Infrastructure Policy Committee
Agenda
2 April 2019
Notice is hereby given, in accordance with the provisions of the Local Government Act 1993 that a Infrastructure Policy Committee meeting of ORANGE CITY COUNCIL will be held in the Council Chamber, Civic Centre, Byng Street, Orange on Tuesday, 2 April 2019.
Garry Styles
General Manager
For apologies please contact Administration on 6393 8218.
Infrastructure Policy Committee 2 April 2019
2.1 Minutes of the Airport Community Committee Meeting - 6 March 2019
2.2 Minutes of the City of Orange Traffic Committee meeting - 12 March 2019
1 Introduction
1.1 Declaration of pecuniary interests, significant non-pecuniary interests and less than significant non-pecuniary interests
The provisions of Chapter 14 of the Local Government Act, 1993 (the Act) regulate the way in which Councillors and designated staff of Council conduct themselves to ensure that there is no conflict between their private interests and their public role.
The Act prescribes that where a member of Council (or a Committee of Council) has a direct or indirect financial (pecuniary) interest in a matter to be considered at a meeting of the Council (or Committee), that interest must be disclosed as soon as practicable after the start of the meeting and the reasons given for declaring such interest.
As members are aware, the provisions of the Local Government Act restrict any member who has declared a pecuniary interest in any matter from participating in the discussion or voting on that matter, and requires that member to vacate the Chamber.
Council’s Code of Conduct provides that if members have a non-pecuniary conflict of interest, the nature of the conflict must be disclosed. The Code of Conduct also provides for a number of ways in which a member may manage non pecuniary conflicts of interest.
Recommendation It is recommended that Committee Members now disclose any conflicts of interest in matters under consideration by the Infrastructure Policy Committee at this meeting. |
RECORD NUMBER: 2019/534
AUTHOR: Ian Greenham, Director Technical Services
EXECUTIVE Summary
The Airport Community Committee met on 6 March 2019 and the recommendations from that meeting are presented to the Infrastructure Policy Committee for adoption.
Link To Delivery/OPerational Plan
The recommendation in this report relates to the Delivery/Operational Plan strategy “13.1 Prosper - Support public and private rail, coach and air services”.
Financial Implications
Nil
Policy and Governance Implications
Nil
That Council resolves to acknowledge the reports presented to the Airport Community Committee at its meeting of 6 March 2019.
|
further considerations
Consideration has been given to the recommendation’s impact on Council’s service delivery; image and reputation; political; environmental; health and safety; employees; stakeholders and project management; and no further implications or risks have been identified.
Attachments
1 Minutes of the Meeting of the Airport Community Committee held on 6 March 2019
2 ACC 6 March 2019 Agenda, D19/19086⇩
ORANGE CITY COUNCIL
MINUTES OF THE
Airport Community Committee
HELD IN Orange Airport, Aerodrome Road, Orange
ON 6 March 2019
COMMENCING AT 5.00pm
Attendance
Cr T Mileto (Chairperson), Cr J McRae, Mr Rohan Williams, Mr Robert Alford, Mrs Anne Salter, Mr John Pullen, Mr Brian Wood, Mr Todd Bryant, Manager Depot, Airport & Emergency Services, Airport Supervisor, Cr S Romano (5.30pm – 5.57pm)
1.1 Apologies and Leave of Absence
RESOLVED Mr R Alford/Mr J Pullen That the apologies be accepted from Mr Andrew Richards, Mr Jason Vials and Mr Michael Seccombe for the Airport Community Committee meeting on 6 March 2019. |
1.3 Declaration of pecuniary interests, significant non-pecuniary interests and less than significant non-pecuniary interests
3 General Reports
TRIM Reference: 2019/407 |
Recommendation Mr R Williams/Mr J Pullen That the information provided in the report on Orange Airport Documents be acknowledged.
|
TRIM Reference: 2019/400 |
That the Airport Community Committee Action Plan be reviewed and updated.
|
4 General BUSINESS
There was discussion on the following topics:
o Report of dull runway lights. Will get them checked
o Security cameras with number plate recognition
o Signage Airport - Welcome to Orange City Council
o Cottage demolition – slash grass
o Roads to airport need tidying up – upgrades in Delivery Plan?
**Cr Romano arrived at the meeting with the time being 5.30pm
o Cabinets in terminal – costings. John Pullen to provide information on Aero Club cabinets
**Cr Romano left the meeting with the time being 5.57pm
o Farming airside – hay making
o Parking upgrade in 2019/2020 Delivery Plan
o Helipads
o Wifi in terminal
o Tim will update the Action Plan
The Meeting Closed at 6.20PM.
Infrastructure Policy Committee 2 April 2019
2.1 Minutes of the Airport Community Committee Meeting - 6 March 2019
Attachment 1 ACC 6 March 2019 Agenda
RECORD NUMBER: 2019/549
AUTHOR: Ian Greenham, Director Technical Services
EXECUTIVE SUMMARY
The City of Orange Traffic Committee held a meeting on 12 March 2019 and the recommendations from that meeting are presented to the Infrastructure Policy Committee for adoption.
Link To Delivery/OPerational Plan
The recommendation in this report relates to the Delivery/Operational Plan strategy “9.1 Preserve - Construct and maintain a road network meets the community’s transport and infrastructure needs”.
Financial Implications
The recommendations will be funded from the signs budget.
Policy and Governance Implications
Nil
That Council resolves: 1 To acknowledge the reports presented to the City of Orange Traffic Committee at its meeting of 12 March 2019. 2 Recommendations 3.1 and 3.3 to 3.6 from the minutes of the City of Orange Traffic Committee meeting of 12 March 2019 being: 3.1 That Council changes the give way sign at the Cameron Place intersection as per the layout in Figure 1 to give priority to the main section of Cameron Place over the cul-de-sac section; 3.3 That Council requests the police to continue to monitor the intersection of Glenroi Avenue and Mitchell Highway; 3.4 That Council informs the writer that the speed limit on this stretch of Leeds Parade will be reduced to 70kph and the guard rail will not be extended; 3.5 That Council approves the amended conditional approval for the Newcrest Orange Challenge event on 30 and 31 March 2019; 3.6 That the school bus zone outside Canobolas Public School be located at the location shown in Annexure 1 of this report.
|
further considerations
Consideration has been given to the recommendation’s impact on Council’s service delivery; image and reputation; political; environmental; health and safety; employees; stakeholders and project management; and no further implications or risks have been identified.
Attachments
1 Minutes of the Meeting of the City of Orange Traffic Committee held on 12 March 2019
2 COTC - 12 March 2019 - Agenda, D19/19085⇩
ORANGE CITY COUNCIL
MINUTES OF THE
City of Orange Traffic Committee
HELD IN Committee Room 3, Civic Centre, Byng Street, Orange
ON 12 March 2019
COMMENCING AT 9.30am
1 Introduction
Attendance
Manager Engineering Services (Chairperson), Mr David Vant, Chief Inspector David Harvey, Ms Angie Drooger (RMS), Strategic Planning and Design Engineer, Road Safety Officer, Works Manager, , Divisional Administration Officer
1.1 Apologies and Leave of Absence
RESOLVED Mr D Vant/Chief Insp D Harvey That the apologies be accepted from Cr R Turner, Sgt Mark Hevers and Mr Geoff Lewis for the City of Orange Traffic Committee meeting on 12 March 2019. |
1.2 Acknowledgement of Country
1.3 Declaration of pecuniary interests, significant non-pecuniary interests and less than significant non-pecuniary interests
Nil
2 Previous Minutes
RESOLVED Mr D Vant/Chief Insp D Harvey That the Minutes of the Meeting of the City of Orange Traffic Committee held on 12 February 2019 (copies of which were circulated to all members) be and are hereby confirmed as a true and accurate record of the proceedings of the City of Orange Traffic Committee meeting held on 12 February 2019 with the addition of the attendance at the meeting of Cr Mileto. |
3 General Reports
TRIM Reference: 2019/450 |
Recommendation Mr D Vant/ Chief Insp D Harvey That Council requests the police to continue to monitor the intersection of Glenroi Avenue and Mitchell Highway.
|
TRIM Reference: 2019/464 |
Recommendation Chief Insp D Harvey /Mr D Vant That Council approves the amended conditional approval for the Newcrest Orange Challenge event on 30 and 31 March 2019.
|
TRIM Reference: 2019/469 |
Recommendation Mr D Vant/ Chief Insp D Harvey That the school bus zone outside Canobolas Public School be located at the location shown in Annexure 1 of this report.
|
4 General BUSINESS
3.2 ANSON STREET SCHOOL 50KPH SPEED ZONE IN LORDS PLACE
The Committee decided that the request for a 40kph speed limit in Lords Place behind Anson Street School should be forwarded to Roads and Maritime Services.
PEDESTRIAN SAFETY – SEYMOUR STREET / MARCH STREET
The Road Safety Officer reported that she had made observations of pedestrian movements in March Street adjacent to Seymour Street as requested by the Committee from its meeting in June 2018. Observations were made before and after school times and only six pedestrians crossed in this area.
The Committee decided there was no need for any pedestrian facility.
The Meeting Closed at 9.59AM.
Infrastructure Policy Committee 2 April 2019
2.2 Minutes of the City of Orange Traffic Committee meeting - 12 March 2019
Attachment 1 COTC - 12 March 2019 - Agenda
RECORD NUMBER: 2019/578
AUTHOR: Ian Greenham, Director Technical Services
EXECUTIVE Summary
The purpose of this report is to update Council on construction and maintenance works which have been carried out since the last current works report to Council.
Link To Delivery/OPerational Plan
The recommendation in this report relates to the Delivery/Operational Plan strategy “9.1 Preserve - Construct and maintain a road network meets the community’s transport and infrastructure needs”.
Financial Implications
Nil
Policy and Governance Implications
Nil
That Council resolves to note the report on Current Works.
|
further considerations
Consideration has been given to the recommendation’s impact on Council’s service delivery; image and reputation; political; environmental; health and safety; employees; stakeholders and project management; and no further implications or risks have been identified.
SUPPORTING INFORMATION
Road Maintenance
Road maintenance in the form of routine pothole patching was undertaken across the City by both the mechanical jet patching unit and by hand with Council’s asphalt patching crew.
Road Upgrading
Cargo Road
Kerb and gutter has now been laid in the lower section at the Ploughmans Lane end of the work. Crews also began on the pavement formation at the Witton Place intersection.
Forest Road - Bloomfield
Undergrounding of an overhead electrical line outside the hospital was undertaken. This will allow for the installation of the last of the new street lighting in this area.
Road Resealing
Road resealing activities were recently undertaken in:
· Bonanza Place
· Dalton Street
· Clancy’s Drive
· Icely Road
· Gallipoli Place
· Hampden Avenue
· National Avenue
· Maple Avenue
· Yarawini Drive
· Baker Street
· Callawa Street
· Calton Road
· Forest Road
· Hill Street
· McNeilly Avenue
· Pines Lane
· Torulosa Way.
Traffic Facilities
Raised Platform at Anson Street and Matthews Avenue
Tactile indicators for the visually impaired were installed at the pedestrian crossing points for each leg.
Anson Street and Moulder Street Roundabout
Urgent repair works were undertaken on sections of kerb on the inner island after some had broken away and become obstructions in the travelling lanes.
Woodward and Wentworth Street Roundabout
Council crews have poured the eastern kerbs for the roundabout and placed the lean mix concrete sub base for the majority of the eastern half.
Photo: Roundabout site following excavation
Photo: Machine formed kerb and gutter being placed on a lean mix concrete base
CONCRETE AND DRAINAGE
Footpath construction
Works were undertaken on concrete footpath construction in the North Orange area.
Specifically:
· Glasson Drive
· Molloy Drive
· Hallaran Way.
Drainage maintenance
Council staff engaged a specialist root cutting contractor to clear drainage lines on the Mitchell Highway at the Byng Street traffic lights. The contractor was successful in clearing the line, thus avoiding costly and inconvenient excavation and replacement works.
Photo: Specialist root cutting head that can clear pipes up to 600mm diameter using high-pressure water and a rotating flail cutter.
WATER SUPPLY SERVICES
The type and number of water supply service responses by maintenance staff are shown in the table below.
Category |
July 2017 – June 2018 |
February 2019 |
Leaking meters |
422 |
26 |
Faulty meters (incorrect readings) |
133 |
0 |
No supply |
72 |
4 |
Water pressure complaints |
24 |
1 |
Meter box/lid replacements |
57 |
5 |
Water quality |
46 |
7 |
Service break |
9 |
0 |
Service leak |
36 |
1 |
Main break |
63 |
4 |
Main leak |
311 |
15 |
Valve leak |
23 |
0 |
Hydrant leak |
90 |
7 |
Total Water Requests |
1286 |
70 |
Private Works Orders
· Installation of a 20mm diameter water service at 110B Clinton Street.
Water Construction Work
· Works are currently progressing on the installation of a 100mm diameter water main around the Lake Canobolas precinct. Currently 1,500m of water main has been installed as well as a 40,000L water storage tank. Council has also gained approval from NSW Fisheries to construct a flow monitoring weir in order to monitor any seepage from Lake Canobolas.
· Council has undertaken the repair of the 300mm diameter water main on Woodward Street. An 8 metre section of pipe was replaced and the road was reconstructed with resurfacing to be undertaken on the week of the 25 March 2019. Council staff are currently assessing the condition of the 300mm water main with a view to including its renewal in future works programs.
· Council has renewed the 300mm water main that is under the proposed roundabout at the intersection of Woodward Street and Wentworth Lane. The water main was renewed with a 300mm diameter ductile iron cement lined (DICL) pipe to ensure pipe integrity.
SEWER SERVICES
The type and number of sewer service responses by maintenance staff are shown in the table below.
Category |
July 2017 – June 2018 |
February 2019 |
Sewer blockages |
391 |
34 |
Odour |
21 |
2 |
Overflows |
140 |
11 |
Total Sewer Requests |
552 |
47 |
Sewer Construction Works
· Council’s sewer main relining contractor (Interflow) has completed all relining works with sewer junction renewals expected to be completed by the end of April 2019.
· Completion of sewer construction works – Astill Court.
Sewer Reconstructions
· Sewer main repairs – 9 Autumn Street.
WATER SUPPLY SECURITY
Water Storage Levels
The combined storage of Suma Park and Spring Creek Dams is currently 41.2%. Water storage trends for the combined storages since October 2016 are shown in the graph below.
Location |
Date |
Level Below Spillway (mm) |
% of Capacity |
Suma Park Dam |
15 March 2019 |
10518 |
34.3 |
Spring Creek Dam |
15 March 2019 |
1415 |
70.5 |
Lake Canobolas |
15 March 2019 |
1463 |
61.5 |
Gosling Creek Dam |
15 March 2019 |
1750 |
53.7 |
Supplementary Raw Water Sources
Extractions from the supplementary raw water supplies in recent months are provided in the table below.
Raw Water Source |
December 2018 (ML) |
January 2019 (ML) |
February 2019 (ML) |
Total (ML) 2018/2019 |
Bores* |
11.19 |
7.84 |
10.91 |
87.18 |
Stormwater |
77.87 |
43.58 |
36.10 |
504.96 |
Macquarie River |
89.07 |
155.33 |
5.43 |
432.37 |
Total |
178.13 |
206.75 |
52.44 |
1024.51 |
* Bores include two at Clifton Grove and one at the Showground
A more detailed monthly summary of raw water transfers can be found on Council’s website at https://www.orange.nsw.gov.au/water/oranges-water-supply/.
The Decision Support Tool (DST) analysis has been completed for the third quarter 2018/19, with continuing dry conditions requiring that all available supplementary raw water sources continue to be operated.
Macquarie River Flows
The flows in the Macquarie River monitored downstream of Long Point (Station 421192) did not exceed the flow rate trigger of 119 ML/d for the period of 20 February to 19 March.
The chart below was sourced from the WaterNSW website with flows presented in megalitres per day (ML/d).
Water Consumption
Average daily residential water consumption during the week ending 14 March 2019 was 252 litres per person per day. The target under Level 3 water restrictions is 220 litres per person per day. The graph below shows the average daily residential water consumption trends since April 2018.
The average daily city-wide water consumption for the period between 16 February 2019 and 16 March 2019 was 15.5 ML/day.
Water Restrictions
Residents are currently on Level 3 water restrictions.
Projecting forward and assuming no inflows (i.e. a worst case supply curve) and based on the current water demand, modelling has predicted that Council may need to implement Level 4 water restrictions in early April i.e. when the combined Suma Park and Spring Creek Dams water storage drops below 40% (currently at 41.2%).
Level 4 residential water restriction details are summarised in the table below.
AREA |
RESTRICTION |
GARDENS |
Garden beds, trees and shrubs may be watered with micro-sprays, drip systems and soaker hoses, (or hand held hoses for a maximum of half hour – subject to notice of motion) only between 4pm–6pm Wednesdays and Sundays (daylight savings times: 6pm - 8pm). |
LAWNS |
Not permitted (including watering of new turf). |
WALLS & PAVED AREAS |
Not permitted |
MOTOR VEHICLES |
Washing vehicles at home is permitted any day between 9am-12noon. Vehicles must be washed on the lawn using a bucket (or trigger hose – subject to notice of motion). |
SWIMMING POOLS & EXTERNAL SPAS |
Topping up of swimming pools and external spas is allowed Any day between 7am-9am and between 8pm-10pm provided pool covers are used. First fill of private pools only with Council permission and adherence to special conditions. |
Ploughmans Valley / North Orange Dual Water Scheme |
Restrictions also apply to the purple pipe system where connected |
Council’s communications team will be commencing an intensive community awareness program focusing on the future implementation of Level 4 water restrictions. This will also include information about dam levels, water consumption and water saving ideas. The residential water use target for Level 4 water restrictions is 200 litres per person per day.
Level 5 water restrictions are to be implemented when the combined Spring Creek and Suma Park Dams water storage drops below 35%
Non-residential water use
Council staff will also be engaging with large water use businesses in order to develop Water Savings Action Plans (WSAP’s). Non-residential water consumers have an important role to play in conserving Orange’s water and reducing the likelihood that greater restrictions will be introduced. Council has developed a tool to assist non-residential users in assessing their current water use levels and implementing changes that can be made to improve their water efficiencies. Potential benefits of completing a WSAP include:
· Improved management of water consumption resulting in reduced water-related costs;
· Change in staff behaviour and strengthened reputation;
· Development of a plan for the continuity of activities, where appropriate, in times of drought;
· Support of broad community efforts in reducing the likelihood that greater restrictions are introduced in the future.
DRINKING WATER QUALITY
Water samples are collected as a component of Orange City Council’s Drinking Water Quality Monitoring Program in accordance with NSW Health requirements. Samples are collected regularly and sent to a NSW Government National Association of Testing Authorities (NATA) accredited laboratory for analysis. Samples collected in February 2019 complied with the Australian Drinking Water Guidelines.
CENTRAL TABLELANDS REGIONAL WATER SECURITY PROJECT – Orange To Carcoar Pipeline
Practical completion for the Orange to Carcoar line was given to the contractor Leed Engineering on 30 November 2018. Minor rectifications have been occurring since, such as the provision of updated works as executed plans and manuals.
There is a 300m section of pipeline that remains to be undertaken along trunk main A in the Central Tablelands Water (CTW) area which CTW indicated that they would like to do themselves. CTW have advised that this work will be completed by then end of April.
As the project has come in significantly under budget there are a few minor improvements that both CTW and Orange are including that were left out in the design stages when it was assumed funding may be insufficient to fully complete the project.
A request has been made to Infrastructure NSW to allow surplus grant funds to be used on other projects within each local government area where there is a nexus to regional water supply. To date INSW have not made a decision on this matter.
EUCHAREENA ROAD RESOURCE RECOVERY CENTRE LANDFILL STAGE 3 (ERRRC)
The construction of the Euchareena Road Resource Recovery Centre (ERRRC) is progressing well. The aggregate drainage layer is in place and the welding of HDPE drainage pipes is well underway.
The connection to the existing cell two however, has presented some problems resulting in the contractor having to take extra precautions when excavating into existing waste. This and other minor scope changes is likely to see the completion of the project delayed by approximately one week. Practical Completion is expected to be given in the week beginning 1 April 2019.
Photo: HDPE pipes being placed within the aggregate drainage layer.
Decommissioning of Dam off Hawkes Lane
The decommissioning of the dam and conversion into a detention basin is anticipated being finished the week beginning 1 April 2019. To date the spillway has been completed and all drainage pipes are in place.
On surveying the empty dam the extent of earth works was noted to be larger than assumed in the original design. New grade lines have now been established with the intent of ensuring the dam remains dry and minimising earthworks.
Remaining works include, completing the bulk earthworks, trimming of the dam walls, planting and hydro seeding.
Photo: Completed spillway and drainage swale prior to hydro seeding.
Southern Feeder Road CONSTRUCTION
Work to date includes the clearing of the site, the commencement of the placement of fill material and the commencement of drainage structures.
A significant amount of unsuitable material (saturated organic soil) has been removed from the site and a drainage mattress installed. The cost of this work is expected to be consistent with the preliminary sums in the contract provided for this eventuality.
Photo: View of SFR construction looking east taken 11 March 2019
AIRPORT PASSENGER NUMBERS
Passenger numbers for February 2019 were 6,387 compared with 5,639 in the same month in 2018.
Airport Energy Usage
Energy used at the airport during February 2019 was 19,914.92 kWh at a cost to Council of $5,420.09.
ENERGY USE
The following information is sourced from E21, Council’s energy software.