Infrastructure Policy Committee

 

Agenda

 

2 July 2019

 

 

Notice is hereby given, in accordance with the provisions of the Local Government Act 1993 that a Infrastructure Policy Committee meeting of ORANGE CITY COUNCIL will be held in the Council Chamber, Civic Centre, Byng Street, Orange on Tuesday, 2 July 2019.

 

 

David Waddell

Acting General Manager

 

For apologies please contact Administration on 6393 8218.

  

 


Infrastructure Policy Committee                                                                   2 July 2019

Agenda

  

1                Introduction.. 3

1.1            Declaration of pecuniary interests, significant non-pecuniary interests and less than significant non-pecuniary interests. 3

2                Committee Minutes. 5

2.1            Minutes of the City of Orange Traffic Committee meeting - 11 June 2019. 5

3                General Reports. 40

3.1            Current Works. 40

 


Infrastructure Policy Committee                                                                   2 July 2019

 

1       Introduction

1.1     Declaration of pecuniary interests, significant non-pecuniary interests and less than significant non-pecuniary interests

The provisions of Chapter 14 of the Local Government Act, 1993 (the Act) regulate the way in which Councillors and designated staff of Council conduct themselves to ensure that there is no conflict between their private interests and their public role.

The Act prescribes that where a member of Council (or a Committee of Council) has a direct or indirect financial (pecuniary) interest in a matter to be considered at a meeting of the Council (or Committee), that interest must be disclosed as soon as practicable after the start of the meeting and the reasons given for declaring such interest.

As members are aware, the provisions of the Local Government Act restrict any member who has declared a pecuniary interest in any matter from participating in the discussion or voting on that matter, and requires that member to vacate the Chamber.

Council’s Code of Conduct provides that if members have a non-pecuniary conflict of interest, the nature of the conflict must be disclosed. The Code of Conduct also provides for a number of ways in which a member may manage non pecuniary conflicts of interest.

Recommendation

It is recommended that Committee Members now disclose any conflicts of interest in matters under consideration by the Infrastructure Policy Committee at this meeting.

 


Infrastructure Policy Committee                                                                  2 July 2019

 

 

2       Committee Minutes

2.1     Minutes of the City of Orange Traffic Committee meeting - 11 June 2019

RECORD NUMBER:       2019/1258

AUTHOR:                       Ian Greenham, Director Technical Services    

 

 

EXECUTIVE SUMMARY

The City of Orange Traffic Committee held a meeting on 11 June 2019 and the recommendations from that meeting are presented to the Infrastructure Policy Committee for adoption.

There was no police representative in attendance at the meeting but the minutes were subsequently endorsed by an email from the police.

Link To Delivery/OPerational Plan

The recommendation in this report relates to the Delivery/Operational Plan strategy “9.1 Preserve - Construct and maintain a road network meets the community’s transport and infrastructure needs”.

Financial Implications

The signage recommendations will be funded from the signs budget.

Policy and Governance Implications

Nil

 

Recommendation

That Council resolves:

1        To acknowledge the reports presented to the City of Orange Traffic Committee at its meeting of 11 June 2019.

2        Recommendations 3.1 to 3.3 and 3.5 and 3.6 from the minutes of the City of Orange Traffic Committee meeting of 11 June 2019 being:

3.1     That Council installs No stopping signs in Bletchington Street at the intersection of McLachlan Street as shown in Annexure A of this report;

3.2     That Council installs No Stopping signs along both sides of Hanrahan Place from the entrance to 100m from the extremity of the cul-de-sac;

3.3     That Council installs No Stopping signs on Green Lane opposite Hillcrest Avenue as per Annexure A of this report after seeking comments from the landowners fronting the proposed No Stopping zone;

3.5     That Council erects wayfinding signage to the Orange Visitors Centre as per the body of this report;

3.6     That the conditional approval for the 2019 NAIDOC march on 28 October 2019 be endorsed subject to compliance with the attached conditions.

 

further considerations

Consideration has been given to the recommendation’s impact on Council’s service delivery; image and reputation; political; environmental; health and safety; employees; stakeholders and project management; and no further implications or risks have been identified.

 

Attachments

1        Minutes of the Meeting of the City of Orange Traffic Committee held on 11 June 2019

2        COTC 11 June 2019 Agenda, D19/37281

 



ORANGE CITY COUNCIL

 

MINUTES OF THE

City of Orange Traffic Committee

HELD IN Committee Room 3, Civic Centre, Byng Street, Orange

ON 11 June 2019

COMMENCING AT 9.30am


 1      Introduction

Attendance

Cr T Mileto (Chairperson), Mr David Vant, Works Manager, Manager Engineering Services

 

1.1     Apologies and Leave of Absence

 

RECOMMENDATION

That the apology be accepted from Mr Geoff Lewis for the City of Orange Traffic Committee meeting on 11 June 2019.

1.2     Acknowledgement of Country

 

1.3     Declaration of pecuniary interests, significant non-pecuniary interests and less than significant non-pecuniary interests

Nil

 

2       Previous Minutes

RESOLVED                                                                                              Mr D Vant/Cr T Mileto

That the Minutes of the Meeting of the City of Orange Traffic Committee held on 9 April 2019 (copies of which were circulated to all members) be and are hereby confirmed as a true and accurate record of the proceedings of the City of Orange Traffic Committee meeting held on 9 April 2019.

 


 

 

3       General Reports

3.1     No stopping signs at the intersection of McLachlan Street and Bletchington Street

TRIM Reference:        2019/842

Recommendation                                                                             Mr D Vant/Cr T Mileto

That Council installs No stopping signs in Bletchington Street at the intersection of McLachlan Street as shown in Annexure A of this report

 

 

3.2     No Stopping at Hanrahan Place

TRIM Reference:        2019/941

Recommendation                                                                             Mr D Vant/Cr T Mileto

That Council installs No Stopping signs along both sides of Hanrahan Place from the entrance to 100m from the extremity of the cul-de-sac.

 

 

3.3     No Stopping in Green Lane

TRIM Reference:        2019/1054

Recommendation                                                                             Mr D Vant/Cr T Mileto

That Council installs No Stopping signs on Green Lane opposite Hillcrest Avenue as per Annexure A of this report after seeking comments from the landowners fronting the proposed No Stopping zone.

 

 

3.4     Farrell Road Potential Conflict with Entry into McDonalds and Childcare Centre

TRIM Reference:        2019/1102

Recommendation                                                                             Mr D Vant/Cr T Mileto

That Council makes no changes to Farrell Road between Saplings Childcare Centre and McDonalds.

 

 


 

 

3.5     Visitor Information Centre Directional Signage

TRIM Reference:        2019/1105

Recommendation                                                                             Mr D Vant/Cr T Mileto

That Council erects wayfinding signage to the Orange Visitors Centre as per the body of this report.

 

 

3.6     2019 NAIDOC March

TRIM Reference:        2019/815

Recommendation                                                                             Mr D Vant/Cr T Mileto

That the conditional approval for the 2019 NAIDOC march on 28 October 2019 be endorsed subject to compliance with the attached conditions.

 

 

 

The Meeting Closed at 10.02AM.

 


Infrastructure Policy Committee                                                                                           2 July 2019

Attachment 1      COTC 11 June 2019 Agenda

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator


 

PDF Creator

 


Infrastructure Policy Committee                                                                  2 July 2019

 

 

3       General Reports

3.1     Current Works

RECORD NUMBER:       2019/1274

AUTHOR:                       Ian Greenham, Director Technical Services    

 

 

EXECUTIVE Summary

The purpose of this report is to update Council on construction and maintenance works which have been carried out since the last current works report to Council.

Link To Delivery/OPerational Plan

The recommendation in this report relates to the Delivery/Operational Plan strategy “9.1 Preserve - Construct and maintain a road network meets the community’s transport and infrastructure needs”.

Financial Implications

Nil

Policy and Governance Implications

Nil

 

Recommendation

That Council resolves to note the report on Current Works.

 

 

further considerations

Consideration has been given to the recommendation’s impact on Council’s service delivery; image and reputation; political; environmental; health and safety; employees; stakeholders and project management; and no further implications or risks have been identified.

SUPPORTING INFORMATION

Road Maintenance

Council’s maintenance crews continued to undertake routine proactive and reactive pothole patching throughout the City:

Council staff continued the gravel road maintenance grading and gravelling program and will work their way through the whole of the gravel road network for treatment as required.


 

Road Upgrading

Forest Road

Defects identified in recent upgrading work near Gander Road have had an initial treatment and temporary seal under warranty by the contractor.  Separate works being undertaken on the Orchard Road to Evergreen Lane portion are progressing and expected to be sealed prior to the end of June.

Burrendong Way

Council’s contractors progressed works on the upgrade of Burrendong Way, south of the Northern Distributor Road (NDR) with the road being reopened to traffic at the NDR end. All new drainage lines have been laid and road pavement construction has progressed to the stage of laying kerb and gutter.

Photo: Burrendong Way reconstruction looking South from the NDR

Cargo Road

Asphalt surfacing was laid on the full length of the Cargo Road upgrade works and extended into Witton Place and Yackerboon Place.

Traffic Facilities

Woodward and Wentworth Street Roundabout

Works on the roundabout were substantially completed at the time of writing this report with recent power pole relocations being effected by Essential Energy accredited contractors.  Remaining works include landscaping, line marking and minor concrete works.

 

Photo: Woodward Street roundabout at Wentworth Lane with concrete paving completed on the Western side.

As part of the blackspot approved treatment a pedestrian refuge was also provided on Woodward Street at Gardiner Road.

CONCRETE AND DRAINAGE

Footpath construction

Footpaths were constructed in:

·     Glasson Drive

Footpath replacements were undertaken in:

·     Sampson Street from March Street to Prince Street

·     Sampson Street from Summer Street to Byng Street

Repair of the asphalt footpath on Summer Street outside of Wontama Aged Care facility was undertaken by Council crews.

WATER SUPPLY SERVICES

The type and number of water supply service responses by maintenance staff are shown in the table below.


 

 


Category

July 2017 – June 2018

May 2019

Leaking meters

422

28

Faulty meters (incorrect readings)

133

2

No supply

72

1

Water pressure complaints

24

1

Meter box/lid replacements

57

4

Water quality

46

3

Service break

9

1

Service leak

36

8

Main break

63

1

Main leak

311

19

Valve leak

23

0

Hydrant leak

90

3

Total Water Requests

1286

71

Private Works Orders

·    160-176 Peisley Street – 25mm water service connection

·    28 Miriam Drive – 20mm water service connection.

Construction Works

·    Council staff have completed the installation of 2700 metres of 100mm diameter polyethylene (PE) water main for the reticulation network at Lake Canobolas. Works are expected to be finalised by the end of June.

·    Works have been completed for the renewal of the Moulder Street water main from Endsleigh Avenue to McLachlan Street.

·    Council has renewed the 20mm water service at 185 Clinton Street.

SEWER SERVICES

The type and number of sewer service responses by maintenance staff are shown in the table below.

 

Category

July 2017 – June 2018

May 2019

Sewer blockages

391

37

Odour

21

2

Overflows

140

14

Total Sewer Requests

552

53

Private Works Orders

·    Manhole connection for the private hospital

·    28 Miriam Drive sewer connection.

Sewer Construction Works

·    All works have been completed for the 2018/19 renewal of 150mm and 225mm diameter sewer mains. The works have seen the renewal of 3700 metres of 150mm diameter sewer main and 313 metres of 225mm diameter sewer main.

·    Council has reconstructed the sewer connection for 196 March Street

WATER SUPPLY SECURITY

Water Storage Levels

The combined storage of Suma Park and Spring Creek Dams is currently 35.33%. Water storage trends for the combined storages since October 2016 are shown in the graph below.

 

Location

Date

Level Below Spillway (mm)

% of Capacity

Suma Park Dam

17 June 2019

12218

27.56

Spring Creek Dam

17 June 2019

1520

68.59

Lake Canobolas

17 June 2019

1853

53.10

Gosling Creek Dam

17 June 2019

1811

52.29

 

 


 

Supplementary Raw Water Sources

Extractions from the supplementary raw water supplies in recent months are provided in the table below.

 

Raw Water Source

March 2019 (ML)

April 2019 (ML)

May 2019 (ML)

Total (ML) 2018/2019

Bores*

12.15

11.42

11.99

122.74

Stormwater

57.74

0.52

81.71

644.93

Macquarie River

7.60

21.29

0.00

461.26

Total

77.49

33.23

93.70

1228.93

* Bores include two at Clifton Grove and one at the Showground

A more detailed monthly summary of raw water transfers can be found on Council’s website at https://www.orange.nsw.gov.au/water/oranges-water-supply/.

The Decision Support Tool (DST) analysis has been completed for the third quarter 2018/19, with continuing dry conditions requiring that all available supplementary raw water sources continue to be operated. The next DST is planned for July 2019.

Macquarie River Flows

The flows in the Macquarie River monitored downstream of Long Point (Station 421192) did not exceed the flow rate trigger of 119 ML/d in the period of 22 May to 18 June 2019. Maximum flow rate for the period was 52.90 ML/day.

The chart below was sourced from the WaterNSW website with flows presented in megalitres per day (ML/d).

 


 

Demand Management

Water Restrictions

Level 5 water restrictions are to be implemented when the combined Spring Creek and Suma Park Dams water storage drops below 35%. A notice of motion to this meeting is proposing that the trigger level to introduce Level 5 water restrictions be changed to when the combined Spring Creek and Suma Park Dams water storage drops below 30%.

Residential water use

Residents are currently on Level 4 water restrictions.

Average daily residential water consumption during the week ending 13 June 2019 was 150 litres per person per day. The target under Level 4 water restrictions is 200 litres per person per day. The graph below shows the average daily residential water consumption trends since July 2018.

Non-residential water use

Council staff will also be engaging with large water use businesses in order to develop Water Savings Action Plans (WSAP’s). Non-residential water consumers have an important role to play in conserving Orange’s water and reducing the likelihood that greater restrictions will be introduced. Council has developed a tool to assist non-residential users in assessing their current water use levels and implementing changes that can be made to improve their water efficiencies.  Potential benefits of completing a WSAP include:

·     Improved management of water consumption resulting in reduced water-related costs;

·     Change in staff behaviour and strengthened reputation;

·     Development of a plan for the continuity of activities, where appropriate, in times of drought;

·     Support of broad community efforts in reducing the likelihood that greater restrictions are introduced in the future.

Total water use

The average daily city-wide water consumption (all users) for the period between 24 May 2019 and 13 June 2019 was 9.36 ML/day.

Council facility water audits

Council staff have undertaken water audits of its building facilities over the last month. The facilities that have been completed include:

·    Civic Centre, Library, Gallery and Museum

·    Council Works Depot

·    Orange City Council’s caravan park and showground

·    Aquatic Centre, Anzac Park Sports Stadium

·    Yarrawong and Spring Street Childcare Centres

·    Sewerage Treatment Plant

·    Giyalang Ganya Centre.

The actions identified from the audit are currently being addressed and all works are expected to be rectified within a month.

Council staff are currently undertaking further audits and improvement plans for sporting grounds, open spaces recreational areas, parks and gardens. These audits are focused around irrigation and possible improvements in water use and water sourcing.  Wade Park, Jack Brabham Park, Brendon Sturgeon Oval, Riawena Oval, Cook Park, Botanic Gardens and Adventure Playground have already been audited.

Staff are also seeking quotations to implement a water leak detection program. This program will be focused around the inspection of 556 km of water mains across the City including water services to each property.

Water meters ranging from 20mm domestic services to 100mm industrial services are also being replaced. Council has replaced approximately 1200 water meters in the 2018/19 financial year.

DRINKING WATER QUALITY

Water samples are collected as a component of Orange City Council’s Drinking Water Quality Monitoring Program in accordance with NSW Health requirements. Samples are collected regularly and sent to a NSW Government National Association of Testing Authorities (NATA) accredited laboratory for analysis. Samples collected in May 2019 complied with the Australian Drinking Water Guidelines.

EUCHAREENA ROAD RESOURCE RECOVERY CENTRE LANDFILL STAGE 3 (ERRRC)

As mentioned in previous reports, the construction of the Euchareena Road Resource Recovery Centre (ERRRC) is complete.  The quality control report for the project has been submitted to the EPA for feedback.  This project was delivered within the budget estimate.

Decommissioning of Dam off Hawkes Lane

The decommissioning of Hawkes dam has been completed, including minor fencing works that were carried out by a separate fencing contractor. This project was delivered within the budget estimate.

SHIRALEE SEWER

Consultant reports, including geotechnical bore logs and a review of environmental factors, will be provided to Council in draft form this week for review and finalization.

The valuation of easements is also anticipated to be completed this week which will allow land negotiations to commence with private landholders and Transport for NSW where the pipe is proposed to transverse its land.

Approval is also required from John Holland Rail to bore under the Orange to Broken Hill railway line. Following this approval, which is anticipated to be received in mid-August, a request for tenders will be advertised.

Southern Feeder Road CONSTRUCTION STAGE 2 (SFR2)

Piling on the SFR2 is anticipated to recommence on Friday 21 June 2019.  Based on the new geotechnical information, pile length has increased from approximately three metres to 23 metres.  The impact on time and costs due the additional piling and delays is currently being evaluated, however it is anticipated that construction work will now be completed early in the new calendar year.

Southern feeder road Stage 3 (SFR3)

SFR3 is effectively an upgrade of Blowes Road and Dairy Creek Road.  The design of the SFR3 is 90% complete with the main outstanding item being the finalization of the intersection configuration at the Mitchell Highway in consultation with the Roads and Maritime Services (RMS).

It is proposed to call tenders for the SFR3 within the next few months.  In the interim, work will commence on property acquisition and the designing telecommunication and Essential Energy power assets to facilitate relocation.

AIRPORT PASSENGER NUMBERS

Passenger numbers for May 2019 were 7,620 compared with 7,073 in the same month in 2018.

 

 

Airport Energy Usage

Energy used at the airport during May 2019 was 25,734.56 kWh at a cost to Council of $7,060.97.

ENERGY USE

The following information is sourced from E21, Council’s energy software.

Monday 17 June 2019