about the application, and

(b)     take into consideration any response received from the Heritage Council within 28 days after the notice is sent.

The subject land is not a Nominated State Heritage Item.

(10)   Conservation Incentives

          The consent authority may grant consent to development for any purpose of a building that is a heritage item or of the land on which such a building is erected, or for any purpose on an Aboriginal place of heritage significance, even though development for that purpose would otherwise not be allowed by this Plan, if the consent authority is satisfied that:

(a)     the conservation of the heritage item or Aboriginal place of heritage significance is facilitated by the granting of consent, and

(b)     the proposed development is in accordance with a heritage management document that has been approved by the consent authority, and

(c)     the consent to the proposed development would require that all necessary conservation work identified in the heritage management document is carried out, and

(d)     the proposed development would not adversely affect the heritage significance of the heritage item, including its setting, or the heritage significance of the Aboriginal place of heritage significance, and

(e)     the proposed development would not have any significant adverse effect on the amenity of the surrounding area.

The conservation incentives clause could be relied upon for adaptive re-use of Caldwell House whilst ever Caldwell House remained on the land. A land-use could be contemplated that is impermissible in the R1 General Residential zone, such as a commercial office building.

The ability to rely upon the incentives clause would be lost if Caldwell House was demolished.

Part 6 - Urban Release Area

Not relevant to the application. The subject site is not located in an Urban Release Area.

Part 7 - Additional Local Provisions

7.3 - Stormwater Management

This clause applies to all industrial, commercial and residential zones and requires that Council be satisfied that the proposal:

(a)     is designed to maximise the use of water permeable surfaces on the land having regard to the soil characteristics affecting onsite infiltration of water

(b)     includes, where practical, onsite stormwater retention for use as an alternative supply to mains water, groundwater or river water; and

(c)     avoids any significant impacts of stormwater runoff on adjoining downstream properties, native bushland and receiving waters, or if that impact cannot be reasonably avoided, minimises and mitigates the impact.

Relevant conditions are attached in relation to the disconnection of services to the buildings approved to be demolished. A soil and erosion control plan will be required to be installed whilst any approved demolition works are undertaken.

7.6 - Groundwater Vulnerability

This clause seeks to protect hydrological functions of groundwater systems and protect resources from both depletion and contamination. Orange has a high water table and large areas of the LGA, including the subject site, are identified with “Groundwater Vulnerability” on the Groundwater Vulnerability Map. This requires that Council consider:

(a)     whether or not the development (including any onsite storage or disposal of solid or liquid waste and chemicals) is likely to cause any groundwater contamination or have any adverse effect on groundwater dependent ecosystems, and

(b)     the cumulative impact (including the impact on nearby groundwater extraction for potable water supply or stock water supply) of the development and any other existing development on groundwater.

Furthermore, consent may not be granted unless Council is satisfied that:

(a)     the development is designed, sited and will be managed to avoid any significant adverse environmental impact, or

(b)     if that impact cannot be reasonably avoided - the development is designed, sited and will be managed to minimise that impact,

(c)     if that impact cannot be minimised - the development will be managed to mitigate that impact.

The proposal is not anticipated to involve the discharge of toxic or noxious substances and is therefore unlikely to contaminate the groundwater or related ecosystems. Measures will need to be implemented to ensure that dust and sediment do not escape the site. The proposal does not involve extraction of groundwater and will therefore not contribute to groundwater depletion.

Clause 7.11 - Essential Services

Clause 7.11 applies and states:

Development consent must not be granted to development unless the consent authority is satisfied that any of the following services that are essential for the proposed development are available or that adequate arrangements have been made to make them available when required:

(a)     the supply of water,

(b)     the supply of electricity,

(c)     the disposal and management of sewage,

(d)     storm water drainage or onsite conservation,

(e)     suitable road access.

In consideration of this clause, all utility services are available to the land. Disconnection to the red brick (more recent) nurses quarters will need to occur as part of the demolition.

STATE ENVIRONMENTAL PLANNING POLICIES

State Environmental Planning Policy 55 - Remediation of Land

Application has been made for a Category 1 remediation and as such SEPP 55 – Remediation of Land is applicable to the assessment of the application. The applicant has sought to treat the application as a Category 1 remediation due to the extent of asbestos material within the buildings.

The application is accompanied by the following documents related to the remediation of the land:

·    Hazardous Materials Survey.

·    Asbestos Removal Options.

·    Asbestos Removal Control Plan.

·    Preliminary Contamination Investigation.

·    Asbestos Audit.

The asbestos will need to be removed from the site and transported to an appropriate facility. The transport of asbestos-containing material falls within the jurisdiction of the EPA. The Asbestos Removal Control Plan provides a detailed explanation and protocols for the removal of asbestos. The other accompanying documentation (Hazardous Materials Survey and Asbestos Audits) inform the Asbestos Removal Control Plan.

Relevant conditions are attached regarding the need for the asbestos removal to be in accordance with the Asbestos Removal Control Plan. Separate specific conditions are attached that obligate the beneficiary of the consent to implement appropriate air monitoring during the clean-up and demolition of the buildings permitted to be demolished. These conditions only relate to the buildings permitted to be demolished. There are also conditions attached obligating the beneficiary of the consent to furnish Council with all necessary clearance certificates for the works.

The Preliminary Contamination Investigation analysed samples taken from the site and tested them for heavy metals and organochlorine pesticides. The sampling returned slightly elevated levels of copper, zinc and lead, but all were below the residential land-use thresholds (noting that commercial uses have a lower threshold). Accordingly, there is no contamination within the site (save for the asbestos within the buildings) that would prevent the land being used for residential or commercial land-uses.

State Environmental Planning Policy (infrastructure) 

State Environmental Planning Policy (infrastructure) is applicable to the application given the proximity of overhead power lines to the subject site in Dalton Street, specifically Clause 45 of the SEPP. This clause requires that Council, where applicable (such as in this case), consult with the electricity supply authority - in this case Essential Energy.

Council staff consulted with Essential Energy during the assessment process. Essential Energy did not raise any objections to the development but did provide Council with their standard requirements for developments within the vicinity of overhead powerlines. These have been included in the draft notice of approval.

PROVISIONS OF ANY DRAFT ENVIRONMENTAL PLANNING INSTRUMENT THAT HAS BEEN PLACED ON EXHIBITION 4.15(1)(a)(ii)

From 31 January to13 April 2018 the Department of Planning and Environment publically exhibited an Explanation of Intended Effect (EIE) and Draft Planning Guidelines for the proposed Remediation of Land SEPP, which will repeal and replace State Environmental Planning Policy 55 – Remediation of Land (SEPP 55). Of particular note, the Draft Planning Guidelines state:

“In undertaking an initial evaluation, a planning authority should consider whether there is any known or potential contamination on nearby or neighbouring properties, or in nearby groundwater, and whether that contamination needs to be considered in the assessment and decision making process.”

“If the planning authority knows that contamination of nearby land is present but has not yet been investigated, it may require further information from the applicant to demonstrate that the contamination on nearby land will not adversely affect the subject land having regard to the proposed use.” (Proposed Remediation of Lands SEPP - Draft Planning Guidelines, Page 10).

Council staff are not aware of any contamination on adjoining sites.

DESIGNATED DEVELOPMENT

The applicant suggest that onsite crushing of the material may occur or it may be transported off-site. In any event, if the material is processed onsite it would be considered ancillary to the demolition and not a stand-alone use of the land, and as such would not be deemed designated development.

INTEGRATED DEVELOPMENT

The applicant has not indicated that the application requires any further approvals from other Government Agencies.

PROVISIONS OF ANY DEVELOPMENT CONTROL PLAN s4.15(1)(a)(iii)

Development Control Plan 2004

Development Control Plan 2004 (“the DCP”) applies to the subject land (Part 0 – LEP, Part 3 – General Considerations, Part 4 – Special Environmental Considerations and Chapter 13 – Heritage). An assessment of the proposed development against the relevant Planning Outcomes will be undertaken below.

Pursuant to Planning Outcome 0.2-1 Interim Planning Outcomes - Conversion of Zones:

·    Throughout this Plan, any reference to a zone in Orange LEP 2000 is to be taken to be a reference to the corresponding zone(s) in the zone conversion table.


 

The corresponding zone to zone 2a (Orange LEP 2000) is zone R1 General Residential (Orange LEP 2011). As such, Orange DCP 2004 – 7 – Development in Residential Areas would ordinarily be the principle part applicable. However, given the application relates to purely demolition, part 7 is not relevant and the other relevant parts are addressed below.

Part 3 – General Considerations

Part 3 provides planning outcomes of a general nature. Those of relevance to this assessment relate to cumulative impacts and waste generation. These are both addressed below under the heading “Likely Impacts”. The other matters within Part 3 not listed here are not relevant to the assessment.

Part 4 – Special Environmental Considerations

Part 4 deal with inter alia, contaminated land. This matter is considered above under the SEPP 55 considerations. The other matters within Part 4 not listed here are not relevant to the assessment.

Part 13 – Heritage

Part 13 deals with heritage considerations and specially deals with demolition of a heritage item; and requires that applications for demolition are well founded and sufficiently justified. Part 13 also requires that for application involving demolition, applicants must include details of the proposed development requiring the demolition of the heritage-significant building or site.

In regards to the above, Council staff are of the view that the applicant has not sufficiently demonstrated that the demolition is justified or well founded. Hence the rationale behind the recommendations contained within this report. In relation to the DCP requirement for the applicant to provide details of the development that necessitates the demolition, this is addressed above in the applicant’s response to Council’s Heritage Advisor’s commentary on the application. The absence of such information is considered as further reasons for the unsoundness of the applicant’s justification.

INFILL GUIDELINES

Despite the land being identified as a heritage item, given there are no building works involved, the Infill Guidelines are not applicable in the assessment of this application.

PROVISIONS PRESCRIBED BY THE REGULATIONS s4.15(1)(a)(iv)

Demolition of a Building (clause 92)

The proposal involves the demolition of all buildings and structures on the land. A condition is attached requiring the demolition to be carried out in accordance with Australian Standard AS2601 - 1991: The Demolition of Structures.

Fire Safety Considerations (clause 93)

The proposal does not involve a change of building use for an existing building.

Buildings to be Upgraded (clause 94)

The proposal does not involve the rebuilding, alteration, enlargement or extension of an existing building.

 

BASIX Commitments (clause 97A)

Not applicable.

THE LIKELY IMPACTS OF THE DEVELOPMENT s4.15(1)(b)

Context and Setting

The subject land is one of the last remnants of the former hospital site. It contains the heritage significant Caldwell House. The proposal to demolish Caldwell House is contrary to the context and setting given the land’s heritage status, and as such should not be supported.

Heritage Impacts

As described above, the development as proposed would result in the loss of an important heritage item. Council staff, through the use of experts in various fields relevant to the proposal, have concluded that there is insufficient grounds to warrant the demolition of the listed heritage item.

As described above, relevant conditions are attached that preclude works of any nature to occur to the Caldwell House building as part of this application.

Noise and Vibration Impacts

Noise Impacts

A Noise and Vibration Assessment has been prepared by Wilkinson Murray Pty Ltd (refer Annexure L). The assessment identified the nearest sensitive receivers as the following dwellings:

·    R1 67 Dalton Street Residence

·    R2 137 Sale Street Residence

·    R3 63 Dalton Street Residence

·    R4 61 Dalton Street Residence

·    R5 59 Dalton Street Residence

·    R6 78 Dalton Street Residence

·    R7 97 Prince Street Residence

·    R8 99 Prince Street Residence

·    M1 65 Dalton Street Women’s Health Orange

·    M2 135 Sale Street Recovery Rehabilitation Services

·    M3 95 Prince Street Cerebral Palsy Alliance

·    M4 127 Sale Street Health Consulting

·    M5 125 Sale Street Health Consulting (vacant)

·    C1 123 Prince Street Hogan’s Pharmacy

·    TAFE March Street Orange College of TAFE

The sensitive receivers are indicated below in the aerial plan extract (Source – Applicants submission) from the Noise and Vibration Assessment.

 

The construction Noise assessment submitted in support of the subject development adopted the following noise management levels (NMLs):

Surrounding Residential Receivers

·    Monday to Friday                          50dBA

·    Saturday                                        50dBA

·    Highly noise affected                     75dBA

Surrounding Non-Residential Receivers

·    Consulting Suites                           65dBA

·    TAFE                                               65dBA

The assessment considered the noise generated at each scenario of the demolition process (based on the demolition stages outlined in the Demolition Methodology by Cook & Roe). The assessment predicted noise levels at the most potentially sensitive receivers. The predicted LAeq 15min noise levels associated with the proposed works exceed the NML at all of the most potentially affected receivers during at least one of the works scenarios. During demolition of multi storey buildings (being those authorised by the consent to be demolished) (the most noise intensive scenario) the predicted LAeq 15min noise levels at residential receivers R6, R7 and R8 exceed the highly affected level of 75 dBA by up to 33dBA at the most effected receiver (99 Prince Street). The applicants submit that these exceedances are primarily due to the use of an excavator with a hammer attachment and also onsite concrete crushing.

It is noted that the development, being demotion of a building is not a permanent activity on the site and as such the impacts are experienced over a relatively short period.

Notwithstanding this, to ensure the impacts remain within acceptable levels, relevant conditions are attached to require a management plan to mitigate the potential noise impacts. This is discussed below under the summary of Noise and Vibration Impacts heading below.

It should be noted that the recommendation of this report to not allow demolition of Caldwell House which effectively reduces the extent of demolition and, as a consequence, will reduce the environmental impacts in the locality.

Finally, it is noted that the demolition of the former base hospital (which occurred opposite the subject land) relied on a comparable demolition methodology, using comparable demolition equipment. This particular development had similar exceedances of the noise management levels; which were addressed via a similar requirement for a management plan. Council staff are recommending a consistent approach with this application.

Vibration impacts

According to the Wilkinson Murray report, the assessment of vibration requires consideration of two components:

·    Human exposure to vibration.

·    The potential for building damage by vibration.

The applicant indicates depending upon the size of the hydraulic hammer, there is a likelihood that the safe working distances for both cosmetic damage and human response cannot be maintained. On this basis consideration should be given to completing the works with a smaller machine so that safe working distances can be met. If the works cannot be conducted with a smaller machine, the works should not proceed without accompanying vibration monitoring to ensure compliance with the vibration standards. Additionally, dilapidation surveys should be considered to establish the condition of nearby structures prior to vibration intensive activities being carried out.

Summary of Noise and Vibration Impacts.

It is recommended in order to address impacts associated with noise and vibration that a Demolition Noise and Vibration Management Plan (DNVMP) be developed prior to works commencing. The DNVMP should address all reasonable and feasible measures to mitigate noise and vibration levels at nearby receivers. During demolition works best practice management strategies must implemented to minimise any potential noise impact. These would include but are not limited to restricting hours of operation (7am to 6pm Monday to Friday and 8am to 1pm Saturdays. No work will occur on Sundays and Public Holidays), scheduling noisy works where practicably possible to the least sensitive time of day for the closest receivers, scheduling construction to minimise multiple use of the noisiest equipment or plant items where practicable, strategic positioning of plant items and work areas to reduce the noise emission to noise sensitive receptors, ensuring construction machinery is well maintained, awareness training for contractors in environmental noise issues and community consultation with local residents/businesses to assist in the alleviation of community concerns.

The attached Notice of Determination includes recommended conditions to address Noise and Vibration impacts.


 

Traffic Impacts

Traffic impacts associated with the development will be limited to trucks delivering machinery and trucks removing material from site, along with passenger vehicles related to people working onsite. The subject land benefits from its proximity to a section of Sale Street (between Dalton and Prince Streets) which has traffic calming devices at the northern and southern ends of the block to reduce traffic speed; as well as on-street parking down the centre of Sale Street which would be able to accommodate workers’ vehicles. Both Sale and Dalton Streets are capable of dealing with the additional traffic movements, particularly heavy vehicles carting waste material from the site.

The development is not expected to generate any unreasonable traffic impacts during the proposed development, particularly given the short term nature of the development.

Air Quality

There is a high likelihood that air quality could be impacted by the demolition of the former nurses quarters, particularly given the presence of asbestos and asbestos-containing material. As such, a condition is attached that requires air quality monitoring by independent and suitably qualified person/s during the entire development, from site establishment through to final clearance.

 

Environmental Impacts

The site does not contain any native vegetation. There are a number of mature introduced deciduous trees that are proposed to be removed, along with a number of small shrubs. The subject trees are not likely to provide habitat to any threatened species and, as such the removal of the subject vegetation is not likely to give rise to any unsatisfactory environmental impacts.

Waste Generation

The development will obviously generate waste. A condition is attached that requires a waste management plan to be submitted. The transport of waste falls within the jurisdiction of the EPA. The waste contractor is obligated to take the waste to appropriate facilities for disposal or re-processing.

Cumulative Impacts

Cumulative impacts of a development can arise under four typical scenarios, namely:

·    time crowded effects where individual impacts occur so close in time that the initial impact is not dispersed before the proceeding occurs

·    space crowded where impacts are felt because they occur so close in space they have a tendency to overlap

·    nibbling effects occur where small, often minor impacts, act together to erode the environmental condition of a locality and

·    synergistic effects, where a mix of heterogeneous impacts interact such that the combined impacts are greater than the sum of the separate effects.


 

There is strong likelihood that one or more of the above scenarios may arise, owing to the demolition methodology and the machinery intended to be used. However, the extent of such scenarios are ameliorated as far as practicable through the recommended conditions of consent.

THE SUITABILITY OF THE SITE s4.15(1)(c)

The site is unsuitable for the proposed development. The retention of the heritage item on the site is strongly recommended for the reasons outlined above.

ANY SUBMISSIONS MADE IN ACCORDANCE WITH THE ACT s4.15(1)(d)

The proposed development is defined as "advertised development" under the provisions of SEPP 55 and the Environmental Planning & Assessment Regulations. The application was advertised for the prescribed period of 30 days on two separate occasions. Due to the extent of additional information submitted by the applicant, it was determined that the new information materially changed the application from what was originally submitted, so the application was publicly exhibited following a second advertisement in the local newspaper. Given the two exhibition periods, the submissions are grouped depending on which submission period they were received in.

 

Initial Exhibition Period

Submission 1 – Steve Adams – 145 Sale Street

The submission is in support of the application and suggests that the building has become a public disgrace. The submission also commends Council on their initiative to purchase and demolish the former base hospital.

Council staff comment

Whilst the building has been left to decay and has been mismanaged, this is not sufficient grounds to warrant its demolition.

Submission 2 – Orange Historical Society

The submission strongly objects to the application. The submission provides a detailed history of the evolution of the site and its relationship with the former hospital site. The submission also makes the points that the building is required to be cleaned prior to demolition and that the extent of disturbance to the building would be far less if the building was properly managed and kept secure.

Council staff comment

Council staff are in full agreement with the points raised in the submission, as articulated in the foregoing assessment.

Submission 3 – Kara Jennison – 78 Dalton Street

The submission is from the owner of the property that shares a common boundary with the subject land, namely part of the western boundary. The submission raises three main concerns: dividing fencing, noise and vibration, and the demolition of Caldwell House.


 

Dividing Fence – The submitter shares a boundary with the subject land. On the boundary is a structure that is proposed to be removed. The structure has a solid wall running along or close to the boundary. Removing the structure would effectively remove part of the wall that acts as the dividing fence.

The submitter has requested that the fence be removed by manual means as opposed to machinery, and that a suitable replacement fence of similar materials and height be constructed prior to the structure being removed. The requests are reasonable, however, given the proximity of the structure on the boundary it may not be possible to construct a preplacement fence until after the structure is removed.

Conditions are attached that require the wall on the common boundary between the subject land and 78 Dalton Street to be removed by manual labour as far as practicable. A further condition is attached that requires a replacement fence of similar materials and of a similar height to be installed on the common boundary within 28 days of the structure being removed.

Noise and Vibration – The submitter requests that dilapidation reports be prepared for all immediately surround structures. The submitter also requests that given the noise exceedances, Council impose a condition that requires the demolition contractor to consult with adjoining neighbours prior to periods of noise occurring.

 

Council staff comment

Council staff have recommended that a condition be imposed that requires dilapidation reports to be prepared for adjoining properties where those owners are happy for the persons preparing the report to enter their land.

In relation to noise impacts, Council staff have recommended that a condition be imposed that requires a Demolition Noise and Vibration Management Plan be prepared prior to works commencing on the land. As part of the Demolition Noise and Vibration Management Plan, the demolition contractor will be required to consult with adjoining owners to advise when the higher noise level activities will occur as part of the demolition. Additionally, the Demolition Noise and Vibration Management Plan will stipulate the protocols for a complaints register. In addition to this, the recommendations out of the acoustic report will be recommended as conditions of consent.

Caldwell House – The submitter raises concerns in relation to the demolition of the heritage listed Caldwell House.

Council staff comment

Council staff agree with the comments made within the submission, hence the reason why the report recommends that no works occur to Caldwell House.

Submission 4 – Euan Greer – 21 Lawson Crescent

The author of the submission strongly opposes the application and raises numerous valid points in support of the retention of Caldwell House.

Council staff comment

Council staff agree with the comments made and points raised in the submission, and as such Council staff are not supporting the demolition of Caldwell House.

Submission 5 – Adaptive Architects (James Nicholson)

The author of the submission is strongly opposed to the demolition of Caldwell House. The author provides a very detailed and highly technical critical analysis of the application and raises many similar points that have been raised by Council staff, such as the fact that the building is required to have all asbestos removed prior to any demolition works occurring on the land. The author also provides a detailed list of how the removal of asbestos could occur in line with heritage conservation principles.

The author of the submission also interrogates the costings provided within the application as originally submitted and rebuts numerous other claims within the application; such as the claim that the building would need to be classed as a type A construction for non-residential uses, or that the undersized rooms preclude adaptive re-use.

The submission is also accompanied by a very detailed concept plan that provides an example of how the building could be redeveloped as Hotel or Motel Accommodation.

Council staff comment

The submission is very detailed and provides a high level technical critique of the application as originally submitted. Council staff concur with much of what has been raised in the submission, and thus Council staff do not support the demolition of Caldwell House.

 

Subsequent Exhibition Period

Submission 1 – Steve and Kay Adams (same author as submission 1 received during the initial exhibition period)

The authors of the submission are in support of the application and suggest that the applicant’s proposition is the only viable option.

Council staff comment

Council staff disagree with the author and the applicant. Council staff have engaged experts who have concluded that Caldwell House can be successfully remediated and safely occupied.

Submission 2 – Anne Salter

The author of the submission strongly opposes the demolition of Caldwell House, raises the point that the building requires the asbestos to be removed prior to demolition, and also raises concerns in relation to the environmental cost of allowing the demolition of Caldwell House.

Council staff comment

Council staff agree with the comments raised in the submission. Council staff are not supporting the demolition of Caldwell House for the reasons raised in the forgoing assessment.


 

Submission 3 – Euan Greer (same author as submission 4 received during the initial exhibition period)

The author of the submission highlights in considerable detail inconsistencies and errors within the amended material, particularly relating to the submitted amended costings. The author also questions the veracity of the assessed extent of asbestos, stating that the level of contamination is based on supposition rather than clear knowledge of contamination levels. Additionally, the author questions the recommendations made in the HIS and the reliance on the other expert reports to arrive at the conclusion presented within the HIS. The author of the submission also provides examples of similar buildings that have been successfully adaptively re-used and provides commentary around the possible options.

Council staff comment

In relation to the costings, Council staff generally agreed that there was missing information, hence why Council engaged Bradford Barker to complete a peer review of the costings and also provide Council with a realistic figure for the retention of Caldwell House. Council staff agree with the comments made in relation to the exact extent of asbestos or asbestos-containing material. Comments have been made in the report in relation to this issue.

The commentary around the heritage issues of the proposal are acknowledged, much of which Council staff agree with; and as such Council staff are not in support of the demolition of Caldwell House.

Submission 4 – Adaptive Architects (same author as submission 5 received during the initial exhibition period)

The author of the submission expresses their strong opposition to the application, specifically the demolition of Caldwell House. The author of the submission presents a detailed critical analysis of the material relied upon to arrive at the conclusion that the building ought to be demolished, and suggests that in arriving at this position the various experts, particularly the author of the HIS, has relied on flawed logic. The submission provides a detailed interrogation of the costings presented and questions the impartiality of the various contractors that have provided quotes.

The submission rebukes the claims made within the additional material that draws a correlation between the asbestos contamination within this application and the “Mr Fluffy” scenario in the ACT.

The author provides a very detailed analysis of how the building could be practically cleaned and encapsulated, whilst ensuring heritage conservation principles are observed and significant heritage fabric is retained. It is important to point out that the author of the submission comes with the authority of being a registered architect and also being listed on the NSW Office of Environment and Heritage – heritage consultant register.

The author also provides rebutting remarks in relation to the claims made around issuance of clearance certificates, insurance implications, and the alleged stigma attached to the building as a result of “continually raising the stakes of the asbestos risk”.


 

Council staff comment

The submission is extremely detailed and provides a very high level critical review of the technical aspects of the proposal. Council staff are essentially in general agreement with much of what is presented in the submission. The submission echoes a critical concern that Council staff hold, that being the HIS does not present a detailed analysis of how the building could realistically be cleaned and made fit for purpose using techniques that align with the Burra Charter. The HIS simply accepts the methodology presented by the other experts and does not challenge or offer alternative ways of cleaning and encapsulating the asbestos within Caldwell House to align with accepted heritage conservation principles.

It is for this reason that Council staff have recommended the imposition of a condition that precludes any works to Caldwell House. When the time comes to clean Caldwell House it will need to be predicted on conservation principles.

Submission 5 Gloria Murray – 81 Prince Street (received outside of the exhibition period)

The submission questions who Health Infrastructure is, queries the built form of the future building and highlights the possible impacts.

Council staff comment

As detailed above, Health Infrastructure sits within the Health Administration Corporation which is a Crown body with the NSW Health Ministry.

In response to the building form and likely impacts, this is not possible to say as the application only seeks consent to demolish the buildings - there is no intent within the application to construct a building.

 

PUBLIC INTEREST s4.15(1)(e)

The proposed development is considered to be of moderate to high interest to the wider public due to the level of heritage significance of the subject building, particularly the social significance attributed to the building, as well as the fact that this is a public building.

Given what the proposal is seeking, it is considered that the proposed development is not in the public interest, and therefore the demolition of Caldwell House should not be supported.

SUMMARY

A Section 4.15 assessment of the development application indicates that the certain parts of the proposed development are not acceptable. The report and recommendations as outlined above do not support the demolition of the heritage listed building being “Caldwell House”. The recommendation by Council staff is to allow the later nurse’s quarters and other non-significant buildings on the land to be demolished; however, the draft consent does not authorise the demolition of Caldwell House itself.

The applicant has presented a number of reasons to support their intent to demolish the buildings on the land which have been scrutinised in detail by Council’s consultants and planning staff.  A detailed assessment of such has been provided within the report.

Attached is a draft Notice of Determination outlining a range of conditions considered appropriate to ensure that the development proceeds in an acceptable manner.

The rationale presented by the applicant for the demolition of this significant heritage item is considered to be unfounded for the reasons given above.

COMMENTS

The requirements of the Environmental Health and Building Surveyor and the Engineering Development Section are included in the attached Notice of Approval.

 

 

Attachments

1          Notice of Approval, D20/37499

2          Plans, D20/37404

3          Submissions, D20/37464

 


Planning and Development Committee                                                                  7 July 2020

Attachment 1      Notice of Approval

 

ORANGE CITY COUNCIL

 

Development Application No DA 234/2018(1)

 

NA20/                                                                   Container PR27695

 

 

DRAFT NOTICE OF DETERMINATION

OF A DEVELOPMENT APPLICATION

issued under the Environmental Planning and Assessment Act 1979

Section 4.18

 

Development Application

 

  Applicant Name:

Health Infrastructure on behalf of Health Administration Corporation

  Applicant Address:

C/- Peter Basha Planning and Development

PO Box 1827

ORANGE  NSW  2800

  Owner’s Name:

Health Administration Corporation

  Land to Be Developed:

Lot 2 DP 1230592 - 129-133 Sale Street, Orange

  Proposed Development:

Demolition of a Heritage Item (all buildings, structures and vegetation to be removed) and Category 1 Remediation (asbestos removal)

 

 

Building Code of Australia

 building classification:

 

Class to be determined by Certifier

 

 

Determination made under

  Section 4.16

 

  Made On:

To be advised

  Determination:

CONSENT GRANTED SUBJECT TO CONDITIONS DESCRIBED BELOW:

 

 

Consent to Operate From:

To be advised

Consent to Lapse On:

To be advised

 

Terms of Approval

 

The reasons for the imposition of conditions are:

(1)      To ensure a quality urban design for the development which complements the surrounding environment.

(2)      To maintain neighbourhood amenity and character.

(3)      To ensure compliance with relevant statutory requirements.

(4)      To provide adequate public health and safety measures.

(5)      To ensure the utility services are suitably managed during demolition of authorised buildings.

(6)      To prevent the proposed development having a detrimental effect on adjoining land uses.

(7)      To minimise the impact of development on the environment.

 

 

 

 

Conditions

 

(1)      The development must be carried out in accordance with:

 

(a)      Plans by Peter Basha Planning and Development – Reference 17067DA – Dated 28.06.2018 sheets 1 – 4 (inc. aerials) (8 sheets)


 

(b)      statements of environmental effects or other similar associated documents that form part of the approval

as amended in accordance with any conditions of this consent.

 

 

GENERAL CONDITIONS

 

(2)      This consent DOES NOT AUTHORISE ANY WORKS to occur to the portion of Caldwell House as shown in figure 1 below, shown in red and labelled "B". For the avoidance of doubt, this condition prevents the removal of asbestos, asbestos containing material or any other fabric from Caldwell House, being that portion of the building as shown in figure 1 below, shown in red and labelled "B". Separate approval is required for the clean-up/remediation of this part of this site.

A picture containing table, street, man, many

Description automatically generated

Figure 1 - significant buildings shown red and labelled "B"

 

(3)      The portion of Caldwell House as shown in figure 1 above shown in red and labelled "B" is not to be demolished.

 

 

PRESCRIBED CONDITIONS

 

(4)      A sign is to be erected in a prominent position on any site on which building work, subdivision work or demolition work is being carried out:

(a)      showing the name, address and telephone number of the principal certifying authority for the work, and

(b)      showing the name of the principal contractor (if any) for any building work and a telephone number on which that person may be contacted outside working hours, and

(c)      stating that unauthorised entry to the site is prohibited.

Any such sign is to be maintained while the building work, subdivision work or demolition work is being carried out.

 

 

PRIOR TO WORKS COMMENCING

 

(5)      A Demolition Noise and Vibration Management Plan (DNVMP) shall be prepared for the authorised demolition works. The DNVMP shall include the following “Management Measures” (as detailed in the Demolition Noise and Vibration Assessment by Wilkinson Murray Report no. 18085 Version B dated July 2018):

·           Demolition activities which are noise or vibration intensive shall only occur during normal construction hours i.e. between 7.00am – 6.00pm Monday to Friday, and 8.00am – 1.00pm Saturday, with no work on Sundays or public holidays.

·           Where practicable any particularly noisy works shall be staged with consideration to the least sensitive time of day for the closest receivers, providing respite periods as necessary.

·           Scheduling demolition activities to minimise multiple use of the noisiest equipment or plant items where practicable.

·           Strategic positioning of plant items and work areas to reduce the noise emission to noise sensitive receptors, where possible.

·           Ensuring demolition machinery engine covers are closed, equipment is well maintained and silencers/mufflers are used, including routine maintenance for major items of demolition equipment that are significant demolition noise contributors.

·           Provision of awareness training for contractors in environmental noise issues, as described above.

·           Community consultation with local residents/businesses shall be undertaken to assist in the alleviation of community concerns. This shall occur prior to works commencing and again prior to each intensive noise generating event where noise management levels are likely to be exceeded.

·           Maintaining a suitable complaints register. Should noise complaints be received, they must be immediately investigated and where appropriate, noise monitoring shall be undertaken at the locations concerned to determine compliance with the determined demolition noise limits. Reasonable and feasible measures would need to be implemented to reduce any noise impacts.

The DNVMP shall be submitted to Council's Director of Development Services for approval prior to works commencing on the site.

 

(6)      Air quality monitoring shall be undertaken in accordance with the Asbestos Removal Control Plan (ARCP) Air Monitoring Program submitted with the application and include (as a minimum) the following measures:

·           Daily air monitoring (control monitoring) shall be undertaken on the site during removal works.

·           The monitoring shall be undertaken in accordance with the Guidance Note on the Membrane Filter Method for Estimating Airborne Asbestos Dust, 2nd Edition [NOHSC:3003(2005)].

·           Air monitoring shall be undertaken by an independent asbestos assessor at fixed locations along boundaries representative of the work areas as determined by the independent asbestos assessor.

·           The frequency of control monitoring shall be daily for the duration of the asbestos removal work. Exposure (personal) monitoring will not be undertaken.

·           Clearance air monitoring shall be undertaken after removal works have been completed in the removal areas, decontamination area and loading bay.

·           Effectiveness and action of the monitoring results shall be undertaken in accordance with the Criteria for Asbestos Fibres Action Levels (SafeWork Australia 2011) (refer below insert for more detail).

(7)      Soil erosion control measures shall be implemented on the site prior to demolition works commencing.

 

(8)      Prior to the demolition works commencing, the applicant is to obtain an approval under Section 68 of the Local Government Act for the temporary closure of any footpath or roadway. A pedestrian/vehicle management plan is to accompany the application. Details are to be provided of the protective hoardings, fences and lighting that are to be used during demolition, excavation and building works in accordance with the requirements of the Occupational Health & Safety Act 2000, Australian Standard AS3798-1996 (Guidelines on Earthworks for Commercial and Residential Developments) and the WorkCover Authority.

Note:  On corner properties particular attention is to be given to the provision of adequate sight distances.

 

(9)      Prior to demolition works commencing, the applicant is to submit a waste management plan that describes the nature of wastes to be removed, the wastes to be recycled and the destination of all wastes. All wastes from the demolition phase of this project are to be deposited at a licensed or approved waste disposal site.

 

(10)    A temporary onsite toilet is to be provided and must remain throughout the project or until an alternative facility meeting Council’s requirements is available onsite.

 

(11)    Due to the extensive nature of the demolition works and their proximity to the public footpath, the applicant is to provide public liability and public risk insurance cover for a minimum of $10,000,000, endorsed to cover Council for its respective rights and interests. Evidence of valid insurance cover must be submitted to Council prior to works commencing on-site.

 

(12)    A dilapidation report(s) shall be prepared by a suitably qualified engineer and shall be submitted to Council prior to works commencing on-site. The report(s) shall address the current condition of all buildings that exist on land that is immediately adjoining the development site. A dilapidation report shall also be prepared for the existing building that is to remain on the subject land as part of this development.

This condition shall not apply in the event that access is refused by those property owners.

 

 

DURING DEMOLITION / SITEWORKS

 

(13)    The removal of all asbestos and asbestos containing material as authorised by this consent shall be carried out in accordance with the Asbestos Removal Control Plan – report no. R7040arcp2 prepared by EnviroWest dated 17 May 2018 and in accordance with Clause 452 of the Work Health and Safety Regulation 2017.

 

(14)    All necessary asbestos clearance certificates shall be furnished to Council within 7 days of being issued. 

 

(15)    All demolition work on the site is to be carried out in accordance with the Demolition Noise and Vibration Assessment report (Reference 18085 Version B) dated July 2018 prepared by Wilkinson Murray.

 

(16)    The wall that is proposed to be removed (forms part of existing carport) on the western boundary that is the common boundary of no. 78 Dalton Street shall be removed by manual labour as far as practicable. 

 

(17)    A replacement fence on the western boundary shared by no. 78 Dalton Street shall be constructed in similar materials and to a height commensurate with the wall that was removed. The construction of the fence shall commence within 28 Days from the date that the existing wall is removed and be completed within four weeks from the date of works commencing on the new wall.


 

(18)    If Aboriginal objects, relics, or other historical items or the like are located during development works, all works in the area of the identified object, relic or item shall cease, and the NSW Office of Environment and Heritage (OEH), and representatives from the Orange Local Aboriginal Land Council shall be notified. Where required, further archaeological investigation shall be undertaken. Development works in the area of the find(s) may recommence if and when outlined by the management strategy, developed in consultation with and approved by the OEH.

 

(19)    In the event of an unexpected find during works such as (but not limited to) the presence of undocumented waste, odorous or stained soil, asbestos (above expected levels as detailed in the submitted documentation), structures such as underground storage tanks, slabs, or any contaminated or suspect material, all work on site must cease immediately.  The beneficiary of the consent must discuss with Council the appropriate process that should be followed therein.  Works on site must not resume unless the express permission of the Director Development Services is obtained in writing.

 

(20)    All construction/demolition work on the site is to be carried out between the hours of 7.00 am and 6.00 pm Monday to Friday inclusive, 7.00 am to 5.00 pm Saturdays and 8.00 am to 5.00 pm Sundays and Public Holidays. Written approval must be obtained from the General Manager of Orange City Council to vary these hours.

 

(21)    Building demolition is to be carried out in accordance with Australian Standard 2601:2001 - The Demolition of Structures and the requirements of Safe Work NSW.

 

(22)    Asbestos containing building materials must be removed in accordance with the provisions of the Work Health and Safety Act 2011 and any guidelines or Codes of Practice published by Safe Work NSW, and disposed of at a licenced landfill in accordance with the requirements of the NSW EPA.

 

(23)    Any adjustments to existing utility services that are made necessary by this development proceeding are to be at the full cost of the developer.

 

(24)    The existing sewer connections to the buildings authorised to be demolished are to be capped off at the sewer main by Council at Developer’s cost.

 

(25)    The existing water services to the buildings authorised to be demolished are to be sealed off at their respective Council mains by Council at the developer’s cost.

 

(26)    All of the foregoing conditions are to be at the full cost of the developer and to the requirements and standards of the Orange City Council Development and Subdivision Code, unless specifically stated otherwise.

 

 

REQUIREMENTS OF ESSENTIAL ENERGY

 

(1)      If the proposed development changes, there may be potential safety risks and it is recommended that Essential Energy is consulted for further comment;

 

(2)      Any existing encumbrances in favour of Essential Energy (or its predecessors) noted on the title of the above property should be complied with;

 

(3)      Essential Energy’s records indicate there is electricity infrastructure located within the property. Any activities within this location must be undertaken in accordance with the latest industry guideline currently known as ISSC 20 Guideline for the Management of Activities within Electricity Easements and Close to Infrastructure.

 

(4)      Prior to carrying out any works, a “Dial Before You Dig” enquiry should be undertaken in accordance with the requirements of Part 5E (Protection of Underground Electricity Power Lines) of the Electricity Supply Act 1995 (NSW).


 

(5)      Given there is electricity infrastructure in the area, it is the responsibility of the person/s completing any works around powerlines to understand their safety responsibilities. SafeWork NSW (www.safework.nsw.gov.au) has publications that provide guidance when working close to electricity infrastructure. These include the Code of Practice – Work near Overhead Power Lines and Code of Practice – Work near Underground Assets.

 

 

 

Other Approvals

 

(1)      Local Government Act 1993 approvals granted under Section 68.

          Nil

(2)      General terms of other approvals integrated as part of this consent.

          Nil

 

 

 

Right of Appeal

 

If you are dissatisfied with this decision, Section 8.7 of the Environmental Planning and Assessment Act 1979 gives you the right to appeal to the Land and Environment Court. Pursuant to Section 8.10, an applicant may only appeal within 6 months after the date the decision is notified.

 

  Disability Discrimination Act 1992:

This application has been assessed in accordance with the Environmental Planning and Assessment Act 1979. No guarantee is given that the proposal complies with the Disability Discrimination Act 1992.

 

The applicant/owner is responsible to ensure compliance with this and other anti-discrimination legislation.

 

The Disability Discrimination Act covers disabilities not catered for in the minimum standards called up in the Building Code of Australia which references AS1428.1 - "Design for Access and Mobility". AS1428 Parts 2, 3 and 4 provides the most comprehensive technical guidance under the Disability Discrimination Act currently available in Australia.

 

  Disclaimer - S88B of the Conveyancing Act 1919 - Restrictions on the Use of Land:

The applicant should note that there could be covenants in favour of persons other than Council restricting what may be built or done upon the subject land. The applicant is advised to check the position before commencing any work.

 

 

Signed:

On behalf of the consent authority ORANGE CITY COUNCIL

 

 

Signature:

 

 

Name:

 

PAUL JOHNSTON - MANAGER DEVELOPMENT ASSESSMENTS

 

Date:

 

To be advised

 

 



Planning and Development Committee                                                                                  7 July 2020

Attachment 2      Plans

PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator



Planning and Development Committee                                                                                 7 July 2020

Attachment 3      Submissions

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


Planning and Development Committee                                                        7 July 2020

2.3     Development Application DA 120/2020(1) - 52-54 Bathurst Road, and 25 and 27 Eyles Street (Taco Bell)

RECORD NUMBER:       2020/1005

AUTHOR:                       David Paine, Senior Planner    

 

 

EXECUTIVE Summary

Application lodged

25 March 2020

Applicant/s

McDuck Properties Pty Limited

Owner/s

Thomsons Corner Pty Limited

Land description

Lot 507 DP 712206, Lots 3 and 4 DP 37362 – 52‑54 Bathurst Road, and 25 and 27 Eyles Street, Orange

Proposed land use

Takeaway Food and Drink Premises and Signage

Value of proposed development

$1,100,000

Council's consent is sought for the construction of a Takeaway Food and Drink Premises and associated Signage on land described as Lot 507, DP 712206 and Lots 3 and 4, and DP 37362. The land is known as 52–54 Bathurst Road, and 25 and 27 Eyles Street, Orange. The subject site is known as the former Thompson’s Nursery site.

A previous Development Application was approved by Council’s Sustainable Development Committee Meeting on 1 April 2014 (DA 134/2013 (1)). The previous application was for a business premises (car wash), restaurant or café (two tenancies), subdivision and signage. The consent remains valid because of physical commencement that has been undertaken to activate the consent.

This application involves the construction of a Takeaway Food and Drink Premises and comprises of the following scope of works: construction of Takeaway Food and Drink Premises with seating for 42 seats; construction of an at-grade car park for 24 vehicles including three (3) staff parking spaces; drive-thru facility, including queuing for nine (9) vehicles; acoustic fence constructed along the southern and western boundary and removal of a street tree on Eyles Street.

The proposal is seeking consent to operate from Sunday to Thursday from 10am to 10pm and from 10am to 11pm on Friday and Saturday.

The proposed development was publicly notified and advertised in accordance with the Council’s Community Participation Plan and one submission was received in response.

The subject land is located within the high profile eastern entry to the business area of the City; the subject land also adjoins the rear yards of properties within the heritage conservation area and is opposite the heritage item, Memory Park.

With the above in mind it is considered the development will present appropriately to the street and will not unreasonably impact upon the heritage significance of both the adjoining conservation area and the heritage item opposite the site.

Council sought the concurrence of Transport for NSW (previously knowns as RMS) which has been obtained and their requirements have been integrated as conditions of consent within the attached notice.

As such, the development is recommended for approval.


 

 

Figure 1 - locality plan

DECISION FRAMEWORK

Development in Orange is governed by two key documents: the Orange Local Environment Plan 2011 and the Orange Development Control Plan 2004. In addition, the Infill Guidelines are used to guide development, particularly in the heritage conservation areas and around heritage items.

Orange Local Environment Plan 2011 – The provisions of the LEP must be considered by the Council in determining the application. LEPs govern the types of development that are permissible or prohibited in different parts of the City and also provide some assessment criteria in specific circumstances. Uses are either permissible or not. The objectives of each zoning and the aims of the LEP itself are also to be considered and can be used to guide decision making around appropriateness of development.

Orange Development Control Plan 2004 – The DCP provides guidelines for development. In general, it is a performance based document rather than prescriptive in nature. For each planning element there are often guidelines used. These guidelines indicate ways of achieving the planning outcomes. It is thus recognised that there may also be other solutions of merit. All design solutions are considered on merit by planning and building staff. Applications should clearly demonstrate how the planning outcomes are being met where alternative design solutions are proposed. The DCP enables developers and architects to use design to achieve the planning outcomes in alternative ways.


 

Director’s comments

Key issues in the assessment of this application relate to traffic and noise impacts, signage and how the development fits generally within the streetscape and surrounding locality.  Some of these issues are highlighted more in this case as the commercial site adjoins residential land.  The issues have been addressed in the body of this report and conditions of consent to mitigate identified issues have been recommended by staff.

It is recommended that Council supports the proposal subject to the adoption of the attached Notice of Determination.

Link To Delivery/OPerational Plan

The recommendation in this report relates to the Delivery/Operational Plan strategy “10.1 Preserve - Engage with the community to ensure plans for growth and development are respectful of our heritage”.

Financial Implications

Nil

Policy and Governance Implications

Nil

 

Recommendation

That Council consents to Development Application DA 120/2020(1) for Takeaway Food and Drink Premises and Signage at Lot 507 DP 712206, and Lots 3 and 4 DP 37362 – 52‑54 Bathurst Road, Orange, and 25 and 27 Eyles Street, Orange pursuant to the conditions of consent in the attached Notice of Approval.

 

further considerations

Consideration has been given to the recommendation’s impact on Council’s service delivery; image and reputation; political; environmental; health and safety; employees; stakeholders and project management; and no further implications or risks have been identified.

SUPPORTING INFORMATION

Council's consent is sought for a Takeaway Food and Drink Premises and associated Signage at Lot 507 DP 712206, and Lots 3 and 4 DP 37362. The land is known as 52–54 Bathurst Road, and 25 and 27 Eyles Street, Orange.

THE PROPOSAL

The development involves the construction of a Takeaway food and drink premise and comprises of the following scope of works:

·      clearing the site

·      construction of Takeaway Food and Drink Premises with seating for 42 seats

·      construction of an at-grade car park for 24 vehicles including three (3) staff parking spaces


 

·      drive-thru facility, including queuing for nine (9) vehicles

·      acoustic fence constructed along the southern and western boundaries

·      associated signage

·      vehicle access will be via the existing driveway on Bathurst Road and via a new entry driveway on Eyles Street

·      removal of a street tree on Eyles Street

·      loading dock facilities

·      site landscaping.

The proposal is seeking consent to operate from Sunday to Thursday from 10am to 10pm and 10am to 11pm on Friday and Saturday.

MATTERS FOR CONSIDERATION

Section 1.7 - Application of Part 7 of the Biodiversity Conservation Act 2016 and Part 7A of the Fisheries Management Act 1994

Section 1.7 of the EP&A Act identifies that Part 7 of the Biodiversity Conservation Act 2016 (BC Act) and Part 7A of the Fisheries Management Act 1994 have effect in connection with terrestrial and aquatic environments.

There are four triggers known to insert a development into the Biodiversity Offset Scheme (i.e. the need for a BDAR to be submitted with a DA):

·    Trigger 1: development occurs in land mapped on the Biodiversity Values Map (OEH) (clause 7.1 of BC Regulation 2017);

·    Trigger 2: development involves clearing/disturbance of native vegetation above a certain area threshold (clauses 7.1 and 7.2 of BC Regulation 2017); or

·    Trigger 3: development is otherwise likely to significantly affect threatened species (clauses 7.2 and 7.3 of BC Act 2016).

The fourth trigger (development proposed to occur in an Area of Outstanding Biodiversity Value (clause 7.2 of BC Act 2016) is generally not applicable to the Orange LGA; as no such areas are known to occur in the LGA. No further comments will be made against the fourth trigger.

Trigger 1

The site is not mapped on the Biodiversity Values Map.

Trigger 2

In consideration of the second trigger, the prescribed clearing threshold for the site is 0.25 hectares pursuant to Clause 7.2 of the Biodiversity Conservation Regulation 2016. The site does not contain any significant vegetation and does not require the clearing of native vegetation.

Trigger 3

The subject land has been zoned for commercial purposes and does not contain or adjoin any land that has been mapped as containing biodiversity significance. The development is unlikely to adversely fragment or disturb the biodiversity structure or ecological functions of the development site or surrounding lands.


 

Section 4.15

Section 4.15 of the Environmental Planning and Assessment Act 1979 requires Council to consider various matters, of which those pertaining to the application are listed below.

PROVISIONS OF ANY ENVIRONMENTAL PLANNING INSTRUMENT s4.15(1)(a)(i)

Orange Local Environmental Plan 2011

Part 1 - Preliminary

Clause 1.2 - Aims of Plan

The broad aims of the LEP are set out under subclause 2. Those relevant to the application are as follows:

(a)     to encourage development which complements and enhances the unique character of Orange as a major regional centre boasting a diverse economy and offering an attractive regional lifestyle,

(b)     to provide for a range of development opportunities that contribute to the social, economic and environmental resources of Orange in a way that allows present and future generations to meet their needs by implementing the principles for ecologically sustainable development,

(f)      to recognise and manage valued environmental heritage, landscape and scenic features of Orange.

The application is considered to be consistent with aims (a), (b) and (f) listed above.

Clause 1.6 - Consent Authority

This clause establishes that, subject to the Act, Council is the consent authority for applications made under the LEP.

Clause 1.7 - Mapping

The subject site is identified on the LEP maps in the following manner:

Land Zoning Map:

Land zoned B6 Enterprise Corridor Zone.

Lot Size Map:

No Minimum Lot Size

Heritage Map:

Not a heritage item or within a conservation area

Height of Buildings Map:

No building height limit

Floor Space Ratio Map:

No floor space limit

Terrestrial Biodiversity Map:

No biodiversity sensitivity on the site

Groundwater Vulnerability Map:

Groundwater vulnerable

Drinking Water Catchment Map:

Not within the drinking water catchment

Watercourse Map:

Not within or affecting a defined watercourse

Urban Release Area Map:

Not within an urban release area

Obstacle Limitation Surface Map:

No restriction on building siting or construction

Additional Permitted Uses Map:

No additional permitted use applies

Flood Planning Map:

Within a flood planning area

Those matters that are of relevance are addressed in detail in the body of this report.


 

Clause 1.9A - Suspension of Covenants, Agreements and Instruments

This clause provides that covenants, agreements and other instruments which seek to restrict the carrying out of development do not apply with the following exceptions:

·    covenants imposed or required by Council

·    prescribed instruments under Section 183A of the Crown Lands Act 1989

·    any conservation agreement under the National Parks and Wildlife Act 1974

·    any trust agreement under the Nature Conservation Trust Act 2001

·    any property vegetation plan under the Native Vegetation Act 2003

·    any biobanking agreement under Part 7A of the Threatened Species Conservation Act 1995

·    any planning agreement under Division 6 of Part 4 of the Environmental Planning and Assessment Act 1979.

Figure 2 – sewer line

A sewer main traverses the subject property along the northern boundary of Lot 3. The design of the development is such that all of the building will avoid the sewer main. However, it may be necessary for the buildings closest to the sewer main to require piers. An easement traverses the centre and rear of Lot 4 and part of the rear of Lot 3. This easement was established to cater for the redirection of the sewer main under the former development that was previously approved. It will be necessary for this easement to be extinguished. The title of the subject property is not affected by any of the above.


 

Part 2 - Permitted or Prohibited Development

Clause 2.1 - Land Use Zones and Clause 2.3 - Zone Objectives and Land Use Table

The subject site is located within the B6 Enterprise Corridor Zone. The proposed development is defined as a Takeaway Food and Drink Premises and signage under OLEP 2011 and is permitted with consent for this zone.

Pursuant to the LEP dictionary;

Take away food and drink premises means premises that are predominantly used for the preparation and retail sale of food or drink (or both) for immediate consumption away from the premises.

Signage means any sign, notice, device, representation or advertisement that advertises or promotes any goods, services or events and any structure or vessel that is principally designed for, or that is used for, the display of signage, and includes any of the following:

(a)     an advertising structure,

(b)     a building identification sign,

(c)     a business identification sign,

but does not include a traffic sign or traffic control facilities.

Clause 2.3 of LEP 2011 references the Objectives for each zone in LEP 2011. These objectives for land zoned B6 Enterprise Corridor are as follows:

1 - Objectives of the B6 Enterprise Corridor Zone

·    To promote businesses along main roads and to encourage a mix of compatible uses.

·    To provide a range of employment uses (including business, office, retail and light industrial uses).

·    To maintain the economic strength of centres by limiting retailing activity.

·    To provide for residential uses, but only as part of a mixed use development.

The development is considered appropriate within the zone and will allow for additional employment in the hospitality sector within the City (associated with the Takeaway Food and Drink Premises uses). The development will not jeopardise the economic strength of the CBD with the retail component limited to food and drink premise uses which are not atypical for the locality.

No residential uses are proposed as part of this development.

Clause 2.6 Subdivision – consent requirements

This clause triggers the need for development consent for the subdivision of land. Whilst the proposal has not specifically nominated that the subject land will be consolidated, this issue has been discussed with the applicant and is standard practice when development is occurring over separate parcels of land. A number of conditions are recommended to ensure that proof of lodgement for registration of a survey plan of consolidation of Lot 507, DP 712206, Lots 3 and 4 DP 37362 with NSW Government Land and Property Information has been undertaken prior to the issue of a Construction Certificate, with formal registration of the plan to occur prior to the issue of an Occupation Certificate.


 

Part 3 - Exempt and Complying Development

The application is not exempt or complying development.

Part 4 - Principal Development Standards

The LEP Principal Development Standards do not apply to this application.

Part 5 - Miscellaneous Provisions

5.10 - Heritage Conservation

(1)     Objectives

          The objectives of this clause are as follows:

(a)     to conserve the environmental heritage of Orange,

(b)     to conserve the heritage significance of heritage items and heritage conservation areas, including associated fabric, settings and views,

(c)     to conserve archaeological sites,

(d)     to conserve Aboriginal objects and Aboriginal places of heritage significance.

The development is not located within a heritage conservation area, nor is the land identified as a heritage item or draft heritage item. The land does, however, adjoin the rear of properties within the Glenroi Heritage Conservation Area and is opposite a Heritage Item identified as Memory Park, with other heritage Items in the vicinity including Bowen Terrace, Wolaroi and 171 Edward Street. As such, it is important to assess the likely impact upon the heritage significance of the conservation area and primarily the heritage item opposite the subject land. Council’s Heritage Advisor has provided the following advice in relation to the proposed development.

Glenroi HCA

In terms of the impacts to the heritage conservation area the proposed development is likely to have a minimal impact. The development is located to the rear of the properties within the conservation area and the development will not be overly visible from within McLachlan Street, nor will it unreasonably impact upon the heritage significance of individual dwellings within the conservation area.

Memory Park

Orange Heritage Inventory describes the significance of Memory Park as follows:

An important visual and historic landscape on the main road and one of the key entry points to the City, the park includes mature tree planting, a watercourse and a range of civic improvements valued by the local community.

The heritage advice centred on a number of minor design suggestions intended to improve the presentation of the development and its relationship to the heritage item and the highway.

It is important to make the point that the development has been designed around an attempt to achieve the required noise criterion so there is a balance to be weighed between heritage considerations and allowing commercial development to occur on a commercially zoned site which adjoins sensitive residential receivers.


 

Heritage Advisor’s Recommendations

1.       The pylon sign (S01) is in very close proximity to the proposed building and its two identical taco bell graphics and the sign/pylon height is very similar to the building. The pylon sign therefore duplicates the graphic of the taco bell applied to the building and adds complexity to the bulk and scale of the building in the vicinity. It is therefore recommended that the pylon sign be deleted from the proposal.

Applicant’s Response

The pylon sign is integral to the branding and marketing of the Taco Bell which does not rely solely on building façade signage. Its location and size (ie: height) was influenced by the existing signage (including existing pylon signs) along Bathurst Road. It is considered that the proposed signage is compatible with the desired character of the area and is consistent with the current signage in the immediate precinct along Bathurst Road including.

(i)      the existing pylon signage on the adjacent BP Service Station site

(ii)     the pylon sign and associates signage for McDonalds

(iii)    the pylon sign and associated signage for KFC

(iv)    the pylon sign and associated signage for Red Rooster

(v)     the pylon sign and associated signage for 7-Eleven Service Station

(vi)    the pylon sign and associated signage for Hungry Jacks.

Planning Officer’s Response

The proposed pylon sign certainly adds to the complexity of the bulk and scale of the building. The subject sign extends above the height of the subject building which is of some concern. The applicant argues that the proposed pylon sign has been designed to be integrated into the building and forms part of the overall building design. Despite the bulk of this particular element, it is considered acceptable in this case on the basis that building and associated signage is well setback from Bathurst Road frontage, is recessive in colour and partly screened by the existing street trees in Bathurst Road and Eyles Street. Further, it is acknowledged that the submitted plans show that the pylon sign only contains an image of a bell and a small amount of written text. Overall, the signage design is considered to be consistent with the overall height of other pylon type signs in the locality and is therefore acceptable in this context.

Heritage Advisor’s Recommendations

2.       Pedestrian access is a feature of Orange and the footpaths are immediately available on both sides of Bathurst Road. Memory Park is a common destination opposite the subject site. It is recommended that consideration is given to a pedestrian access from Bathurst Road in the location next to the Taco Bell porch entry with the banner sign (S02) being relocated to the north western portion of the site. The pedestrian access is to be provided with appropriate rumble or similar safety measures to protect pedestrians from vehicles.


 

Planning Officer’s Comments:

The plans have been amended to include a pedestrian access from Bathurst Road. The internal driveway design should ensure low speed traffic movements to facilitate pedestrian safety from Bathurst Road into the site.

Heritage Advisor’s Recommendations

3.       Replica materials are not supported in the Orange Conservation Areas and in areas with urban design quality and visual prominence. The integrity of materials and in particular timber from which many traditional buildings are fabricated is valued and protected.

An alternate plain powder coat or anodised finish for the aluminium cladding proposed for the North and East elevations is an option as is another/alternate wood composite board cladding type product such as Urbanline Euro dark cedar Selkta or equal.

Applicant’s Response:

A number of high quality products were considered for the project with the final mix notated on the architectural plans. The nominated materials are standard for all Taco Bell stores and represent the best and most durable materials that are available. In order to maintain consistence for the brand, Council can appreciate that this is to be reflected in the selected materials which are also being implemented in the proposed Bathurst store (which is in a Heritage Conservation Area) and the proposed Tamworth store (which has been approved).

Planning Officer’s Comments:

The material and colours proposed by the applicant are considered “corporate materials”. Whilst not ideal given the location of the site in a high profile area and positioned on the fringe of the heritage conservation area, the fact that the building incorporates recessive colours, is well setback from Bathurst Road by around 9m and partly screened by the existing street trees in Bathurst Road renders the design acceptable. Adequate landscaping will assist with integrating the building within the streetscape. The material and colour proposed are considered acceptable in this setting.

Heritage Advisor’s Recommendations

4.       The colour for the perimeter fencing should be similar to Windspray to best reflect and background the adjoining planting.

Planning Officer’s Comments:

A condition has been included in the draft conditions to ensure compliance with this request.

Heritage Advisor’s Recommendations

5.       An additional tree should be provided to the northern end of the Eyles Street boundary planting at a similar spacing to the adjoining two proposed trees with the objective of screening the car park and loading bay areas in the vicinity.


 

Applicant’s Response:

An additional tree is not supported as this would screen and obscure the building from the street.

Planning Officer’s Comments:

The landscape plan and recommended conditions incorporates tree planting that would assist in reducing the perceived bulk of the development and would provide for increased screening for adjoining properties. On balance, it is considered that the proposed landscaping for the site as amended by conditions of consent will ensure a good quality design which will complement the aesthetic quality and amenity for the development and surrounds.

Heritage Advisor’s Recommendations

6.       An additional tree should be provided in the northern corner of the lawn space next to the Plant screen space, so as to increase the tall background planting to the south and west of the site and building while improving the screening to the service spaces.

Applicant’s Response:

The landscape plan will be amended to add the additional tree.

Planning Officer’s Comments:

A condition has been included in the draft conditions of consent that requires the planting of an additional tree. The landscape plan incorporates tree planting that would assist in reducing the perceived bulk of the development and would provide for increased screening for adjoining properties. On balance, it is considered that the proposed landscaping for the site is of a good quality design and would complement the aesthetic quality and amenity for the development and surrounds.

Heritage Advisor’s Recommendations

8.       The driveway surfaces including the new apron crossovers to Bathurst and Eyles Streets are to utilize Charcoal pigment to produce a dark grey coloured concrete consistent with the traditional Basalt colour in Orange.

Applicant’s Response:

The internal car park will be bitumen sealed and therefore pigmenting is not an option. The crossovers will be concrete but should not be pigmented as they will clash with the existing concrete footpaths and kerb and gutter.

Planning Officer’s Comments:

It is considered that the proposed bitumen seal would provide a dark colouring which is adequate for this development in its heritage context.


 

Part 7 - Additional Local Provisions

7.1 - Earthworks

This clause establishes a range of matters that must be considered prior to granting development consent for any application involving earthworks, such as:

 

(a)     the likely disruption of, or any detrimental effect on, existing drainage patterns and soil stability in the locality of the development

(b)     the effect of the development on the likely future use or redevelopment of the land

(c)     the quality of the fill or the soil to be excavated, or both

(d)     the effect of the development on the existing and likely amenity of adjoining properties

(e)     the source of any fill material and the destination of any excavated material

(f)     the likelihood of disturbing relics

(g)     the proximity to and potential for adverse impacts on any waterway, drinking water catchment or environmentally sensitive area

(h)     any measures proposed to minimise or mitigate the impacts referred to in paragraph (g).

The earthworks proposed in the application are limited to the extent of cutting and filling required for the proposed Takeaway Food and Drink Premise and associated site works. The extent of disruption to the drainage of the site is considered to be minor and will not detrimentally affect adjoining properties or receiving waterways.

The extent of the earthworks will not materially affect the potential future use or redevelopment of the site that may occur at the end of the proposed development's lifespan.

The site is not known to be contaminated, nor is the site known to contain any Aboriginal, European or Archaeological relics. Previous known uses of the site do not suggest that any relics are likely to be uncovered. However, conditions are imposed to ensure that should site works uncover a potential relic or artefact, works will be halted to enable proper investigation by relevant authorities and the proponent required to seek relevant permits to either destroy or relocate the findings.

The earthworks will be appropriately supported onsite and the change in ground level is not substantial. Therefore the effect on the amenity of adjoining properties is considered to be minor.

The site is not in proximity to any waterway, drinking water catchment or sensitive area. Conditions will be imposed to require a sediment control plan, including silt traps and other protective measures, to ensure that loose dirt and sediment does not escape the site boundaries.


 

7.2 - Flood Planning

This clause applies to land identified on the Flood Planning Map as a Flood Planning Area and requires that, before any consent is issued, Council must be satisfied that the proposal:

(a)     is compatible with the flood hazard of the land, and

(b)     is not likely to significantly adversely affect flood behaviour resulting in detrimental increases in the potential flood affectation of other development or properties, and

(c)     incorporates appropriate measures to manage risk to life from flood, and

 

(d)     is not likely to significantly adversely affect the environment or cause avoidable erosion, siltation, destruction of riparian vegetation or a reduction in the stability of river banks or watercourses, and

(e)     is not likely to result in unsustainable social and economic costs to the community as a consequence of flooding.

A flood level and freeboard were established as part of the assessment of the previously approved business premise and have been used as part of this development for the building. Council’s Technical Services Division have recommended a condition of consent be attached to the notice of approval that requires the plans to be amended to reduce the height of the proposed car park to the existing natural surface levels. This will ensure that the proposed development is unlikely to change flooding regimes on or off the site and would be unlikely to cause or contribute to erosion, siltation or reduce riparian vegetation. Revised building and engineering plans with amended levels will therefore need to be submitted with any construction certificate. The revised levels will need to address any resultant grade changes so as to maintain appropriate access.

7.3 - Stormwater Management

This clause applies to all industrial, commercial and residential zones and requires that Council be satisfied that the proposal:

(a)     is designed to maximise the use of water permeable surfaces on the land having regard to the soil characteristics affecting onsite infiltration of water

(b)     includes, where practical, onsite stormwater retention for use as an alternative supply to mains water, groundwater or river water; and

(c)     avoids any significant impacts of stormwater runoff on adjoining downstream properties, native bushland and receiving waters, or if that impact cannot be reasonably avoided, minimises and mitigates the impact.

The proposal has been designed to include permeable surfaces and includes onsite retention of stormwater through the use of detention basins. It is therefore considered that stormwater management is satisfactory.


 

7.6 - Groundwater Vulnerability

This clause seeks to protect hydrological functions of groundwater systems and protect resources from both depletion and contamination. Orange has a high water table and large areas of the LGA, including the subject site, are identified with “Groundwater Vulnerability” on the Groundwater Vulnerability Map. This requires that Council consider:

(a)     whether or not the development (including any onsite storage or disposal of solid or liquid waste and chemicals) is likely to cause any groundwater contamination or have any adverse effect on groundwater dependent ecosystems, and

(b)     the cumulative impact (including the impact on nearby groundwater extraction for potable water supply or stock water supply) of the development and any other existing development on groundwater.

 

Furthermore, consent may not be granted unless Council is satisfied that:

(a)     the development is designed, sited and will be managed to avoid any significant adverse environmental impact, or

(b)     if that impact cannot be reasonably avoided - the development is designed, sited and will be managed to minimise that impact,

(c)     if that impact cannot be minimised - the development will be managed to mitigate that impact.

The proposal is not anticipated to involve the discharge of toxic or noxious substances and is therefore unlikely to contaminate the groundwater or related ecosystems. The proposal does not involve extraction of groundwater and will therefore not contribute to groundwater depletion. The design and siting of the proposal has sought to avoid impacts on groundwater and is therefore considered acceptable.

The applicant will be required to enter into a trade waste agreement with Council in relation to the discharge of liquids associated with the Takeaway food and drink premise.

Clause 7.11 - Essential Services

Clause 7.11 applies and states:

Development consent must not be granted to development unless the consent authority is satisfied that any of the following services that are essential for the proposed development are available or that adequate arrangements have been made to make them available when required:

(a)     the supply of water,

(b)     the supply of electricity,

(c)     the disposal and management of sewage,

(d)     storm water drainage or onsite conservation,

(e)     suitable road access.

In consideration of this clause, all utility services are available to the land and are adequate for the proposal.

STATE ENVIRONMENTAL PLANNING POLICIES

State Environmental Planning Policy 55 Remediation of Land

State Environmental Planning Policy 55 - Remediation of Land (SEPP 55) is applicable. Pursuant to Clause 7 Contamination and remediation to be considered in determining development application:

(1)     A consent authority must not consent to the carrying out of any development on land unless:

(a)     it has considered whether the land is contaminated, and

(b)     if the land is contaminated, it is satisfied that the land is suitable in its contaminated state (or will be suitable, after remediation) for the purpose for which the development is proposed to be carried out, and

(c)     if the land requires remediation to be made suitable for the purpose for which the development is proposed to be carried out, it is satisfied that the land will be remediated before the land is used for that purpose.

The previous use of 52-54 Bathurst Road and 27 Eyles Street was for the purpose of a plant nursery, locally known as Thomson’s Nursery. The previous use is not considered to raise any concerns regarding potential contamination. The proposal is considered acceptable under the above policy.

State Environmental Planning Policy 64 - Advertising and Signage

State Environmental Planning Policy 64 - Advertising and Signage (SEPP 64) is applicable and states in part:

3        Aims, Objectives etc

(1)     This Policy aims:

(a)     to ensure that signage (including advertising):

(i)      is compatible with the desired amenity and visual character of an area, and

(ii)     provides effective communication in suitable locations, and

(iii)    is of high quality design and finish, and

(8)     Granting of Consent to Signage

A consent authority must not grant development consent to an application to display signage unless the consent authority is satisfied:

(a)     that the signage is consistent with the objectives of this Policy as set out in Clause 3 (1) (a), and

(b)     that the signage the subject of the application satisfies the assessment criteria specified in Schedule 1.

The proposal includes a banner sign and two illuminated entry signs for each access on both Bathurst Road and Elyes Street. The four illuminated entry signs (2.1m high – two at each entry/exit point) and the proposed banner sign along the Bathurst Road street frontage will result in a proliferation of signage along the street frontages and is therefore not supported.

 

Further, Council’s Technical Services Division have supported this position and have advised that the proposed entry/exit signage in particular should be removed due to traffic safety concerns indicating that all signage at these points should be limited to traffic directional signage that is approved by Transport for NSW.  The submitted plans show that the banner signage has no content at this stage and is likely to be used for product advertising over time which is prohibited in any event under the provisions of the SEPP. In order to restrain the extent of signage on what is an important site on the entrance to the CBD attached is a condition of consent that requires the entry exit signage and the banner sign along Bathurst Road frontage to be removed. Given that the pylon sign and branding of the building have been supported, it is considered that the deletion of the entry signs and the banner is appropriate for the site.

The amended signage subject to the adoption of the recommendation are considered to consistent with the aims and objectives of the plan.

 

1 - Character of the Area

·    Is the proposal compatible with the existing or desired future character of the area or locality in which it is proposed to be located?

·    Is the proposal consistent with a particular theme for outdoor advertising in the area or locality?

The area is characterised as a mix of commercial and established residential properties with signage primarily associated with the commercial uses and some educational uses such as Wolaroi school signage. The character of the area is also influenced by the proximity of the Glenroi Heritage Conservation Area and the nearby heritage items (particularly Memory Park opposite). The character of the land is further influenced by its high profile location on the entrance to the business area of the City.

Given the above, it is considered important to protect the character of the area by ensuring that any signage is consistent with the requirements of the SEPP. The proposed signage subject to the adoption of the recommended conditions of consent discussed above will ensure that the signage is consistent with existing character of the area.

2 - Special Areas

·    Does the proposal detract from the amenity or visual quality of any environmentally sensitive areas, heritage areas, natural or other conservation areas, open space areas, waterways, rural landscapes or residential areas?

Whilst the subject land is not within a residential zoning, nor is it within a heritage conservation area or a listed item, the land does adjoin a residential zoning and is located between a heritage conservation area and a heritage item.

Therefore, it is the opinion of Council staff that the land, in terms of the application of the SEPP, is considered a special area by virtue of the land’s proximity to the residential land and heritage conservation area and heritage item. To this end, the signage within the development is to be limited to business identification signage only. This is consistent with the provisions of the DCP in relation to this site. Further the recommended conditions will ensure that signage is acceptable for this precinct.

3 - Views and Vistas

·    Does the proposal obscure or compromise important views?

·    Does the proposal dominate the skyline and reduce the quality of vistas?

·    Does the proposal respect the viewing rights of other advertisers?

The proposed signage, apart from the 8.3m pylon and other signage discussed above is shown to be limited to flush wall signage and, as such will not obscure or compromise important views, nor will it dominate the skyline or jeopardise the viewing rights of other signs in the area. In terms of the 8.3m pylon sign, the sign is sited in a manner that will not impact upon views and is a height commensurate with the height of the proposed building and other pylon signage located along Bathurst Road.  It is considered that proposed pylon signage will not dominate the skyline, nor reduce the quality of important view corridors.

 

4 - Streetscape, Setting or Landscape

·    Is the scale, proportion and form of the proposal appropriate for the streetscape, setting or landscape?

·    Does the proposal contribute to the visual interest of the streetscape, setting or landscape?

·    Does the proposal reduce clutter by rationalising and simplifying existing advertising?

·    Does the proposal screen unsightliness?

·    Does the proposal protrude above buildings, structures or tree canopies in the area or locality?

·    Does the proposal require ongoing vegetation management?

As indicated above, the proposal included a banner sign and four large directional signage on both the Bathurst Road and Eyles Street entry/exist. A condition has been included in the attached Notice to remove the banner sign and entry exit signs completely. The overall scale, proportions and forms of the remaining signage are appropriate within the context of the setting.

Landscaping on the site has been designed as part of the overall proposal, and low maintenance vegetation and grasses will be planted around the pylon signage.

5 - Site and Building

·    Is the proposal compatible with the scale, proportion and other characteristics of the site or building, or both, on which the proposed signage is to be located?

·    Does the proposal respect important features of the site or building, or both?

·    Does the proposal show innovation and imagination in its relationship to the site or building, or both?

As discussed above the proposed entry/exit signage and the banner sign along Bathurst Road are not supported. The remaining signage is considered to be compatible with the scale, proportion and other characteristics of the site and proposed buildings on the land. The proposed level of signage subject to the adoption of the recommended conditions is not unreasonable for this type of land use.

6 - Associated Devices and Logos with Advertisements and Advertising Structures

·    Have any safety devices, platforms, lighting devices or logos been designed as an integral part of the signage or structure on which it is to be displayed?

The proposed signage does not include any safety devices, platforms or lighting devices that form an integral part of the signage or structure on which it is to be displayed. The proposed signage includes a corporate logo in the design, which meets the definition of business identification signage.

7 - Illumination

·    Would illumination result in unacceptable glare?

·    Would illumination affect safety for pedestrians, vehicles or aircraft?

·    Would illumination detract from the amenity of any residence or other form of accommodation?

·    Can the intensity of the illumination be adjusted, if necessary?

·    Is the illumination subject to a curfew?

The proposed illumination is considered acceptable. Attached is a condition of consent which requires all lighting associated with the signage to be designed in accordance with AS4282 1997 - Control of the Obtrusive Effects of Outdoor Lighting.

The illumination of signage is unlikely to create an adverse impact for users of Bathurst Road, nor existing dwellings in the vicinity of the subject land.

8 - Safety

·    Would the proposal reduce the safety for any public road?

·    Would the proposal reduce the safety for pedestrians or bicyclists?

·    Would the proposal reduce the safety for pedestrians, particularly children, by obscuring sightlines from public areas?

Council’s Technical Services Division advise that the two illuminated entry/exit signs located on both Bathurst Road and Eyles Street are not supported given that they have the potential to obstruct movement, obscure sightlines, or reduce the safety along the public road. Council’s Technical Services Division have recommended that such signage is removed from the plans with all directional signage required for the site to be submitted for separate approval by both Orange City Council and Transport for NSW. Conditions attached to this effect.

STATE ENVIRONMENTAL PLANNING POLICIES

The following State Environmental Planning Policies apply to the subject development:

State Environmental Planning Policy Infrastructure 2007

Clauses 101 and 104 of this SEPP are applicable to this development, and are discussed below. Concurrence with the Transport NSW (TfNSW) is required for this proposal.

 

 

101 - Development with Frontage to Classified Road

The primary objective of this clause is to ensure that new development does not compromise the effective and ongoing operation and function of classified roads. The consent authority must not grant consent to development on land that has a frontage to a classified road unless it is satisfied that:

(a)     where practicable, vehicular access to the land is provided by a road other than the classified road, and

(b)     the safety, efficiency and ongoing operation of the classified road will not be adversely affected by the development as a result of:

(i)      the design of the vehicular access to the land, or

(ii)     the emission of smoke or dust from the development, or

(iii)    the nature, volume or frequency of vehicles using the classified road to gain access to the land, and

(c)     the development is of a type that is not sensitive to traffic noise or vehicle emissions, or is appropriately located and designed, or includes measures, to ameliorate potential traffic noise or vehicle emissions within the site of the development arising from the adjacent classified road.

104 - Traffic-Generating Development

This clause applies to a takeaway food and drink premise of any size where it has direct vehicular or pedestrian access to a classified road or to a road that connects to a classified road where the access is within 90m of the connection. It requires the consent authority to give written notice of the application to the Transport NSW and take their response into consideration, as well as consider the accessibility of the site concerned, and any potential traffic safety, road congestion or parking implications of the development.

The requirements of the Transport NSW have been integrated into the notice of approval as conditions of consent, and are as follows:

·    The proposed driveway via the Mitchell Highway is to be undertaken via a left in and left out only arrangement.

·    Construction of the driveway located along the Mitchell Highway may be subject to the developer and TfNSW entering into a Works Authorisation Deed (WAD) for the developer to undertake private financing and construction of any works along the State classified road network. The WAD is to be entered into prior to the commencement of demolition works.

·    A detailed design is to be submitted by the proponent to TfNSW and Council for approval for the concrete layback driveway prior to construction. The driveway is to be designed to provide good sight lines between pedestrians and motorists, match road levels and not interfere with drainage.

·    The design is to also include relevant signage, line marking and a concrete splay or similar in the driveway along the Mitchell Highway to advise customers that all egress from the site into the Mitchell Highway is left turn only.

·    The current line marking arrangement in the shoulder of the Mitchell Highway near the proposed driveway will be subject to TfNSW concurrence as part of the detailed design process.

·    All vehicular movements to and from the site are to be undertaken in a forward movement.

·    Prior to the issuance of an Occupation Certificate, any redundant kerb layback crossing accessed along the Mitchell Highway servicing the land are to be removed and replaced with kerb and gutter to match existing kerb and gutter. Driveways are to be designed and maintained to provide good sight lines between pedestrians and motorists, match road levels and not interfere with drainage.

·    Landscaping, signage and fencing are not to impede the sight lines of traffic within or when passing, entering or departing the site. Safe Intersection Sight Distance (SISD) requirements outlined in Austroads Guide to Road Design Part 4A is to be provided in both directions at the intersection of the driveway and the Mitchell Highway.

·    It was noted there are various mature trees located along the frontage of the site, any removal of vegetation required to be undertaken to meet requirements is subject to the relevant consent and does not form part of TfNSW concurrence.

·    Any current arrangement of on-street parking along the site frontage of the Mitchell Highway is to be replaced by ‘No Stopping’ signage (R5-400) at minimum, either side of the driveway within the Mitchell Highway, by the proponent prior to occupation of the premises. Relevant and timely communication to adjoining land owners impacted as a result of this change should be managed by the consent authority.

·    Adequate turning circles, storage room and vertical clearances are to be provided within the site for the largest type of vehicle (9m) that will need to access the site during construction and operation.

·    All demolition works are to be undertaken within the bounds of the site only.

·    Prior to the commencement of construction works, the proponent is to contact TfNSW Field Traffic Manager on 1300 656 371 to determine if a Road Occupancy Licence (ROL) is required. In the event that an ROL is required, the proponent is to obtain the ROL prior to works commencing within 3m of the travel lanes in the Mitchell Highway.

·    Prior to the issue of an Occupation Certificate, all works required to facilitate the development shall be completed.

It is considered that the site has been appropriately designed to ensure that access points, car parking, queuing, loading and manoeuvring arrangements are sufficient for the proposed take away premise, and will not adversely impact on the surrounding road network, or on neighbouring properties. It should be noted that access egress to Bathurst Road will be limited to a left in left out manoeuvre meaning that traffic travelling towards Bathurst would be required to access the development via Eyles Street.


 

PROVISIONS OF ANY DRAFT ENVIRONMENTAL PLANNING INSTRUMENT THAT HAS BEEN PLACED ON EXHIBITION 4.15(1)(a)(ii)

From 31 January to 13 April 2018 the Department of Planning and Environment publically exhibited an Explanation of Intended Effect (EIE) and Draft Planning Guidelines for the proposed Remediation of Land SEPP, which will repeal and replace State Environmental Planning Policy 55 – Remediation of Land (SEPP 55). Of particular note, the Draft Planning Guidelines state:

“In undertaking an initial evaluation, a planning authority should consider whether there is any known or potential contamination on nearby or neighbouring properties, or in nearby groundwater, and whether that contamination needs to be considered in the assessment and decision making process.”

“If the planning authority knows that contamination of nearby land is present but has not yet been investigated, it may require further information from the applicant to demonstrate that the contamination on nearby land will not adversely affect the subject land having regard to the proposed use.” (Proposed Remediation of Lands SEPP - Draft Planning Guidelines, Page 10).

 

The Draft Remediation of Land SEPP is applicable to this proposal. The Draft SEPP requires in part that consideration be given to potential contamination on nearby or neighbouring properties and groundwater.

The contaminated status of adjoining lands will not impact on the proposed development.

DESIGNATED DEVELOPMENT

The proposed development is not designated development.

INTEGRATED DEVELOPMENT

The proposed development is not integrated development although concurrence was required from Transport for NSW for access in the site from a classified road.   Concurrence has been obtained from Transport for NSW (see above for details) and their requirements have been integrated as conditions of consent within the attached notice.

PROVISIONS OF ANY DEVELOPMENT CONTROL PLAN s4.15(1)(a)(iii)

Development Control Plan 2004

Development Control Plan 2004 (“the DCP”) applies to the subject land, Chapter 2 – Natural Resource Management, Chapter 8 - Development in Business Zones, Chapter 13 - Heritage, Chapter 14 - Advertising and Chapter 15 - Car Parking). An assessment of the proposed development against the relevant Planning Outcomes has been undertaken below.


 

Chapter 2 - Natural Resource Management

Section 2.1 - Water Quality

Section 2.1 - Water Quality identifies that development that concentrates, redirects flows, increases flow rates or disturbs land in close proximity to creeks has the potential to affect waterways with associated erosion, sedimentation and release of nutrients, which combine to affect downstream water quality.

Section 2.1 also identifies that development involving groundwater extraction and/or onsite wastewater disposal is deemed to affect groundwater resources.

The relevant matters have previously been addressed in detail under the headings “7.3 ‑ Stormwater” and “7.6 - Groundwater Vulnerability”.

It is considered that the requirements of the DCP have been adequately addressed by this proposal.

Section 2.2 - Soil Resources

Section 2.2 - Soil Resources identifies that soil characteristics influence land use and development capability, including the suitability for building footings, onsite waste disposal, road engineering and drainage.

Council’s Technical Services Division has recommended a condition of consent requiring that the development is to be constructed in accordance with Council’s Development and Subdivision Code. This has been included in the condition of consent.

 

Erosion and Sedimentation

The DCP sets the following Planning Outcome in regard to Erosion and Sedimentation:

·    Measures implemented during construction to ensure that the landform is stabilised and erosion is controlled.

An erosion and sediment control plan will be required in conjunction with the engineering design plans for the development. A condition is recommended in relation to this matter.

It is considered that the requirements of the DCP have been adequately addressed.

Chapter 8 - Development in Business Zones

Business Services Areas

·    Applications clearly demonstrate that the development will not detract from the role of the CBD as a regional centre.

The development is not likely to impact upon the primacy role of the CBD. This type of development is considered appropriate within the zone and will appeal to the travelling public.

·    Provision of adequate fire-safety measures and facilities for disabled persons (according to the BCA) is addressed at the application stage (relevant for all development but particularly important where converting residential buildings for business use).

Relevant conditions are attached in relation to fire-safety and disabled access. These are considerations relevant to the construction certificate stage of the development.

·    Heritage streetscapes are conserved and enhanced through adaptive reuse of heritage buildings, restrained advertising and landscaped gardens.

The development is not considered to form part of a heritage streetscape and is essentially a vacant commercial site, albeit within a high profile area of the City. The design is considered appropriate for its setting and zoning.

·    Areas on the main roads into and out of Orange (such as Molong Road and Bathurst Road) provide a high level of architectural design to enhance the visual character of the City entrances.

The site is a prominent and high profile site on the eastern entrance to the City and, as such, the architectural design of the development is of high importance.

The building is a modern design which has been designed for a specific use – Takeaway premises and is considered acceptable in terms of its visual character.

The application was supported by a detailed landscape plan.  The proposed landscaping will ensure that the development is suitably integrates well with the Bathurst Road streetscape.

·    All sites contain an element of landscaping. Landscaping provided is of a bulk, scale and height relative to buildings nearest the front property boundary so as to provide beautification and visual relief to the built form proposed or existing on the site.

 

The depth of the landscape bed at the site frontage is sufficient to accommodate the spread of plantings that meet the abovementioned outcomes but, where practicable, a minimum depth of 3m is provided. Plantings are designed to provide shade for parking areas, to break up large areas of bitumen, to enhance building preservation and to screen against noise.

A landscape plan has been submitted in support of the development. The development is considered appropriate in this regard.  The proposal includes the removal of one street tree in Eyles Street to facilitate the new access.  The Street tree is of poor quality and Council’s City Presentation Manager supports its removal subject to a number of conditions including a condition to replant the existing blister within the road reserve on the corner of Bathurst Road and Eyles Street.  A condition is recommended in relation to this matter.

Chapter 13 - Heritage

Development In The Vicinity Of Heritage Items

·    Development conforms with recognised conservation principles.

Heritage considerations have been addressed in previous sections of this report.


 

Chapter 14 - Advertisements

Advertisements

·    The location, size, colour and design of advertisement complement the character of the locality.

·    Advertisements on buildings fit within the envelope of the building.

As indicated previously in this report, the proposed signage is considered appropriate for the type of business and its location.

·    Free-standing pole or pylon signs relate to the height of associated buildings in business and industrial areas.

The applicant is proposing a pylon sign with a height of 8.3m. This is considered an appropriate height, consistent with the scale of the development and other signage within the vicinity.

High-Profile Areas

·    Business identification Signs complement the character of the locality.

As indicated previously in this report, the proposed signage is considered appropriate for the type of business and its location.

Chapter 15 - Car Parking

Off-street car parking spaces are required to be provided at the following rates for specific land uses:

Land Use

Minimum Requirements

Fast Food outlet

Development with onsite seating and drive-through facilities, the greater of:

·   One (1) space per two seats (internal seating)

·    One (1) space per three seats (internal and external seating)

 

Plus an extension area for queuing of cars for a drive-through facility is required (queue length of five (5) to twelve (12) cars measured from pick-up point). There should also be a minimum of four (4) car spaces for cars queued from the ordering point.

The submitted plans show that the development will incorporate 42 seats. The applicant has provided a total of 24 onsite spaces (including one disabled spaces and three spaces dedicated for staff parking) in compliance with the requirements of the DCP. The proposal incorporates queuing capacity for up to nine (9) vehicles including a minimum of four (4) spaces from the order point. The proposal complies with the above requirement.

Provision is to be made onsite or at a convenient location for the type of delivery or service vehicle appropriate to the type of development. Consideration is to be given to the type of vehicles that are likely to service the site. The plans show that an 8.8m delivery vehicle is able to service the development. Council’s Technical Services Division have attached a condition that the maximum size vehicle allowed within the site be 8.8m.

PROVISIONS PRESCRIBED BY THE REGULATIONS s4.15(1)(a)(iv)

Demolition of a Building (clause 92)

The proposal does not involve the demolition of a building.

Fire Safety Considerations (clause 93)

The proposal does not involve a change of building use for an existing building.

Buildings to be Upgraded (clause 94)

The proposal does not involve the rebuilding, alteration, enlargement or extension of an existing building.

BASIX Commitments (clause 97A)

BASIX is not applicable to the proposed development. A Section J energy efficiency statement will be required with the Construction Certificate application.

THE LIKELY IMPACTS OF THE DEVELOPMENT s4.15(1)(b)

Context and Setting

The context and setting of a particular area is established by taking into account the surrounding situation having regard for adjoining land-uses, scenic qualities, scale of surrounding development, previous land-use, etc.

 

The locality immediately surrounding the subject land, as well as the subject land itself is characterised as an area of mixed land uses including commercial land (i.e. the former use of the subject land as a nursery and adjacent petrol station for instance), residential land-uses and public spaces including Memory Park opposite the site.

In terms of the compatibility with adjoining residential land-uses, the development is considered acceptable. An acoustic report has been prepared that indicates the development will achieve the relevant noise criteria, subject to a number of conditions. The scale of the development is considered appropriate for the site and its zoning.

Safety and Security

The proposed development provides for passive surveillance of the street and surrounding area. The internal driveway design should ensure low speed traffic movements to facilitate pedestrian safety.

Initial discussions with NSW Police recommended that any approval should include a condition for closed-circuit television (CCTV). A condition has been included in the draft schedule of conditions.

As such, the proposed development is considered acceptable in relation to safety and security.

Residential Amenity

The proposed development adjoins residential land-uses on the southern and western boundaries and consideration of the residential amenity of these properties is critical to the assessment of the development and as such has been separated under the following headings.

Noise Impacts

The development is accompanied by an acoustic report prepared by Day Design Pty Consulting Acoustics Engineer dated December 13 March 2020. The report states that the development will meet the relevant noise criteria subject to a number of recommendations.

The recommendations from the acoustic consultant include:

·    Acoustic fences should be constructed along the west boundary of the site extending approximately 35m from the northern most point to the north building line. This section of fence shall be constructed to a minimum height of 2.4m above the ground level of the drive-thru driveway.

·    Acoustic fences shall be constructed for the remainder of the west boundary and the southern boundary to a minimum height of 1.8m above the ground level of the drive-thru driveway.

·    The plant area should be constructed from an acoustically opaque material, such as Colorbond, lapped and capped timber, masonry etc, to a height of either 1.8m above ground level of the plant area or at least 600mm above the tallest item of plant (whichever is the greater).

Council’s Environmental Health staff have reviewed the report and recommendations. The above recommendations have been addressed by appropriate conditions of consent.

 

Hours of Operation

The proposal is seeking consent to operate from Sunday to Thursday from 10am to 10pm and from 10am to 11pm on Friday and Saturday. The acoustic report indicates that the development will comply with noise requirements during these times. The proposed hours of operation are considered acceptable. A relevant condition is attached in relation to the hours of operation.

Traffic Impacts

The subject land is located adjacent to the Mitchell Highway which is a classified road. As such, Transport for NSW has the function of controlling the travels lanes of the subject road. Council’s officers have undertaken consultation with Transport for NSW in relation to vehicle access and other related traffic issues. Council has obtained concurrence of Transport for NSW (previously knowns as RMS) and their requirements have been integrated as conditions of consent within the attached notice.

It is considered that the site has been appropriately designed to ensure that access points, car parking, queuing, loading and manoeuvring arrangements are sufficient for the proposed take away premise, and will not adversely impact on the surrounding road network, or on neighbouring properties. Transport for NSW will require access/egress to Bathurst Road to be limited to a left in left out manoeuvre meaning that customers traveling south-east towards Bathurst along the Mitchell Highway will be required to access the site via the channelized right turn lane into Eyles Street with egress for those customers travelling towards Bathurst to also be via Eyles Street and Bathurst Road. The additional traffic generated by the development is not expected to have any negative impact on the local road network. Council’s Technical Services Division concur with the recommendations of Transport for NSW.

Visual Impacts

The development is not likely to present any unreasonable impacts in terms of visual amenity. The building is setback from Bathurst Road and partly screened by the existing street trees in Bathurst Road. Adequate landscaping will assist with integrating the building within the streetscape.

Public Domain

The proposal includes the removal of a street tree which is located on Eyles Street, to enable the construction of the new driveway. The removal of the street tree was supported by Council’s Manager of City Presentation.

The Manager of City Presentation also recommended that the blister within the road reserve on the corner of Bathurst Road and Eyles Street be replanted. A number of conditions have been included in the notice of determination.

The development is not likely to unreasonably impact upon any public open space and is considered acceptable.

Waste Impacts

A Waste Management Plan has been provided with the application. The proposal provides for individual storage bins. The applicant has demonstrated that a heavy rigid vehicle (HRV) can access the site and leave in a forward direction.

 

A condition of consent has been included to restrict the collection of waste to specific hours.

The application has provided no details of the manner in which litter will be suitably managed both onsite and in the surrounding street network. Attached is a condition of consent which requires the applicant to submit a litter patrol management plan for the approval of the Manager of Building and Environment prior to the issue of a construction certificate. The litter patrol management plan will be required to detail the commitments required to be undertaken by the operator of the site to suitably manage the pick-up of rubbish from the site and the surrounding street network.

Social- economic Impacts

The development has the potential to provide for positive socio-economic impacts. The development will allow additional employment during both construction and operational phases of the development.

Economic Impacts

The development has the potential to result in positive economic impacts for the City. The development will create additional competition in the Takeaway food market. The development will also generate employment during the construction phase and ongoing employment within the hospitality sector.

Cumulative Impacts

The development is not likely to present any unreasonable cumulative impacts within the locality. The acoustic assessment concludes that the development is acceptable in terms of noise. The development is also considered acceptable in terms of traffic, parking and manoeuvring and will not present any unreasonable environmental impacts within the locality.

THE SUITABILITY OF THE SITE s4.15(1)(c)

Adequate services are available to the site to facilitate the proposed development. The site is considered suitable for the proposed development.

ANY SUBMISSIONS MADE IN ACCORDANCE WITH THE ACT s4.15(1)(d)

The proposed development is defined as "advertised development" under the provisions of the LEP. The application was advertised for the prescribed period of 14 days and, at the end of that period, one submission was received in response.

Submission

The submission raised concerns about the location of the proposed driveway off Eyles Street and the potential impacts on their property due to the close proximity to their driveway.

Other concerns relate to accessing their driveway, increased traffic along a narrow street and the potential impacts of the development on their pets.

 

Figure 3 - looking towards the southern boundary of the site and the location of the proposed driveway. The existing street tree in Eyles Street will be removed to enable the construction of the new driveway.

Most of the buildings structures, including the ordering point, loading bay, main building and plant area, are located well away from the southern boundary, although it is acknowledged that the drive-thru is located in close proximity to the southern boundary.  The construction of the acoustic fence (1.8m) and landscaping along with the site’s design should minimise potential impact on adjoining residents. The submitted Environmental Noise Assessment Report prepared by Day Design states the development will meet the relevant noise criteria subject to a number of recommendations. These recommendations will be addressed by an appropriate conditions of consent.

The proposal complies with the parking provisions contained within the DCP. The proposal has provided a total of 24 onsite spaces (including one disabled spaces and three spaces dedicated for staff parking). The proposed development is not expected to have a significant impact on the existing road network.

The application was also supported by a Plan of Management which outlines Noise Management Practices, Safety and Security Management Practices and complaint handling procedures, which should ensure that if any complaints arise during the operation of the business, these complaints should be appropriately managed by the operator.  A condition is recommended in relation to this matter.

PUBLIC INTEREST s4.15(1)(e)

The proposed development is considered to be of minor interest to the wider public due to the relatively localised nature of potential impacts. The proposal is not inconsistent with any relevant policy statements, planning studies, and guidelines etc that have not been considered in this assessment.

 

SUMMARY

The proposed development is permissible with the consent of Council. The proposed development complies with the relevant aims, objectives and provisions of Orange LEP 2011 (as amended) and DCP 2004. A Section 4.15 assessment of the development indicates that the development is acceptable in this instance. Attached is a draft Notice of Approval outlining a range of conditions considered appropriate to ensure that the development proceeds in an acceptable manner.

COMMENTS

The requirements of the Environmental Health and Building Surveyor and the Engineering Development Section are included in the attached Notice of Approval.

 

Attachments

1          Notice of Approval, D20/36902

2          Plans, D20/36904

3          Submission, D20/35648

 


Planning and Development Committee                                                                  7 July 2020

Attachment 1      Notice of Approval

 

ORANGE CITY COUNCIL

 

Development Application No DA 120/2020(1)

 

NA20/                                                                     Container PR1206

 

NOTICE OF DETERMINATION

OF A DEVELOPMENT APPLICATION

issued under the Environmental Planning and Assessment Act 1979

Section 4.18

 

Development Application

 

  Applicant Name:

McDuck Properties Pty Limited

  Applicant Address:

Attention: Mr H Abbott

300 Rainbow Street

COOGEE  NSW  2023

  Owner’s Name:

Thomsons Corner Pty Limited

  Land to Be Developed:

Lot 507 DP 712206, Lots 3 and 4 DP 37362 – 52‑54 Bathurst Road, 25 and 27 Eyles Street, Orange

  Proposed Development:

Take Away Food and Drink Premises and Signage

 

 

Building Code of Australia

 building classification:

 

As determined by the Certifier

 

 

Determination made under

  Section 4.16

 

  Made On:

7 July 2020

  Determination:

CONSENT GRANTED SUBJECT TO CONDITIONS DESCRIBED BELOW:

 

 

Consent to Operate From:

8 July 2020

Consent to Lapse On:

8 July 2025

 

Terms of Approval

The reasons for the imposition of conditions are:

(1)      To ensure a quality urban design for the development which complements the surrounding environment.

(2)      To maintain neighbourhood amenity and character.

(3)      To ensure the utility services are available to the site and adequate for the development.

(4)      To prevent the proposed development having a detrimental effect on adjoining land uses.

(5)      To minimise the impact of development on the environment.

 

 

 

Conditions

(1)      The development must be carried out in accordance with:

(a)      Plans numbered: DA00 Cover Page and Location Plan,

DA01 Site Plan, DA02 Site Traffic Plan Rev: D,

DA03 Proposed Floor Plan Rev: D, DA04 Roof Plan,

DA05 Elevation Sheet No 1, DA06 Elevation Sheet No 2,

DA07 Boundary Elevations, DA08 Sections,

DA09 Signage Plan, DA10 Signage Details Sheet No 1,

DA11 Signage Details Sheet No 2, DA12 External Finishes


 

(b)      statements of environmental effects or other similar associated documents that form part of the approval

as amended in accordance with any conditions of this consent.

 

 

PRESCRIBED CONDITIONS

 

(2)      All building work must be carried out in accordance with the provisions of the Building Code of Australia.

 

(3)      A sign is to be erected in a prominent position on any site on which building work, subdivision work or demolition work is being carried out:

(a)      showing the name, address and telephone number of the principal certifying authority for the work, and

(b)      showing the name of the principal contractor (if any) for any building work and a telephone number on which that person may be contacted outside working hours, and

(c)      stating that unauthorised entry to the site is prohibited.

Any such sign is to be maintained while the building work, subdivision work or demolition work is being carried out.

 

(4)      Where any excavation work on the site extends below the level of the base of the footings of a building on adjoining land, the person having the benefit of the development consent must, at the person’s own expense:

(a)      protect and support the adjoining premises from possible damage from the excavation, and

(b)      where necessary, underpin the adjoining premises to prevent any such damage.

Note:  This condition does not apply if the person having the benefit of the development consent owns the adjoining land or the owner of the adjoining land has given consent in writing to this condition not applying.

 

 

PRIOR TO THE ISSUE OF A CONSTRUCTION CERTIFICATE

 

(5)      The colour of the all external fencing shall be ‘Windspray’ or a similar colour. Full details are to be provided prior to the release of the Construction Certificate.

 

(6)      Prior to the release of the Construction Certificate the applicant shall submit a revised signage plan indicating that all of the concrete blade signs shown on the Bathurst Road and Eyles Street vehicle entry/exits (Signs Numbered S05 and SO8) are removed.  The proposed banner sign does not form part of this consent and shall be removed from the revised signage plan.

(7)      Traffic movements into the development from Eyles Street and from the development onto Bathurst Road (Mitchell Highway SH7) shall be in accordance with the requirements of Transport for NSW (TfNSW) as articulated in their letter dated 9 June 2020. The TfNSW requirements for the development are:

·    The proposed driveway via the Mitchell Highway is to be undertaken via a left in and left out only arrangement.

·    Construction of the driveway located along the Mitchell Highway may be subject to the developer and TfNSW entering into a Works Authorisation Deed (WAD) for the developer to undertake private financing and construction of any works along the State classified road network. The WAD is to be entered into prior to the commencement of demolition works.

·    A detailed design is to be submitted by the proponent to TfNSW and Council for approval for the concrete layback driveway prior to construction. The driveway is to be designed to provide good sight lines between pedestrians and motorists, match road levels and not interfere with drainage.


 

·    The design is to also include relevant signage, line marking and a concrete splay or similar in the driveway along the Mitchell Highway to advise customers that all egress from the site into the Mitchell Highway is left turn only.

·    The current line marking arrangement in the shoulder of the Mitchell Highway near the proposed driveway will be subject to TfNSW concurrence as part of the detailed design process.

·    All vehicular movements to and from the site are to be undertaken in a forward movement.

·    Adequate turning circles, storage room and vertical clearances are to be provided within the site for the largest type of vehicle (9m) that will need to access the site during construction and operation.

Any removal of vegetation required to be undertaken to meet the above requirements is subject to the relevant consent being obtained from Orange City Council and does not form part of TfNSW concurrence.

Full details of the above requirements shall be submitted to Orange City Council and Transport for NSW for approval prior to the release of the Construction Certificate.

 

(8)      A detailed amended Landscaping Plan shall be submitted to and approved by Council’s Manager Development Assessments prior to the issue of a Construction Certificate.  The amended landscaping plan shall incorporate the following:

·    One (1) additional tree in the northern corner of the lawn area next to the plant screen. The subject trees shall have a mature height commensurate with the height buildings on the land.

·    The Landscape Plan shall be modified to include the blister within the road reserve on the corner of Eyles Street and Bathurst Road.  The amended Landscape Plan shall specify a minimum of two deciduous trees attaining a minimum height of 4m and a maximum height of 6m on maturity (due to close proximity to overhead power lines).  The trees shall have a minimum lot size of 100 litre.  Low understorey/groundcover plants shall also be incorporated into the amended Landscape Plan.

·    A replacement street tree of the same species of those existing within Eyles Street.  The tree shall be replaced at full cost by the applicant with super-advanced trees of a species nominated by Council's relevant officer.

The clearing of existing vegetation within the blister shall be the responsibility of the proponent and undertaken following Council's WHS procedures.

 

(9)      An approval under Section 68 of the Local Government Act is to be sought from Orange City Council, as the Water and Sewer Authority, for alterations to water and sewer. No plumbing and drainage is to commence until approval is granted.

 

(10)    Prior to the issue of the Construction Certificate, evidence shall be submitted to Council of the lodgement of plans with the Department of Lands and Property Information to consolidate Lots 3 and 4 in DP 37362 and Lot 507 in DP 712206 into one parcel.

 

(11)    The applicant shall prepare and submit a Litter Patrol Management Plan for the approval of the Manager of Development Assessment prior to the issue of a construction certificate. The Litter Patrol Management plan shall detail the commitments required to be undertaken by the operator of the premises to suitably manage the pick-up of rubbish from the site and the surrounding street network and open spaces.

 

(12)    Engineering plans, showing details of all proposed work and adhering to any engineering conditions of development consent, are to be submitted to, and approved by, Orange City Council or an Accredited Certifier (Categories B1, C3, C4, C6) prior to the issuing of a Construction Certificate.

 

(13)    A water and soil erosion control plan is to be submitted to Orange City Council or an Accredited Certifier (Categories B1, C3, C4, C6) for approval prior to the issuing of a Construction Certificate. The control plan is to be in accordance with the Orange City Council Development and Subdivision Code and the Landcom, Managing Urban Stormwater; Soils and Construction Handbook.


 

(14)    The development’s stormwater design is to include stormwater detention within the development, designed to limit peak outflows from the land to the pre-existing natural outflows up to the 100 year ARI frequency, with sufficient allowance in overflow spillway design capacity to safely pass flows of lower frequency (that is, a rarer event) without damage to downstream developments. Where appropriate, the spillway design capacity is to be determined in accordance with the requirements of the Dam Safety Committee.

The design of the detention storage is to be undertaken using the ILSAX/DRAINS rainfall-runoff hydrologic model or an approved equivalent capable of assessing runoff volumes and their temporal distribution as well as peak flow rates. The model is to be used to calculate the flow rates for the existing and post-development conditions. The developed flows are to be routed through the proposed storage within the model so that the outflows obtained are no greater than the flows obtained for the pre-existing natural flows. A report detailing the results of the analysis, which includes:

·    catchment plan showing sub-catchments under existing and developed conditions;

·    schematic diagram of the catchment model showing sub areas and linkages;

·    tabulation detailing the elevation, storage volume and discharge relationships; and

·    tabulation for the range of frequencies analysed, the inflows, outflows and peak storage levels for both existing and developed conditions;

together with copies of the data files for the model and engineering design plans of the required drainage system are to be submitted to Orange City Council upon application for a Construction Certificate.

The detention basin design shall allow for inundation of the site during flood events. Signage to alert users of the carpark of the risk of flooding shall be installed.

 

(15)    Engineering plans providing complete details of the proposed driveway and car parking areas are to be submitted to Orange City Council or an Accredited Certifier (Categories B1, C3, C4, C6) upon application for a Construction Certificate. These plans are to provide details of levels, cross falls of all pavements, proposed sealing materials and proposed drainage works and are to be in accordance with Orange City Council Development and Subdivision Code.

The submitted plans shall also detail modifications to the proposed parking, entrance gates and driveway to accommodate the turn path of a 9.0m heavy vehicle with a minimum 0.3m clearance to parking spaces, kerbs and other structures.

The parking layout shall be generally as per the approved plans with the following additional details:

·    Parking space dimensions shall be in accordance with AS2890.1; and

·    Parking spaces assigned to staff parking and general parking to be clearly identified by signage or line marking; and

·    All heavy vehicle servicing areas shall be clearly identified by signage or line marking; and

·    Pedestrian crossing line marking shall be installed between the front entry area and the Bathurst Road footpath; and

·    The two existing vehicle laybacks/footpath crossings in Eyles Street shall be removed and the footpath reserve reinstated; and

·    The concrete blade signs shown on the Bathurst Road and Eyles Street vehicle entry/exits shall be removed. Signage at the entry/exit points shall be limited to regulatory signage on posts as required by TfNSW.

 

(16)    A Liquid Trade Waste Application is to be submitted to Orange City Council prior to the issuing of a Construction Certificate.  The application is to be in accordance with Orange City Council’s Liquid Trade Waste Policy. Engineering plans submitted as part of the application are to show details of all proposed liquid trade waste pre-treatment systems and their connection to sewer.

Where applicable, the applicant is to enter into a Liquid Trade Waste Service Agreement with Orange City Council in accordance with the Orange City Council Liquid Trade Waste Policy.


 

(17)    Payment of contributions for water, sewer and drainage works is required to be made at the contribution rate applicable at the time that the payment is made.  The contributions are based on 0.30 ETs for water supply headworks and 2.28 ETs for sewerage headworks.  A Certificate of Compliance, from Orange City Council in accordance with the Water Management Act 2000, will be issued upon payment of the contributions.

This Certificate of Compliance is to be submitted to the Principal Certifying Authority prior to the issuing of a Construction Certificate.

 

(18)    Backflow Prevention Devices are to be installed to AS3500 and in accordance with Orange City Council Backflow Protection Guidelines. Details of the Backflow Prevention Devices are to be submitted to Orange City Council prior to the issuing of a Construction Certificate.

Certificates for testable Backflow Prevention Devices are to be submitted to Orange City Council by a plumber with backflow qualifications prior to the issue of an Occupation Certificate.

 

(19)    A Road Opening Permit in accordance with Section 138 of the Roads Act 1993 must be approved by Council prior to a Construction Certificate being issued or any intrusive works being carried out within the public road or footpath reserve.

 

(20)    The minimum floor level of the building shall be 866.75m AHD. The Construction Certificate plans shall be amended to reduce the height of the carpark to existing natural surface levels. No filling of the site shall occur below the existing 865.9m AHD contour other than the footprint of the proposed building and pedestrian access paths. All vehicle manoeuvring areas, carparks and landscaping below the existing 865.9m AHD contour shall be constructed to the existing natural ground levels.

 

(21)    Prior to the issue of a Construction Certificate, written approval shall be obtained from Telstra/NBN for any relocation or modification works to the existing telecommunications pit located in the Eyles Street vehicle crossover.

 

 

PRIOR TO WORKS COMMENCING

 

(22)    A Construction Certificate application is required to be submitted to, and issued by Council/Accredited Certifier prior to any excavation or building works being carried out onsite.

 

(23)    A temporary onsite toilet is to be provided and must remain throughout the project or until an alternative facility meeting Council’s requirements is available onsite.

 

(24)    The location and depth of the sewer junction/connection to Council’s sewerage system is to be determined to ensure that adequate fall to the sewer is available.

 

(25)    Soil erosion control measures shall be implemented on the site.

 

(26)    Prior to the commencement of construction works, the proponent is to contact TfNSW Field Traffic Manager on 1300 656 371 to determine if a Road Occupancy Licence (ROL) is required. In the event that an ROL is required, the proponent is to obtain the ROL prior to works commencing within 3m of the travel lanes in the Mitchell Highway.

 

 

DURING CONSTRUCTION/SITEWORKS

 

(27)    All construction/demolition work on the site is to be carried out between the hours of 7am and 6pm Monday to Friday inclusive, 7am to 5pm Saturdays and 8am to 5pm Sundays and Public Holidays. Written approval must be obtained from the General Manager of Orange City Council to vary these hours.

 

(28)    All materials on site or being delivered to the site are to be contained within the site. The requirements of the Protection of the Environment Operations Act 1997 are to be complied with when placing/stockpiling loose material or when disposing of waste products or during any other activities likely to pollute drains or watercourses.

(29)    No portion of the building - including footings, eaves, overhang and service pipes - shall encroach into any easement.

 

(30)    All services (water, sewer and stormwater) shall be laid outside the easement unless there is a direct connection to the main within that easement.

 

(31)    Any adjustments to existing utility services that are made necessary by this development proceeding are to be at the full cost of the developer.

 

(32)    The provisions and requirements of the Orange City Council Development and Subdivision Code are to be applied to this application and all work constructed within the development is to be in accordance with that Code.

The developer is to be entirely responsible for the provision of water, sewerage and drainage facilities capable of servicing the development from Council’s existing infrastructure. The developer is to be responsible for gaining access over adjoining land for services where necessary and easements are to be created about all water, sewer and drainage mains within and outside the lots they serve.

 

(33)    All driveway and parking areas are to be sealed with hot mix or concrete and are to be designed for all expected loading conditions (provided however that the minimum pavement depth for gravel and flush seal roadways is 200mm) and be in accordance with the Orange City Council Development and Subdivision Code. In the event that concrete is proposed a “charcoal” pigment to produce a dark grey coloured concrete finish will be required.

 

(34)    Heavy-duty concrete kerb and gutter laybacks and footpath crossings are to be constructed for the entrances to the proposed development. The location and construction of the laybacks and footpath crossings are to be as required by the Orange City Council Development and Subdivision Code, Road Opening Permit and TfNSW requirements.

 

(35)    The existing 150mm diameter sewer main that crosses the site is to be accurately located. Where the main is positioned adjacent to any proposed building work, measures are to be taken in accordance with Orange City Council Policy - Building over and/or adjacent to sewers ST009.

 

(36)    The water and sewerage services to the existing allotments, where they are not proposed to be used as part of this development, are to be sealed off at their respective Council mains.

 

(37)    The fit-out of the food preparation and storage areas are to be installed in accordance with the requirements of Food Safety Standard 3.2.3 "Food Premises and Equipment" of the Australian New Zealand Food Standards Code and Australian Standard 4674-2004 "Design and construction and fit-out of food premises".

 

(38)    In the event of an unexpected find during works such as (but not limited to) the presence of undocumented waste, odorous or stained soil, asbestos, structures such a underground storage tanks, slabs, or any contaminated or suspect material, all work on site must cease immediately. The beneficiary of the consent must discuss with Council the appropriate process that should be followed therein.  Works on site must not resume unless the express permission of the Director Development Services is obtained in writing.

 

(39)    All demolition works are to be undertaken within the bounds of the site only.

 

 

PRIOR TO THE ISSUE OF AN OCCUPATION CERTIFICATE

 

(40)    No person is to use or occupy the building or alteration that is the subject of this approval without the prior issuing of an Occupation Certificate.

 

(41)    Prior to the issuance of an Occupation Certificate, any redundant kerb layback crossing accessed along the Mitchell Highway servicing the land are to be removed and replaced with kerb and gutter to match existing kerb and gutter. Driveways are to be designed and maintained to provide good sight lines between pedestrians and motorists, match road levels and not interfere with drainage.


 

(42)    Landscaping, signage and fencing shall not to impede the sight lines of traffic within or when passing, entering or departing the site. Safe Intersection Sight Distance (SISD) requirements outlined in Austroads Guide to Road Design Part 4A is to be provided in both directions at the intersection of the driveway and the Mitchell Highway.

 

(43)    Any current arrangement of on-street parking along the site frontage of the Mitchell Highway is to be replaced by ‘No Stopping’ signage (R5-400) at minimum, either side of the driveway within the Mitchell Highway, by the proponent prior to occupation of the premises. Relevant and timely communication to adjoining land owners impacted as a result of this change should be managed by the consent authority.

 

(44)    Prior to the issue of an Occupation Certificate, all works required by Transport NSW to facilitate the development shall be completed.

 

(46)    Finished ground levels are to be graded away from the buildings and adjoining properties and must achieve natural drainage. The concentrated flows are to be dispersed down slope or collected and discharged to the stormwater drainage system.

 

(47)    The owner of the building/s must cause the Council to be given a Final Fire Safety Certificate on completion of the building in relation to essential fire or other safety measures included in the schedule attached to this approval.

 

(48)    A total of 24 off-street car parking spaces are to be provided upon the site in accordance with the approved plans and the provisions of Development Control Plan 2004. The parking spaces are to be constructed in accordance with the requirements of Council's Development and Subdivision Code, prior to the issuing of an Occupation Certificate.

 

(49)    Where Orange City Council is not the Principal Certifying Authority, a final inspection of water connection, sewer and stormwater drainage shall be undertaken by Orange City Council and a final Notice of Inspection issued, prior to the issue of either an interim or a final Occupation Certificate.

 

(50)    The cut and fill is to be retained and/or adequately battered and stabilised (within the allotment) prior to the issue of an Occupation Certificate.

Landscaping shall be installed in accordance with the approved plans and shall be permanently maintained to the satisfaction of Councils Manager Development Assessments.

 

(51)    A Certificate of Compliance, from a Qualified Engineer, stating that the stormwater detention basin complies with the approved engineering plans is to be submitted to the Principal Certifying Authority prior to the issuing of an Occupation Certificate.

 

(52)    Certification from Orange City Council is required to be submitted to the Principal Certifying Authority prior to the issue of an Occupation Certificate stating that all works relating to connection of the development to Council assets, works on public land, works on public roads, stormwater, sewer and water reticulation mains and footpaths have been carried out in accordance with the Orange City Council Development and Subdivision Code and the foregoing conditions, and that Council will take ownership of the infrastructure assets.

 

(53)    A Road Opening Permit Certificate of Compliance is to be issued for the works by Council prior to any Occupation/Final Certificate being issued for the development.

 

(54)    Prior to the issue of an Occupation Certificate Lot 507 DP 712206, and Lots 3 and 4 DP 37362 shall be consolidated. An easement, to drain sewage and to provide Council access for maintenance of sewerage works, a minimum of 2.0m wide is to be created over the existing sewer main. Evidence that the lots have been consolidated and the sewer easement has been registered shall be submitted to the Principal Certifying Authority prior to issuing of an Occupation Certificate.

 

(55)    Certificates for testable Backflow Prevention Devices are to be submitted to Orange City Council by a plumber with backflow qualifications prior to the issue of an Occupation Certificate.


 

(56)    Acoustic fences are to be constructed along the western boundary of the site extending approximately 35m from the northern most point of the northern building line.  This section of fence shall be constructed of lapped and capped hardwood fencing (excluding post and rails) to a minimum height of 2.4m above ground level of the drive-thru driveway. Acoustic fences shall be constructed for the remainder of the western and southern boundaries to a minimum height of 1.8m above the ground level of the drive-thru driveway, in accordance with the Environmental Noise Assessment Report 6934-1.1R, prepared by Day Design Pty Ltd.

 

(57)    The plant area is to be constructed from an acoustically opaque material, such as Colorbond, lapped and capped timber, masonry etc, to a height of either 1.8m above ground level of the plant area or at least 600mm above the tallest item of plant, whichever is the greater, in accordance with the Environmental Noise Assessment Report 6934-1.1R, prepared by Day Design Pty Ltd.

 

(58)    The total sound power level of plant installed within the plant area shall not exceed 76 dBA, and the total sound power level for all rooftop plant shall not exceed 85 dBA, in accordance with the Environmental Noise Assessment Report 6934-1.1R, prepared by Day Design Pty Ltd.

 

(59)    All of the foregoing conditions are to be at the full cost of the developer and to the requirements and standards of the Orange City Council Development and Subdivision Code, unless specifically stated otherwise. All work required by the foregoing conditions is to be completed prior to the issuing of an Occupation Certificate, unless stated otherwise.

 

 

MATTERS FOR THE ONGOING PERFORMANCE AND OPERATION OF THE DEVELOPMENT

(60)    The proposed floodlighting of the premises is to be designed, positioned, and installed, including appropriate shielding and orientation of the lighting fixture, as to not give rise to obtrusive light, interfere with traffic safety or detract from the amenity of surrounding properties in accordance with Australian Standard 4282:1997 - Control of the obtrusive effects of outdoor lighting. 

(61)    An assessment of noise emissions from the premises is to be provided to Council within three months from the issue of any Occupation Certificate. This commissioning report is to indicate noise levels through the monitoring of noise emanating from the normal peak use of the premises and determine if any necessary noise mitigation measures are required.  Any identified mitigation works shall be carried out within one month of the commissioning report, and the operation of the premises shall be carried out in accordance with any recommendations set out in the report.

(62)    Truck deliveries to the site are to occur only between the hours of 7am and 6pm.

(63)    Without the prior approval of Council, the hours of operation of the premises are not to exceed Sunday to Monday 10am to 10pm and from 10am to 11pm on Friday and Saturday.

(64)    Restaurant seating shall be no greater than 42 seats.

(65)    The operational controls contained within the approved Litter Patrol Management Plan and the Plan of Management must be complied with at all times.

(66)    A closed circuit television system (CCTV), incorporating digital video surveillance cameras and recorders, being installed and maintained on the premises and car parking area and to be operated during trading hours. The video surveillance cameras are also to continue recording for 30 minutes after closure of the premises.

 

 

Other Approvals

(1)      Local Government Act 1993 approvals granted under Section 68.

          Nil

(2)      General terms of other approvals integrated as part of this consent.

          Nil

 

 


 

 

 

Right of Appeal

 

If you are dissatisfied with this decision, Section 8.7 of the Environmental Planning and Assessment Act 1979 gives you the right to appeal to the Land and Environment Court. Pursuant to Section 8.10, an applicant may only appeal within 6 months after the date the decision is notified.

 

 

  Disability Discrimination Act 1992:

This application has been assessed in accordance with the Environmental Planning and Assessment Act 1979. No guarantee is given that the proposal complies with the Disability Discrimination Act 1992.

 

The applicant/owner is responsible to ensure compliance with this and other anti-discrimination legislation.

 

The Disability Discrimination Act covers disabilities not catered for in the minimum standards called up in the Building Code of Australia which references AS1428.1 - "Design for Access and Mobility". AS1428 Parts 2, 3 and 4 provides the most comprehensive technical guidance under the Disability Discrimination Act currently available in Australia.

 

 

  Disclaimer - S88B of the Conveyancing Act 1919 - Restrictions on the Use of Land:

The applicant should note that there could be covenants in favour of persons other than Council restricting what may be built or done upon the subject land. The applicant is advised to check the position before commencing any work.

 

 

Signed:

On behalf of the consent authority ORANGE CITY COUNCIL

 

 

Signature:

 

 

Name:

 

PAUL JOHNSTON - MANAGER DEVELOPMENT ASSESSMENTS

 

Date:

 

8 July 2020

 


Planning and Development Committee                                                                                  7 July 2020

Attachment 2      Plans

PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator


PDF Creator




Planning and Development Committee                                                                                 7 July 2020

Attachment 3      Submission

PDF Creator 



[1]    Asbestos Management Plans are very common, particularly for buildings the same era as Caldwell House.

[2]    Embodied Energy is the total amount of energy expended in all the processes of constructing a building including: the energy used in manufacturing all of materials used in the building, the energy used in transporting the materials, the energy used to build the building; and the energy used to demolish and dispose of the building at the end of its lifecycle.

      NB: embodied energy does not include the energy used to operate the building over its life-cycle (Dixit et. al 2010).

[3]    The highest and best use of the property as a commercial use that could complement the new DPI building for example would only be permissible with the heritage items remaining on the land and an applicant utilising the incentives clause under the LEP.